Building Intent Decision

A decision on the building intent is the building office decision that approves a building intent under Act 25/2025 and ends the proceedings.

What is a decision on the building intent?

A decision on the building intent (rozhodnutie o stavebnom zámere) is the decision with which a building office approves a building intent (§ 60 ods. 1 of zákon č. 25/2025 Z. z.).

The Building Act applies from 1 April 2025. Almost every new structure, change of a completed structure, demolition and alteration needs this decision unless the act says otherwise (§ 18 ods. 2). The decision ends the proceedings on the building intent. The building intent is the documentation the office approves.

The decision does not replace the whole old permit chain. Builders may build only to a project that the office has verified, or on the basis of a notification (§ 25). The old step names map to the new ones in § 84 ods. 11:

Until 31 March 2025Since 1 April 2025
Territorial proceedings (územné konanie)Proceedings on the building intent, ending in the decision
Building proceedings (stavebné konanie)Verification of the project (overenie projektu stavby)
Occupancy proceedings (kolaudačné konanie)Occupancy approval (kolaudácia)

What does the decision contain?

The decision approves the building intent and sets the conditions for building (§ 60 ods. 1). It does the following:

  • It decides on conflicting requirements and opinions from the report on the negotiation of the intent.
  • It decides on the objections of the parties.
  • It names the plots that form the building site, taken from cadastre data.
  • It sets how to mark the site and the structure.
  • It sets the requirements of the affected authorities from their binding opinions and of the affected legal persons from their binding statements.
  • It sets the stages of construction that need an inspection.
  • It sets the construction period.
  • It may order trial operation.

If the builder chooses the contractor only after the project is verified, the decision sets a duty. The builder reports the contractor and the site manager within 15 days of signing the contract. A structure built in stages gets a construction schedule in the decision (§ 60 ods. 2).

How long does the office have to issue the decision?

The office has 30, 60 or 90 days from the day the application is complete (§ 58).

CasePeriod
The office can decide from the application without a hearing or site inspection30 days
Other cases60 days
Reserved structure, linear structure, many parties or a needed expert opinion90 days

The period does not include the time to deliver the notice of the start or the time until the hearing (§ 58 ods. 3). It stops while the office waits for an expert opinion or a state expert review (§ 58 ods. 2).

The builder collects the binding opinions before filing, so they are not part of this period (§ 20, § 50 ods. 2). From 1 January 2027 the time until the comment period ends is also left out when there is no hearing (§ 58 ods. 3 as amended by zákon č. 243/2026 Z. z.). See reserved structure for the 90-day group.

How long is the decision valid?

The validity runs from the day the decision becomes final (§ 61 ods. 1). The office may set a longer period.

Subject of the decisionValidity
Ordinary structure2 years
Linear structure or reserved structure3 years
Information structure or assembled product1 year

The decision does not lapse if the builder filed a request to verify the project in time. It ceases to apply when the verification clause loses validity (§ 61 ods. 1). That clause loses validity if works do not start within two years of its issue. The office may set a longer period (§ 65 ods. 6).

Can the validity be extended?

Yes, on request filed before the period ends. The office extends it by at most two years at a time, and the total with extensions is at most seven years (§ 62 ods. 3). The seven-year limit does not apply to linear structures and nuclear facilities. The period does not run from the request until the decision on it is final.

The office needs a new binding opinion of the planning authority and a new binding statement of the affected legal person. It does not need them if the data of the area are current in the information system (§ 62 ods. 4).

When do I need a decision on the building intent?

A new family house needs one (§ 18 ods. 2). A small structure (drobná stavba) needs only a notification. Examples are a shed or a garage up to 50 m² and 5 m high (§ 2 ods. 4 písm. a, § 18 ods. 3). Repairs of a façade or a roof covering need neither (§ 18 ods. 5). See minor structure.

A notified structure can still move to the building intent proceedings. The office then tells the builder that third-party rights are affected or that it must set conditions (§ 63 ods. 5). Amendment 243/2026 changes the structure definitions from 1 January 2027.

What happens after the decision?

  1. The designer prepares the project in line with the decision (§ 24 ods. 1). Authorities that reserved the review issue a compliance declaration (doložka súladu) in 30 days, or 60 days for complex structures. Silence counts as approval (§ 24 ods. 2 and 3).
  2. The builder asks the office that issued the decision to verify the project. The office verifies it in 30 days, but only if the declarations are positive and the project matches the decision (§ 65 ods. 1 to 3).
  3. The builder builds to the verified project (§ 25).
  4. The builder files a proposal for occupancy approval (kolaudácia). A new structure needs it, and it ends with an occupancy certificate (§ 66 ods. 1 and 2, § 15 ods. 5 písm. d). See occupancy approval.

Who does the decision bind, and can it change?

The decision binds the legal successors of the builder and of the other parties (§ 61 ods. 4). The office announces it in the same way as the start of the proceedings (§ 61 ods. 2). It uses a public notice when there are more than 20 parties or an environmental assessment preceded the case (§ 61 ods. 3).

The office may change the decision in four cases (§ 62 ods. 1). The cases are a new builder and a longer validity. They also include a new construction period or time for a temporary structure. The last case is an added underground communication line in a linear structure. It may cancel the decision if a serious irreparable construction defect or a find on the plot stops completion (§ 62 ods. 7). A party cannot appeal a change or a cancellation, except the addition of a communication line (§ 62 ods. 8).

What does the decision cost?

The state fee depends on the building type (položka 59 písm. a of zákon č. 145/1995 Z. z., version valid on 1 November 2026).

BuildingFee
Residential building with 1 or 2 flats300 euro
Residential building with 3 to 10 flats1,000 euro
Residential building with 11 to 50 flats2,000 euro
Residential building with 51 to 100 flats3,500 euro
Residential building with 101 or more flats5,000 euro
Non-residential building that is a simple structure300 euro
Non-residential building up to 500 m² floor area500 euro
Non-residential building up to 1,000 m² floor area1,000 euro
Non-residential building over 1,000 and up to 2,000 m²2,000 euro
Non-residential building over 2,000 and up to 5,000 m²5,000 euro
Non-residential building over 5,000 and up to 10,000 m²8,000 euro
Non-residential building over 10,000 m²10,000 euro

Demolition or change of a structure costs 25% of the rate. Project verification costs 30% of the rate when the office assesses it with the intent, and 50% when it assesses it alone (písm. b bod 1 and 2). A filing by electronic means pays 50% of the fee, and the reduction is at most 50 euro (§ 6 ods. 2).

Frequently asked questions

What is a decision on the building intent?
It is the decision with which a building office approves a building intent and ends the proceedings (§ 60 ods. 1 of zákon č. 25/2025 Z. z.). It sets the building site, the conditions and the construction period.
How long does the office have to issue the decision?
It has 30 days from a complete application when it can decide without a hearing or inspection, and 60 days in other cases. It has 90 days for reserved or linear structures, many parties or an expert opinion (§ 58).
How long is the decision valid?
It is valid for two years from the day it becomes final, or three years for linear and reserved structures. It does not lapse if the builder files a request to verify the project in time (§ 61 ods. 1).
Can I start building with the decision alone?
No. A structure may be built only to a project that the office verified, or on the basis of a notification (§ 25). The office verifies the project on request in 30 days (§ 65 ods. 1 and 2).
When do I need a decision on the building intent?
You need one for almost every new structure, change of a completed structure, demolition and alteration, unless the act says otherwise (§ 18 ods. 2). Small structures need a notification, and repairs of a façade or roof covering need neither (§ 18 ods. 3 and 5).
What does the decision cost for a family house?
The state fee is 300 euro for a building with one or two flats (položka 59 písm. a bod 1 of zákon č. 145/1995 Z. z.). Project verification adds 30% or 50% of that rate. Electronic filing halves the fee, with a reduction of at most 50 euro.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 15, 18, 20, 24, 25, 50, 51, 58 to 63, 65, 66, 84
  2. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59, § 6 ods. 2
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex