Building Intent Proceedings

Proceedings on the building intent are the building office procedure under Act 25/2025 that decides on a building intent and ends with a decision.

What are the proceedings on the building intent?

Proceedings on the building intent (konanie o stavebnom zámere) are the building office procedure that decides on a building intent (§ 48 to 60).

The Building Act (zákon č. 25/2025 Z. z.) applies from 1 April 2025. The proceedings took the place of the old territorial proceedings (územné konanie, § 84 ods. 11 písm. a). They end with the decision on the building intent. The verification of the project is a separate step after the decision (§ 65). The building intent is the documentation the office assesses.

Do the proceedings apply to cases filed before 1 April 2025?

No. The old rules in the version valid until 31 March 2025 still apply to some cases (§ 84 ods. 4 and 5). The new act governs all other cases.

SituationRules
The building office received the application by 31 March 2025Old rules
Proceedings started by 31 March 2025Old rules
A territorial decision under the old rules, then a later application for a building permit or occupancy decisionOld rules
A new case filed after 31 March 2025 without such a decisionZákon č. 25/2025 Z. z.

Which office runs the proceedings?

The building office (stavebný úrad) is the municipality, and it acts as part of the state administration (§ 15 ods. 1). The same body also decides on related matters during the works and issues the occupancy certificate (§ 48 ods. 1). See building office.

If one intent covers a set of structures that fall under several offices, the office of the main structure leads the proceedings. The other offices act as affected authorities (§ 48 ods. 2).

Who takes part in the proceedings?

The parties are the following (§ 49 ods. 1):

  • the builder (stavebník).
  • the owner of the structure or the plot and anyone with another right to it.
  • the owners of neighbouring structures and plots whose rights the decision may directly affect.
  • anyone who has this status under a special law.

Tenants of flats and non-residential premises are not parties (§ 49 ods. 2). The designer is a party for the content of the intent and the report on its negotiation (§ 49 ods. 3).

What happens before the builder files?

The designer or the builder prepares the intent and the negotiation report before the application.

  1. They share the documentation in the information system of the Úrad pre územné plánovanie a výstavbu (§ 8 ods. 3, § 20 ods. 1).
  2. They ask the planning authority and the affected authorities for a binding opinion. They ask the affected legal persons for a binding statement (§ 20 ods. 1).
  3. An authority has 30 days to answer, or 60 days for a complex structure. If it stays silent, the law presumes it has no remarks (§ 21 ods. 9, § 22 ods. 5).
  4. They write the report on the negotiation of the intent. It evaluates every opinion and states how each remark was handled (§ 23 ods. 1).

How do the proceedings run step by step?

  1. The builder files the application with the office electronically on the set form. The application includes the project documentation from an authorised person and the report (§ 50 ods. 1 and 2).
  2. If the application is incomplete, the office calls the builder within 15 days to complete it. It warns that it will otherwise stop the proceedings (§ 50 ods. 3, § 56 ods. 1 písm. e).
  3. The office announces the start within 7 days of a complete application to the parties, the affected authorities and the affected legal persons. The notice names the hearing and inspection if ordered (§ 51 ods. 1 and 2).
  4. Without a hearing, parties have at least 7 working days from delivery of the notice to comment (§ 51 ods. 2). The notice goes out by public notice in three cases. There are more than 20 parties, an environmental assessment preceded the case, or a party is unknown (§ 51 ods. 3).
  5. The office orders a hearing if the report shows that the builder and the designer refused conflicting conditions. It may join the hearing with a site inspection. The office delivers the summons at least 7 working days before (§ 53 ods. 1 and 4).
  6. If binding opinions conflict, the office leads the authorities to an agreement. If that fails, it interrupts the proceedings and asks the superior bodies, which answer in 30 days (§ 54 ods. 2).
  7. If a party raises a property dispute that the office cannot decide, the office tries to settle it. If that fails, it asks the party to go to court within a period of at most 60 days (§ 55).
  8. The office issues the decision (§ 60).

How long do the proceedings take?

The office decides within 30, 60 or 90 days from the day the application is complete (§ 58).

CasePeriod
The office can decide from the application without a hearing or site inspection30 days
Other cases60 days
Reserved structure, linear structure, many parties or a needed expert opinion90 days

The period does not include the time to deliver the notice of the start or the time until the hearing (§ 58 ods. 3). It stops while the office lacks an expert opinion or a state expert review (§ 58 ods. 2).

What does the office check, and when does it reject the application?

The office examines the following (§ 57 ods. 2):

  • the applicant has a right to the plot or structure that allows the works.
  • the works comply with the decision of the environmental impact assessment authority.
  • the documents show compliance with protected interests and with the binding opinion of the planning authority.
  • a structure for public use or a building visited by the public meets the barrier-free requirements.
  • the report applies the binding opinions and statements and handles the comments of the parties.
  • a designer prepared the intent, and the builder or a designer prepared the report.

The office rejects the application in these cases (§ 59).

  • the siting conflicts with the binding opinion of the planning authority or with the assessment decision.
  • a designer did not prepare the intent.
  • the structure conflicts with an interest protected by a special law.
  • a public structure does not meet the barrier-free requirements.
  • the structure has no sufficient access from a public road.
  • a utility owner states that the structure cannot connect to the water, sewer or power network. The rule does not apply if the structure needs no connection.
  • a conflict between binding opinions remains unresolved.

What changes from 1 January 2027?

Parliament promulgated zákon č. 243/2026 Z. z. on 7 October 2026. Its Article I amends the Building Act from 1 January 2027. The changes to these proceedings include the following:

  • The office announces the start within 7 working days instead of 7 days (§ 51 ods. 1).
  • If the builder attaches the project, the office first decides on the intent. It verifies the project after the decision is final (§ 57 ods. 3).
  • The time until the comment period ends is not counted when there is no hearing (§ 58 ods. 3).
  • The office may approve after the fact some structures built without a verified project from 1 April 2025 to 31 December 2026. The list is short. Filing does not allow the builder to continue the works (§ 18 ods. 2, § 57 ods. 5 and 6, § 60 ods. 4).

Frequently asked questions

What are the proceedings on the building intent?
They are the building office procedure that decides on a building intent and ends with a decision (§ 48 to 60 of zákon č. 25/2025 Z. z.). They took the place of the old territorial proceedings (§ 84 ods. 11 písm. a).
How long do the proceedings take?
The office decides within 30 days from a complete application when it needs no hearing or inspection, and within 60 days in other cases. It has 90 days for reserved or linear structures, many parties or an expert opinion (§ 58).
What is the difference between the proceedings and the decision?
The proceedings are the whole procedure at the building office. The decision on the building intent is its result, in which the office approves the intent (§ 60 ods. 1).
How do I file the application?
The builder files it with the building office electronically on the set form, with the project documentation and the negotiation report (§ 50 ods. 1 and 2). The information system of the Úrad stores the documents (§ 8 ods. 3).
Can neighbours object?
Yes. Owners of neighbouring structures and plots are parties if the decision may directly affect their rights. They can give comments and objections until the hearing, or for at least 7 working days if there is no hearing (§ 49 ods. 1, § 51 ods. 2).
Do cases filed before 1 April 2025 follow the new act?
No. An application delivered or proceedings started by 31 March 2025 follow the old rules (§ 84 ods. 4). New cases follow zákon č. 25/2025 Z. z.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 8, 15, 18, 20 to 23, 48 to 60, 65, 84
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex