How Building a House in Slovakia Works, Plot to Occupancy

14 min read
A family house under construction at shell stage, with blockwork walls and newly erected roof trusses

Building a family house in Slovakia follows a fixed order: plot, design, decision on the building intent, project verification, construction and kolaudácia (the final inspection). This order applies from 1 April 2025, when the Building Act No. 25/2025 Z. z. took effect. The act no longer uses the terms zoning decision, building permit and occupancy decision. People still search for them, so the article gives them as old names at each step. The act sets periods for the authorities. It sets none for the design work, the choice of a contractor or the construction itself, so the article gives no total duration.

The edge of a partly cast floor slab, reinforcement mesh still exposed above timber formwork and steel props
The edge of a partly cast floor slab with reinforcement still exposed above the formwork.

What are the steps of building a family house, and which periods does the act set?

The table shows the steps in order and the periods from the text of the act. The periods are for a simple structure, which most family houses are (explained in the next section). The text used is Act 25/2025 Z. z. as in force from 1 November 2025 to 31 December 2026.

StepWho actsPeriod in the act
Plot and the right to build on itThe builderThe act sets no period
Building intent and binding opinionsThe designer, affected authorities, affected legal personsPlanning authority 30 days, other affected authorities 30 days (60 for complex structures), legal persons 30 days (at most 60)
Decision on the building intentThe building office30 days if no hearing or site visit is needed, otherwise 60 days, in set cases 90 days
Project of the building and its verificationThe designer, the building officeVerification 30 days from the application
Contractor and notice of the start of worksThe builderBefore the building works start
ConstructionThe contractor, the site managerThe decision on the building intent sets the construction period
KolaudáciaThe building officeDate of the inspection within 7 working days, inspection within 30 days of the notice of the date, certificate within 15 days of the inspection

What happened to the building permit after 1 April 2025?

Act 25/2025 Z. z. has no building permit. Under § 84 para. 11, from 1 April 2025 the territorial proceeding became the proceeding on the building intent. The building proceeding became project verification, and the occupancy proceeding became kolaudácia. Every structure therefore needs a decision on the building intent (§ 18 para. 2). A structure may be built only to a verified project of the building or on the basis of a notification (§ 25).

If the building office received your submission by 31 March 2025, or the proceeding began by that day, the previous rules apply. This is in § 84 para. 4. If you already hold a zoning decision or a building permit under the old rules, the old rules also apply. They cover the next steps you file after 31 March 2025 (§ 84 paras. 5 and 6).

A residential building is a simple structure if it meets three limits. It has at most three flats and a built-up area of at most 300 m2. It has at most two storeys above ground (§ 2 para. 6 point a). It may also have one storey below ground and an attic or set-back storey. A larger house is not a simple structure.

When is a notification enough instead of a decision?

A house does not go this route. It applies to small structures on the plot, such as sheds, garages up to 50 m2 and pools. The act requires notification for minor structures under § 2 para. 4 points a to c. For other minor structures it requires notification in several cases. These include a structure closer than 2 m to the plot boundary, a building on a fixed foundation and an underground structure (§ 18 para. 3). The office handles a notification within 30 days by verifying the project of the structure for notification. If it does not verify the project, the office is presumed to have issued the verification clause (§ 63 paras. 6 and 7). Kolaudácia is not required for notified structures (§ 66 para. 1). Details are in the article Notification or Building Permit? What Applies Now.

What should you examine on a plot before buying it?

Make sure that the plot allows what you want to build and that you will have the right to build on it. The building office reviews exactly these points when it decides. Due diligence on the plot covers mainly the following:

  • The land-use plan. Building is allowed only in line with the binding part of the spatial planning documentation (§ 21 para. 1). A building plot is the part of the territory that this documentation sets aside for development (§ 7 para. 1). You find what applies to the plot in the municipal land-use plan.
  • The right to the plot. The builder must hold ownership or another right that lets them build. A right registered in the real estate cadastre needs no further proof (§ 29 paras. 1 and 2). If the applicant has no right to the plot, the office stops the proceeding (§ 56 para. 1 point a).
  • Access and networks. The office rejects the application if the structure has no access from a public road of sufficient capacity. It also rejects it if an affected legal person states a connection problem. The problem is that the structure cannot be connected to the water main, the sewer or the electricity network. This does not apply if the structure needs no connection or the networks are out of reach (§ 59 para. 1 points e and f).

Which stages of documentation does a house need, and who prepares them?

The act knows four stages of project documentation. They are the building intent, the project of the building, the project of the building for notification and the implementation project (§ 9 para. 1). A family house needs the building intent and the project of the building. The act requires the implementation project only for a reserved structure (§ 9 para. 5). An architectural study is not in the act. It is an agreement between you and the architect. The article From Study to Implementation Project covers the content of each stage.

The builder gives the designer a technical brief that describes the purpose, operation and scope of the structure (§ 30 para. 1). Unless agreed otherwise with the designer, the builder arranges the land surveyor. The builder also arranges the geological and other surveys (§ 30 para. 2 points a and b). The designer is responsible for two things. The building intent must meet the builder's requirements. The project of the building must follow the decision on the building intent (§ 35 para. 6 points a and b).

How does the proceeding on the building intent work?

  1. The designer or the builder makes the project documentation available in the information system. They ask the planning authority and the affected authorities for binding opinions, and the affected legal persons for binding statements (§ 20 para. 1). An affected authority issues a binding opinion (§ 21). A legal person, such as a network operator, issues a binding statement (§ 22).
  2. The designer evaluates the opinions and statements in the report on the consultation of the building intent (§ 23 para. 1).
  3. The builder files the application electronically on the set form and attaches the documentation and the report (§ 50 paras. 1 and 2). If the application lacks required items, the office calls for completion within 15 days of delivery (§ 50 para. 3).
  4. The office announces the start of the proceeding within seven days of the day the application is complete (§ 51 para. 1). The parties include owners of neighbouring plots and structures if the decision may directly affect their rights (§ 49 para. 1 point c). If the office orders no oral hearing, the comment period is at least seven working days from delivery of the notice (§ 51 para. 2).
  5. The office decides within 30 days of the complete application if no oral hearing or site visit is needed, otherwise within 60 days. It decides within 90 days in some cases. These are a reserved or linear structure, a structure with many parties, or a case that needs an expert opinion. See § 58 paras. 1 and 2. The time for delivering the notice and the time until the oral hearing do not count (§ 58 para. 3).

The decision on the building intent is not treated as issued when the office stays inactive. The Building Act presumes consent from silence in four cases only. They are the binding opinion of an affected authority and the binding statement of a legal person (§ 21 para. 9, § 22 para. 5). The other two are a compliance declaration (§ 24 para. 3) and a notification (§ 63 para. 7). A planning authority that misses its period is inactive (Act 200/2022 Z. z., § 24a para. 13). Act 200/2022 Z. z. then presumes that it has no comments and has issued a binding opinion of compliance with the spatial plan (§ 35 para. 1 písm. a). For a house as a simple structure this authority has 30 days to issue its opinion (§ 24a para. 5).

The decision is valid for two years from legal force, and for three years for a reserved or linear structure. It does not lapse if an application for project verification was filed in that period (§ 61 para. 1). On request the office extends the validity by at most two years, but the total may not exceed seven years (§ 62 para. 3). The article Building Permit in Slovakia 2026: Process and Deadlines covers the procedure in detail.

When can building start after the decision?

