Building Permit

A building permit (stavebné povolenie) was the decision that allowed construction under the old Act 50/1976 Zb., replaced on 1 April 2025.

What was a building permit?

A building permit (stavebné povolenie) was a decision of the building office that allowed a person to build or to change a structure. It belongs to the old Building Act, zákon č. 50/1976 Zb., in the version valid until 31 March 2025. Since 1 April 2025 the new Building Act, zákon č. 25/2025 Z. z., governs building procedures.

The old act allowed building only with a building permit or after a notification to the building office (§ 54). A permit covered structures of every kind and changes such as an extension, an added floor or an alteration (§ 55 ods. 1). Notification was enough for some small works (§ 55 ods. 2).

In the permit the office set binding conditions for building and use and decided on objections (§ 66 ods. 1). It also set a deadline for finishing the structure (§ 66 ods. 3 písm. d). The permit lapsed if building did not start within two years of the day it became final. The office could set a longer period (§ 67 ods. 2). A building permit allowed building to start, and occupancy approval (kolaudácia) allows use of the finished building.

How did the old permit procedure work?

The builder applied to the building office with documentation from an authorised person and proof of a right to the land (§ 58 ods. 1 and 2). The documentation had to follow the territorial decision (územné rozhodnutie) or the binding opinion of the planning authority (§ 60 ods. 1).

  1. The office announced the start of the proceedings within 7 days of a complete application. It ordered an oral hearing with a site inspection (§ 61 ods. 1). It could skip the hearing when it knew the site well (§ 61 ods. 2).
  2. Affected authorities gave opinions by the set deadline. The office deemed a silent authority to agree (§ 61 ods. 6).
  3. The office examined planning conditions, public interests, technical requirements and the person who would do the work (§ 62 ods. 1). Then it decided.

The decision deadline came from the general administrative procedure act (zákon č. 71/1967 Zb.). It gave 30 days from the start of the proceedings and 60 days in especially complex cases (§ 49 ods. 2).

What replaced the building permit on 1 April 2025?

The old building proceedings (stavebné konanie) became the verification of the project (overenie projektu stavby). The old territorial proceedings (územné konanie) became the proceedings on the building intent (konanie o stavebnom zámere) (§ 84 ods. 11 písm. a and b).

The office ends the building intent proceedings with a decision on the building intent (rozhodnutie o stavebnom zámere, § 60). A builder may start work only on a project that the office verified with a verification clause (overovacia doložka, § 25 and § 65 ods. 5). Work without a verified project counts as unauthorised (§ 28 ods. 1). So the nearest equivalent of the old permit is the verified project, which rests on the decision.

The office may decide on the intent and verify the project in one step. The builder then files positive compliance declarations (doložky súladu) from the affected authorities (§ 57 ods. 3).

This page describes the text of zákon č. 25/2025 Z. z. in force on 1 November 2026 (version 01.11.2025 to 31.12.2026). Amendment 243/2026 Z. z. changes it from 1 January 2027, and the last section lists the changes that touch this page.

How do I get permission to build a family house under the current act?

The builder needs a decision on the building intent and then a verified project. The municipal building office issues both. A notification is enough in some cases (§ 18 ods. 2 and 3). A simple structure (jednoduchá stavba) includes a residential building with at most three flats. It has at most two above-ground floors and a built-up area of at most 300 m2 (§ 2 ods. 6 písm. a).

  1. A designer prepares the building intent (stavebný zámer). The office rejects an intent that a designer did not prepare (§ 59 ods. 1 písm. b).
  2. The builder or designer asks for binding opinions (záväzné stanoviská) from the spatial planning authority and the affected authorities. The request goes through the information system (§ 20 ods. 1).
  3. The builder files the application electronically on the prescribed form. The application includes the documentation and the report on the discussion of the intent (§ 50 ods. 1 and 2).
  4. The office issues the decision on the building intent (§ 60 ods. 1).
  5. The office verifies the project within 30 days (§ 65 ods. 2). It may do both in one step when the builder files positive compliance declarations (§ 57 ods. 3).
  6. After the works, the kolaudácia ends with the occupancy certificate (kolaudačné osvedčenie, § 66 and § 67).

Who issues the decision and how long does it take?

The municipality is the building office (stavebný úrad, § 15 ods. 1). It issues decisions on the building intent, handles notifications, verifies projects and issues occupancy certificates (§ 15 ods. 5).

The office has 30 days when it can decide on the papers alone and 60 days when it needs a hearing or site inspection. It has 90 days for reserved and linear structures, for cases with many parties and when an expert opinion is needed (§ 58 ods. 1 and 2). The days count from the day the application is complete. Delivery of the notice and the time until a hearing do not count (§ 58 ods. 3).

Binding opinions come before the application. An authority has 30 days, or 60 days for a complex structure. If it stays silent, the law deems that it has no comments (§ 21 ods. 9). The act sets no time for the design work. See also building permit timeline.

Do I need a decision for a garage, an extension or a renovation?

It depends on the work. Section 18 ods. 2 requires a decision on the building intent for every structure, change of a completed structure, removal and alteration, unless ods. 3 to 5 say otherwise.

  • A separate garage up to 50 m2 and 5 m high is a small structure (drobná stavba, § 2 ods. 4 písm. a). It needs a notification (ohlásenie, § 18 ods. 3). The office has 30 days. If it does not verify the project in time, the law deems that it did (§ 63 ods. 6 and 7). See minor structure notification.
  • A larger garage is not a small structure and needs the decision.
  • An extension (prístavba) is the widening of an existing structure on its footprint (§ 5 ods. 3). It is a change of a completed structure and needs the decision.
  • Repairs such as a new roof covering, a repaired facade or new windows need neither a decision nor a notification (§ 18 ods. 5 písm. a bod 1).
  • Other alterations (stavebné úpravy, § 2 ods. 9) need a notification in the cases of § 18 ods. 3 písm. a to i, for example closer than 2 m to the plot boundary. Otherwise they need nothing (§ 18 ods. 5 písm. k).

