Occupancy Approval
Occupancy approval (kolaudácia) is a procedure that checks a finished building and ends with a certificate that allows its use.
What is occupancy approval (kolaudácia)?
Occupancy approval (kolaudácia) is a procedure that checks a finished building and ends with a certificate that allows its use. The building office runs it. The certificate is the kolaudačné osvedčenie (§ 66 and 67 of zákon č. 25/2025 Z. z.).
A finished building, or a part that can be used on its own, may go into permanent use only after kolaudácia (§ 66 ods. 1). The certificate states that the building is technically fit for its designed purpose. It does not replace an operating permit under other laws (§ 67 ods. 2 and 3). The office that ran the intent proceedings issues it (§ 48 ods. 1).
The procedure has this name since 1 April 2025. The old kolaudačné konanie became kolaudácia (§ 84 ods. 11 písm. c).
When does a building need occupancy approval?
It applies to new structures, changes of completed structures and terrain modifications that needed a decision on the building intent (§ 66 ods. 1). Structures built on a notification and alterations do not need it. An alteration that comes with a change of use does need it.
A building may serve only the purpose named in the certificate (§ 68 ods. 1).
Does an extension, a superstructure or a renovation need occupancy approval?
An extension or a superstructure needs it when it needed a decision on the building intent. A renovation that stays within alterations does not (§ 66 ods. 1).
The act calls an extension (prístavba), a superstructure (nadstavba) and a built-in structure (vstavba) a change of a completed structure (§ 5 ods. 1). An extension widens the building on the plan. A superstructure adds at least one storey, attic or set-back storey (§ 5 ods. 3 and 4).
Alterations (stavebné úpravy) work on the structure of an existing building without changing the building. Examples are the renewal of the facade or the roof. Interior work that does not change the size of the building is another example (§ 2 ods. 9 písm. a). The builder must notify alterations before the work (§ 63 ods. 1).
A change of use (zmena v užívaní stavby) is a separate case. If it comes with a change of a completed structure, the office deals with it in the intent proceedings and does kolaudácia after completion. If it comes with notified alterations, the office deals with it after the alterations are finished (§ 68 ods. 3).
Which documents does the builder file?
The builder files a proposal with attachments that depend on the type of structure (§ 66 ods. 2). The act lists these attachments.
- The site diary (stavebný denník), the final statement of the site manager (stavbyvedúci) and the as-built documentation.
- Surveying documents: setting out, a control protocol on the position, a geometric plan for the cadastre and a survey of the finished structure.
- A handover protocol, which the office may waive in justified cases, and a trial operation protocol if the office permitted one.
- Test records of samples of building products taken on site and results of inspections of reserved technical equipment.
- An energy certificate, if the building must have one.
- The binding opinions and statements obtained before the filing.
- Proof of payment of the local development fee, if the municipality levied it.
The owner of a new building that must be certified has to hold the energy certificate on the day of the filing. The office may decide otherwise (§ 8 ods. 1 písm. a of zákon č. 555/2005 Z. z.). The certificate lasts at most ten years (§ 7 ods. 7).
How does the procedure run?
- The builder files the proposal (§ 66 ods. 2).
- Within 7 working days of a complete proposal, the office announces the inspection date to the builder and the affected authorities. It invites the general designer and the general contractor. For a reserved structure (vyhradená stavba), it also invites the person who carried out construction supervision and the future operator. The inspection takes place within 30 days of the announcement (§ 66 ods. 3).
- At the inspection the office checks that the structure is complete and fit for safe use under the verified project. It also checks the building technical systems, the network connections, the rainwater handling, the reserved equipment and the energy performance (§ 66 ods. 4).
- If the builder left the structure unfinished or defective, the office writes a protocol and sets a deadline to remove the defects. It interrupts the procedure meanwhile (§ 66 ods. 5). If the builder does not remove them, the office stops the procedure (§ 66 ods. 6). It also stops it when the builder departed from the verified project (§ 66 ods. 8).
- If the structure is fit for operation, the office issues the certificate within 15 days of the inspection (§ 66 ods. 7). It tells the affected authorities (§ 67 ods. 4).
The parties are the builder, the owner of the building and the owner of the land. If there are more than 20 parties, or a party is unknown, the office announces the procedure by public notice (§ 66 ods. 9).
This page describes the text in force on 1 November 2026. Amendment 243/2026 Z. z. changes it from 1 January 2027. The section "What changes on 1 January 2027?" lists the changes.
How long does occupancy approval take in total?
The act states three periods one after the other and no single total (§ 66 ods. 3 and 7). The office announces the inspection date within 7 working days of a complete proposal. The inspection takes place within 30 days of the announcement. The office issues the certificate within 15 days of the inspection.
| Step | Period | Counts from |
|---|---|---|
| Office announces the inspection date | 7 working days | Delivery of a complete proposal (§ 66 ods. 3) |
| Inspection takes place | 30 days | The announcement (§ 66 ods. 3) |
| Office issues the certificate | 15 days | The inspection (§ 66 ods. 7) |
If the inspection finds no defect, the sum is at most 7 working days plus 45 days from a complete proposal. Time to remove defects comes on top. The office sets that deadline and interrupts the procedure meanwhile (§ 66 ods. 5). The time to collect the attachments and the binding opinions comes before the filing and is not part of these periods.
What changes on 1 January 2027?
The date of promulgation of amendment 243/2026 Z. z. is 7 October 2026. Its Article I changes kolaudácia from 1 January 2027 (čl. I bod 149 to 162). The changes are these.
- Scope. The act requires kolaudácia for a new structure, a change of a completed structure, alterations and maintenance. The office must have issued a decision on the building intent for them. The list no longer names terrain modifications. The office may waive kolaudácia for notified works after which it decided that they need an intent decision (new § 66 ods. 1).
- Attachments. The final statement of the site manager leaves the list. The handover record includes the contractor's declaration that the structure matches the verified project. Official tests, expert inspections and expert tests replace the word "revisions" in the list of results for reserved technical equipment. A new attachment is proof of the builder's right to the land or the structure. It applies when the real structure differs from the intent and the builder does not own the land (čl. I bod 150 to 153).
- People. The office also invites the owner of the structure and the owner of the land when they are not the builder. Only the builder is a party. The two owners become participating persons (zúčastnená osoba) (čl. I bod 154 and 158).
- Access and induced adjustments. If they were not a condition of the permit, the office does not assess their completion when the builder shows safe use and safe access. If they were a condition, the office may waive it for kolaudácia when the builder secures safe use and access (new § 66 ods. 5). The same rule applies to kolaudácia under old permits (new § 84a ods. 5).
- The certificate. It names the main purpose and any other purposes. For a building it also names the floor area share of each purpose (new § 67 ods. 3). A stage of a structure built in stages may have its own kolaudácia (new § 67 ods. 2). The act states that no appeal lies against the certificate (new § 67 ods. 7). The office also sends notice of the certificate to affected legal persons (čl. I bod 161).
- Stopped kolaudácia. A decision to stop kolaudácia because the structure departs from the verified project also goes to the building inspectorate (čl. I bod 157).
- Offences. The separate offences of operating a building before the certificate and for another purpose go away (čl. I bod 188). The offence of using a building without the certificate or against it stays, with the verb "uses" in place of "operates". It also covers use without a permit for early use or for trial operation (čl. I bod 192).
Can a change made before completion be handled together with occupancy approval?
It depends on the permit. For a building with a territorial decision or a building permit from the old act, yes. The old rules apply to both the change before completion and the kolaudačné rozhodnutie. This holds even for an application filed after 31 March 2025 (§ 84 ods. 5 and 6). Under the old act the office may merge the proceedings on the change before completion with the kolaudačné konanie. This holds if the real construction does not depart substantially from the verified documentation (§ 81 ods. 4 of zákon č. 50/1976 Zb.). The participants of the building proceedings whom the change could affect then also become participants (§ 78 ods. 2).
Under the new act, no. Kolaudácia has no step for a change. The office checks the finished building against the verified project (§ 66 ods. 4 písm. a). If the builder built against the verified project, the office stops kolaudácia (§ 66 ods. 8). So the builder settles the change during the work, in one of the two ways below.
A deviation that does not contradict the intent decision and the conditions of the affected bodies is handled on site. On the proposal of the site manager, the designer or the construction supervisor, the builder can call an extraordinary inspection before the work. The designer marks the deviation in the project. The site manager records it in the minutes and in the site diary (§ 43 ods. 2). If the building office did not attend, the builder sends it the minutes. The office approves them within three days (§ 43 ods. 3).
If the deviation does not fit this route, the office decides that the builder needs a verification of the changed project. It may also decide that a new intent proceeding is necessary (§ 43 ods. 3). The rules for the verification of a project apply to a change of the project (§ 65 ods. 7). See change before completion.
Can a building be used before the certificate is issued?
Yes, but only with a decision of the office, for trial operation or for early use. The office decides within 30 days of the request in both cases (§ 69 ods. 3 and § 70 ods. 3).
Trial operation (skúšobná prevádzka) is temporary use of a finished building for tests and measurements. The office permits it when only operation can check the building. The owner, the builder or the contractor can ask for it (§ 69 ods. 1). The office sets the conditions and the duration. It permits at most 24 months. Extensions are possible, but the total is at most four years (§ 69 ods. 3 and 4). The builder or contractor writes a protocol that serves as a basis for kolaudácia (§ 69 ods. 5).
Early use (predčasné užívanie) is time-limited use of a building or a part of it before it is fully complete. The office may permit it if it does not endanger the completion. The part must meet the basic requirements for buildings and the general technical requirements (§ 70 ods. 1). The builder files the request. The attachments are the statements of the affected bodies and the consent of the contractor and the designer (§ 70 ods. 2). The office permits at most 12 months. Extensions are possible, but the total is at most five years (§ 70 ods. 4).
Both decisions end when the permitted time ends, or earlier when the office issues the certificate (§ 69 ods. 6 and § 70 ods. 5). Section 66 applies to both procedures by analogy (§ 69 ods. 7 and § 70 ods. 6).
What is the difference between the kolaudačné osvedčenie and the kolaudačné rozhodnutie?
The kolaudačné osvedčenie is the outcome of kolaudácia under the new act, in force since 1 April 2025. The kolaudačné rozhodnutie was the outcome under the old act (§ 76 ods. 1 and § 82 ods. 1 of zákon č. 50/1976 Zb.). The as-built documentation is attached to the certificate (§ 67 ods. 2).
| Aspect | Old regime (until 31 March 2025) | New regime (from 1 April 2025) |
|---|---|---|
| Procedure | Kolaudačné konanie | Kolaudácia |
| Outcome | Kolaudačné rozhodnutie | Kolaudačné osvedčenie |
| Notice of the inspection | At least 10 days before the oral hearing with a site inspection (§ 80 ods. 1 of zákon 50/1976) | Date announced within 7 working days of a complete proposal. Inspection within 30 days of the announcement (§ 66 ods. 3) |
What if the building has an old permit or an old approval?
If the building has a territorial decision or a building permit from the old act, the application for the kolaudačné rozhodnutie follows the old rules. This holds even when the builder files it after 31 March 2025 (§ 84 ods. 5 and 6). Proceedings begun by 31 March 2025 also end under the old rules (§ 84 ods. 4). They keep the old state fees (§ 19w of zákon 145/1995).
An approval issued under the old act, for example in 2018, stays in place. Legal relations that rest on decisions under the old rules stay (§ 84 ods. 1).
What if a building was built or used without permission?
Kolaudácia is not the route for it. The office checks a finished building against its verified project (§ 66 ods. 4 písm. a). It stops the procedure when the building contradicts that project (§ 66 ods. 8). The building inspectorate can order the owner to remove a structure or a change built by unpermitted works (§ 78 ods. 1 písm. a).
People search for this as retroactive kolaudácia (dodatočná kolaudácia). The act has no procedure with that name. The transitional rules keep two old routes open for some owners.
- The review of fitness for use (preskúmanie spôsobilosti stavby na užívanie). Old rules apply if the building meets the old conditions and the owner files by 31 March 2029 (§ 84 ods. 7 písm. a). From 1 January 2027 the date is 31 December 2040 (čl. I bod 224 of zákon č. 243/2026 Z. z.). See review of fitness for occupancy.
- The subsequent permit of a building (dodatočné povolenie stavby). Old rules apply if the building meets neither the old conditions for a lawful building nor those for the review. The owner must file from 1 April 2025 to 31 March 2029 (§ 84 ods. 7 písm. b). From 1 January 2027 the owner can file until 31 December 2040, and only for a building built by 31 March 2025 (čl. I bod 224 and 225).
What does occupancy approval cost?
The state fee for the certificate is 30% of the fee for the decision on the building intent. The rate is in položka 59 písm. e of zákon č. 145/1995 Z. z. For a single-flat or two-flat building that fee is 300 euro, so the certificate costs 90 euro. A repeated inspection costs 20%, which is 60 euro (písm. f). Electronic filing pays 50% of the fee, and the reduction is at most 50 euro (§ 6 ods. 2). Under the old rules the fee for a family house was 100 euro (položka 62a písm. a bod 1).
What happens if someone uses a building without the certificate?
Operating a building without a kolaudačné osvedčenie is an offence. The building inspectorate (stavebný inšpektorát) can impose a fine from 30 euro up to 15,000 euro (§ 79 ods. 3 písm. c, ods. 6 písm. c, ods. 8). An owner who lets another person operate the building also commits it (§ 79 ods. 3 písm. c).
Operating a building before the office issues the certificate is also an offence. The fine is from 30 euro up to 3,000 euro (§ 79 ods. 2 písm. e and ods. 6 písm. b). Using a building for another purpose than the one in the certificate is an offence too (§ 79 ods. 2 písm. d). A sole trader or a legal person who uses a building without the certificate pays more. The fine is from 10,000 euro up to 150,000 euro (§ 80 ods. 4 písm. c).
What happens after the certificate?
The building may go into permanent use for the purpose in the certificate (§ 66 ods. 1 and § 68 ods. 1). The information on the certificate and the as-built documentation go to the district office (okresný úrad), which keeps the cadastre. The administrator of the planning and construction information system sends them (§ 21 ods. 2 of zákon č. 162/1995 Z. z.).
The cadastral act sets one condition for the entry of a building: outer walls and a roof structure bound it (§ 46 ods. 2). A structure may have no house number (súpisné číslo). Then the cadastre enters the person named in the certificate as the owner, unless another document shows a different owner (§ 46 ods. 2). See cadastral registration.
Which mistakes do builders make?
The act makes these mistakes concrete.
- Using the building, or letting another person use it, before the certificate. This is an offence (§ 79 ods. 2 písm. e and ods. 3 písm. c).
- Filing an incomplete proposal. The 7 working days start only from a complete proposal, and § 66 ods. 2 lists the attachments (§ 66 ods. 3).
- Building against the verified project. The office stops kolaudácia (§ 66 ods. 8).
- Missing the deadline to remove defects. The office stops kolaudácia (§ 66 ods. 6).
- Using the building for another purpose than the one in the certificate (§ 68 ods. 1 and § 79 ods. 2 písm. d).
- Filing without an energy certificate when the building must have one (§ 66 ods. 2 písm. j).
What should the builder do?
- Check that the building needed a decision on the building intent. Notified structures and alterations need no kolaudácia (§ 66 ods. 1).
- Keep the site diary and record every deviation from the verified project (§ 43 ods. 2).
- Collect the attachments listed in § 66 ods. 2, including the as-built survey and the energy certificate if the building must have one.
- File the proposal with the office that issued the intent decision (§ 48 ods. 1 and § 66 ods. 2).
- Attend the inspection with the general designer and the general contractor, whom the office invites (§ 66 ods. 3).
- Remove any defect within the deadline of the office (§ 66 ods. 5).
- Do not use the building until you hold the certificate. Ask for trial operation or early use if you need to use it sooner (§ 69 and 70).
Frequently asked questions
- What does kolaudácia mean?
- Kolaudácia is the Slovak term for occupancy approval. The building office checks a finished building and issues a certificate, the kolaudačné osvedčenie. A finished building may go into permanent use only after it (§ 66 ods. 1 and § 67 ods. 1 of zákon 25/2025).
- Does an extension, a superstructure or a renovation need kolaudácia?
- An extension or a superstructure needs it when it needed a decision on the building intent (§ 5 ods. 1 and § 66 ods. 1). Alterations such as renewing a roof do not, unless they come with a change of use.
- How long does occupancy approval take?
- The act sets three periods and no single total. The office announces the inspection date within 7 working days of a complete proposal. It holds the inspection within 30 days of that notice. It issues the certificate within 15 days of the inspection (§ 66 ods. 3 and 7).
- Can a building be approved after the fact if it was built without permission?
- The act has no procedure called retroactive kolaudácia. Kolaudácia checks the building against its verified project (§ 66 ods. 4 písm. a). Old routes stay open for some owners who file by 31 March 2029 (§ 84 ods. 7). From 1 January 2027 the date is 31 December 2040 (čl. I bod 224 of zákon č. 243/2026 Z. z.).
- Which documents does the builder file for kolaudácia?
- The builder files a proposal with attachments that depend on the type of structure (§ 66 ods. 2). They include the site diary, the final statement of the site manager and the as-built documentation. They also include the surveying documents, the handover protocol, test records of building product samples and results of inspections of reserved technical equipment. The energy certificate is an attachment if the building must have one.
- What does occupancy approval cost?
- The state fee for a single-flat or two-flat building is 90 euro. That is 30% of 300 euro (položka 59 písm. e of zákon 145/1995, version valid from 1 September 2026). A repeated inspection costs 60 euro.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2, 5, 43, 48, 63, 65, 66, 67, 68, 69, 70, 78, 79, 80, 84
- Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon) · Slov-Lex · § 76, 78, 80, 81, 82, 88a
- Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59 písm. a, e, f, § 6 ods. 2, § 19w
- Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 62a
- Zákon č. 555/2005 Z. z. o energetickej hospodárnosti budov a o zmene a doplnení niektorých zákonov · Slov-Lex · § 7 ods. 7, § 8 ods. 1
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · čl. I bod 149 až 162, 224 až 226
- Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Slov-Lex · § 21 ods. 2, § 46 ods. 2
- Change of a Building Before Completion 2026
- Self-Building a House in Slovakia: What the Law Allows
- House Handover and Defect Claims
- Shell, Holodom or Turnkey: What You Buy
- Energy certificate and class A0: what it rates and when
- Notification or Building Permit? What Applies Now
- Construction Supervisor, Site Manager, Author Supervision
- How Building a House in Slovakia Works, Plot to Occupancy
- Occupancy Approval Step by Step + Checklist
- Building Permit 2026: Process and Deadlines