Only after the project of the building is verified. Works without a verified project of the building, or against it, are unpermitted building works (§ 28 para. 1). The same office that issued the decision verifies the project. The period is 30 days from an application. The builder attaches the project of the building and the compliance declarations to it (§ 65 paras. 1 and 2). The office verifies that the project matches the decision and the conditions from the opinions and statements (§ 65 para. 3). On the builder's request the office may decide on the building intent and verify the project at the same time. The builder must submit consenting compliance declarations (§ 57 para. 3). The verification clause lapses if building works do not start within two years (§ 65 para. 6). Building without a verified project is an offence. The fine is 30 to 15,000 euro (§ 79 para. 3 point a, para. 6 point c).

Before works start, the builder notifies the office of the start of building works and gives the contractor's details. The builder hands the contractor the verified project, the final decision and the plots for the site (§ 30 para. 3). If you choose the contractor only after verification, the decision sets a duty. You must name the contractor and the site manager within 15 days of signing the contract (§ 60 para. 1 point h).

The start of construction is the start of works directly connected with building the structure. Fencing, setting up the site, providing access, water and electricity, clearing vegetation and removing waste do not count as the start (§ 41). A new structure may be built only after a land surveyor has set it out (§ 42 para. 1).

How do you choose a contractor and what should the contract settle?

If the builder has no authorisation to build structures, the builder must have the structure built by an authorised contractor (§ 26 para. 2). The contractor is a person authorised to build structures under contract (§ 31 para. 1). A contractor who signed a contract with the builder for the whole structure is the general contractor of the structure (§ 31 para. 3). A builder who fails to ensure that the supplier of the works holds the required authorisation commits an offence (§ 79 para. 3 point d).

The scope of the building works follows from the verified project of the building (§ 27 para. 2). Bids are comparable only when all bidders in a contractor tender price the same scope. The Commercial Code (§ 536 para. 1) and the Civil Code (§ 631) both define the contract for work. Under the Commercial Code, building a structure is always a work (§ 536 para. 2). Before signing, find out which of the two codes applies to your contract.

A builder may build a family house as a simple structure on their own. The condition is that a person authorised for site supervision leads the works (§ 26 para. 3). The article Self-Build House in Slovakia has the details.

Who watches over the building works?

The act separates four roles that people often mix up.

  • The site manager organises and directs the works, runs the site and keeps the construction diary. The site manager is responsible for the professional management of the construction. The site manager writes the final opinion on the conformity of the structure with the verified project. See § 37 paras. 1 and 2 and § 39 para. 1.
  • Construction supervision is carried out by a person the builder appoints. This person follows the progress of the works against the verified project and the technical rules and reads the construction diary (§ 36 para. 1). The act requires it for a reserved structure and for self-build (§ 30 para. 5 point a, para. 6 point a). For a house built by a contractor, § 30 puts no such duty on the builder. The glossary explains more about construction supervision.
  • Designer supervision monitors whether the works match the project of the building. The designer is entitled to carry it out (§ 35 para. 10). The builder must ensure it is carried out during construction (§ 30 para. 4 point d).
  • Author supervision is the right of the author of the architectural work to examine whether the works match the author's design (§ 35 para. 10). The contractor must allow it if the author asks. This does not apply where it conflicts with the contractor's legitimate interests (Copyright Act 185/2015 Z. z., § 33 para. 8).

The article Construction Supervision vs Author Supervision explains the difference in detail.

What if the house departs from the project during construction?

Settle the change before the contractor carries it out. If works would depart from the verified project, the builder may call an extraordinary inspection of the construction (§ 43 para. 2). If the departure does not conflict with the decision or the conditions from the opinions and statements, the designer marks it in the building project. The site manager records it in the minutes and in the construction diary. If the office did not attend, it approves the minutes within three days of delivery. If the office cannot permit it this way, it decides the change needs verification or a new proceeding on the building intent (§ 43 para. 3). The designer may approve a change only after the fire protection specialist agrees to it in advance for the affected part (§ 35 para. 11).

How does kolaudácia work and what follows it?

A finished structure may be put into permanent use only after kolaudácia (§ 66 para. 1). Kolaudácia starts on the builder's proposal. Depending on the structure type, the attachments include the construction diary, the final opinion of the site manager, the as-built documentation and the surveying documentation. They also include the protocol on handover and takeover of the structure and records of tests and measurements. If the building needs an energy performance certificate, that is an attachment too (§ 66 para. 2). The office announces the date of the inspection within seven working days of the complete proposal. The inspection must take place within 30 days of the notice. The office issues the certificate within 15 days of the inspection (§ 66 paras. 3 and 7). If it finds defects, the office interrupts kolaudácia and sets a period to remove them. If they are not removed, it stops kolaudácia (§ 66 paras. 5 and 6). Operating a structure without the occupancy certificate is an offence (§ 79 para. 3 point c).

The office invites the general designer and the general contractor to the inspection (§ 66 para. 3). The inspection covers whether the structure is finished, including access, and fit for safe use under the verified project. It also covers whether the technical building system works. Further points are the connection to the networks in the municipality, and rainwater that is retained or drained without burdening the surroundings (§ 66 para. 4 points a, c, d, e). If the municipality has levied the local development fee, the proposal also needs proof that it, or an instalment, was paid (§ 66 para. 2 point l).

The occupancy certificate (kolaudačné osvedčenie) is the document on kolaudácia and certifies that the structure is technically fit for its designed purpose. The as-built documentation is its attachment (§ 67 paras. 1 and 2). The system administrator sends the cadastre information about the certificate and the verified as-built documentation (Act 162/1995 Z. z., § 21 para. 2). A structure is entered in the cadastre if it is bounded by external walls and a roof structure (§ 46 para. 2). The article Occupancy Approval Step by Step has the step-by-step procedure.

How much are the administrative fees for a house?

Fees are set by Act 145/1995 Z. z. on administrative fees, item 59, in the version from 1 November 2026. For a building with one or two flats, the fee for the decision on the building intent is 300 euro. For a building with three to ten flats it is 1,000 euro. Project verification costs 50 % of that rate if the project is assessed on its own. It costs 30 % if it is assessed together with the building intent. The occupancy certificate costs 30 % of the rate. For a submission by electronic means the fee is halved, but reduced by at most 50 euro (§ 6 para. 2). If the office does not act within the period set by the Building Act, it refunds the fee (item 59, note 2).

These rates do not include the price of the design or of the building works. The contract with the designer and the contractor sets those.

How long does the whole process take, and where is time lost?

The act sets no total. Only the office has periods. Design, the choice of a contractor and construction have none. The decision on the building intent sets the construction period (§ 60 para. 1 point i). No source with a verified average for the whole process is available, so the article gives none. The act itself extends or stops the time in these cases:

  • An incomplete application. The office calls for completion within 15 days. If the applicant does not complete it, the office stops the proceeding (§ 50 para. 3, § 56 para. 1 point e).
  • A conflict between binding opinions. The office interrupts the proceeding and asks the superior bodies for opinions, which they issue within 30 days. If the conflict remains, the Office for Spatial Planning and Construction decides within 30 days of receiving those opinions (§ 54 para. 2).
  • A civil dispute between parties about ownership or other rights. The office interrupts the proceeding and sets a period to file a court claim of at most 60 days (§ 55 para. 2).
  • Lapse of validity. The decision and the verification clause have their own periods (§ 61 para. 1, § 65 para. 6).
  • Defects found at kolaudácia. While the builder does not remove them, kolaudácia stays interrupted (§ 66 para. 5).

What changes on 1 January 2027?

Act 243/2026 Z. z. amends the Building Act. Its Articles I to XIII apply from 1 January 2027 (Art. XV), so they are not yet in force. For a house the most important changes are these:

  • Three periods do not count towards the decision period. The first is the time for delivering the notice of the start of the proceeding. The second is the time until the oral hearing. The third applies if no hearing is ordered: the time until the comment period ends (new § 58 para. 3, point 124).
  • If the proceeding covered the project of the building together with the building intent, the office verifies the project after the decision becomes final. This applies where the decision does not require the project to be reworked (new § 65 para. 4, points 143 to 148).
  • The final opinion of the site manager stops being part of the contractor's execution documentation (realizačná dokumentácia) and an attachment to kolaudácia. The protocol on handover and takeover of the structure becomes a record. It includes the contractor's declaration that the structure conforms to the verified project (points 41, 42, 150, 151).
  • The notice of the start of works to the office is filed on a set form (§ 30 para. 3 point a, point 89).
  • The act now lists the activities of the person appointed for construction supervision as entitlements. They become duties (§ 36 paras. 1 and 2, points 98 and 99).

Frequently asked questions

How long does it take to build a house from buying the plot to kolaudácia?
The act sets no total duration. Only the building office and the affected authorities have periods. Examples are 30, 60 or 90 days for the decision on the building intent and 30 days for project verification. At kolaudácia the periods are 7 working days, 30 days and 15 days. Design, the choice of a contractor and construction have no statutory period. The decision on the building intent sets the construction period (§ 60 para. 1 point i).
Do you still need a building permit in 2026?
Not under that name. Act 25/2025 Z. z. has no building permit. A family house needs a decision on the building intent and then project verification. Under § 84 para. 11, from 1 April 2025 other regulations read three old terms in a new way. Territorial proceeding reads as the proceeding on the building intent. Building proceeding reads as project verification. Occupancy proceeding reads as kolaudácia. Old proceedings started by 31 March 2025 are finished under the old rules (§ 84 para. 4).
When can I start building?
Only after the project of the building is verified. Building works without a verified project, or against it, are unpermitted (§ 28 para. 1). Before works start, the builder notifies the office of the start and gives the contractor's details. The builder also hands the contractor the project, the decision and the plots (§ 30 para. 3). A land surveyor must set out a new structure before it is built (§ 42 para. 1).
Do I need construction supervision to build a house?
The act requires it for a reserved structure and for self-build (§ 30 para. 5 point a, para. 6 point a). For a house built by a contractor, § 30 puts no such duty on the builder. The builder must, however, ensure designer supervision of the construction (§ 30 para. 4 point d).
Can I move into the house before kolaudácia?
No. A finished structure may be put into permanent use only after kolaudácia (§ 66 para. 1). On the builder's request the office may allow time-limited early use of the structure or a part of it. This needs two conditions: early use does not endanger completion and the structure meets the basic requirements (§ 70 para. 1). Operating a structure without the occupancy certificate is an offence with a fine of 30 to 15,000 euro (§ 79 para. 3 point c, para. 6 point c).
What if I filed my application before 1 April 2025?
If the building office received the submission by 31 March 2025, or the proceeding began by that day, the previous rules apply (§ 84 para. 4). For a structure with a zoning decision or a building permit under the old rules, the old rules also apply to later submissions. Examples are the application for a building permit and the occupancy decision (§ 84 paras. 5 and 6). A period in a decision that began to run under the old rules keeps running (§ 84 para. 3).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 50 ods. 1, § 84 ods. 11
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I
  3. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 5 písm. u), § 22 ods. 3 až 5, § 24a ods. 5, 13, § 35 ods. 1
  4. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Národná rada Slovenskej republiky, via Slov-Lex · § 3, 6 to 10, 12, 19w, sadzobník položka 59
  5. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 21 ods. 2, § 46 ods. 2, § 67
  6. Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 536 to 565, § 554 ods. 5
  7. Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 120 ods. 2
  8. Zákon č. 185/2015 Z. z. Autorský zákon · Národná rada Slovenskej republiky, via Slov-Lex · § 3 ods. 1 and 6, § 33 ods. 1, 7 and 8, § 91 ods. 1

Topic

  • Building process