The state fee for a notified small structure is 50 euro. For a notified alteration it is 150 euro on a residential building and 300 euro on another building (položka 59 písm. b bod 5 and 6 of zákon 145/1995, version 01.11.2026 to 30.11.2026).

How do the old and new procedures compare?

AspectOld regime (until 31 March 2025)New regime (from 1 April 2025)
Steps and documentsTerritorial proceedings and territorial decision, then building proceedings and building permitBuilding intent proceedings and decision, then verification of the project and verified project
Decision deadline30 days, or 60 days in especially complex cases (§ 49 ods. 2 of zákon 71/1967)30 days, 60 days with a hearing or site inspection, 90 days in the cases of § 58 ods. 2
ValidityThe permit lapses if works do not start within 2 years (§ 67 ods. 2)The decision lasts 2 years, or 3 years for linear and reserved structures (§ 61 ods. 1). The verification clause lapses if works do not start within 2 years (§ 65 ods. 6)
Silent authorityAn affected authority that stayed silent counted as agreeing (§ 61 ods. 6)A deemed outcome applies to binding opinions (§ 21 ods. 9), compliance declarations (§ 24 ods. 3) and notified works (§ 63 ods. 7). The act has none for the decision on the building intent
State fee, family house100 euro for the building permit (zákon 145/1995, položka 60)300 euro for the decision on a single-flat or two-flat building, plus 30% or 50% of that for verifying the project (zákon 145/1995, položka 59)

What happens to proceedings that began before 1 April 2025?

Section 84 of zákon č. 25/2025 Z. z. lets the old rules finish many open matters.

SituationRules that applySource
A filing reached the building office, or proceedings began there, by 31 March 2025Old rules§ 84 ods. 4 písm. a and b
The office issued a territorial decision under the old act. The builder files a later application (after 31 March 2025) for a building permit, a change before completion, early use, trial operation or a kolaudačné rozhodnutieOld rules§ 84 ods. 5
The office issued a building permit under the old act and no territorial decision was needed. The builder files a later application for a change before completion, early use, trial operation or a kolaudačné rozhodnutieOld rules§ 84 ods. 6
A completed building was built without a permit. The owner asks for a review of fitness for use or for retrospective approvalOld rules, if the owner files by 31 March 2029 and meets the conditions§ 84 ods. 7

The building office that was competent under the old rules runs these proceedings (§ 84 ods. 8). Appeals go to the regional office, and appeals against its decision go to the Úrad pre územné plánovanie a výstavbu (§ 84 ods. 9 and 10). These proceedings keep the old state fees (§ 19w of zákon 145/1995).

What changes from 1 January 2027?

Amendment 243/2026 Z. z., Art. I, applies from 1 January 2027. It changes several points on this page.

  • Section 18 ods. 3 no longer lists small structures by letter. A small structure needs a notification only when one of the cases in § 18 ods. 3 písm. a to i applies.
  • Section 65 changes. When the project was part of the proceedings and the decision asks for no rework, the office verifies it after the decision becomes final.
  • Section 18 ods. 2 adds a decision on the building intent for some works done from 1 April 2025 to 31 December 2026 without a verified project. The works are those that the amendment calls "nepovolená stavba".

The act in force on 1 November 2026 has no such procedure for works done after 31 March 2025. Read the consolidated text of 25/2025 for 1 January 2027 before you rely on this section.

Frequently asked questions

Does the building permit still exist in Slovakia?
Not for new applications. Since 1 April 2025 the building office decides on a building intent and verifies the project instead. Matters that began under the old act can still end under the old rules (§ 84 ods. 4 to 6 of zákon 25/2025).
How do I get permission to build a family house now?
Apply to the municipal building office for a decision on the building intent, then for the verification of the project (§ 18 ods. 2, § 60, § 65 of zákon 25/2025). A designer must prepare the intent. The office may decide on the intent and verify the project in one step (§ 57 ods. 3).
How long does the procedure take?
The office decides within 30, 60 or 90 days from the day the application is complete (§ 58 of zákon 25/2025). It verifies the project within 30 days (§ 65 ods. 2). Binding opinions before the application take 30 or 60 days each (§ 21 ods. 9).
Do I need a decision for a garage or an extension?
A separate garage up to 50 m2 and 5 m high needs only a notification (§ 2 ods. 4 písm. a and § 18 ods. 3). A larger garage and an extension of a house need the decision on the building intent (§ 5 ods. 3 and § 18 ods. 2 of zákon 25/2025).
How much does the permit cost?
The state fee for the decision on the building intent for a single-flat or two-flat building is 300 euro. Verifying the project costs 30% or 50% of that rate (položka 59 of zákon 145/1995, version 01.11.2026). The old permit for a family house cost 100 euro (položka 60, version 15.03.2025).
Does a permit issued before 1 April 2025 still count?
Yes. Legal relations created under the old rules stay preserved (§ 84 ods. 1 of zákon 25/2025). Deadlines that began to run under the old rules keep running (§ 84 ods. 3).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2, 5, 15, 18, 20, 21, 24, 25, 28, 50, 57, 58, 59, 60, 61, 63, 65, 66, 67, 84
  2. Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon) · Slov-Lex · § 54, 55, 58, 60, 61, 62, 66, 67, 76
  3. Zákon č. 71/1967 Zb. o správnom konaní (správny poriadok) · Slov-Lex · § 49 ods. 2
  4. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59
  5. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 60
  6. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex