Building Authority

A building authority is a municipality that decides on building intents, notifications and occupancy under the Building Act 25/2025.

What is a building authority?

A building authority (stavebný úrad) is the municipality, acting for the state, that decides on building matters in its territory. The act states: "Stavebným úradom je obec", and the work is a transferred state task (25/2025 Z. z. § 15 ods. 1).

At least two employees with a special qualification must staff it (§ 15 ods. 6). The Office for Spatial Planning and Construction (Úrad pre územné plánovanie a výstavbu SR, the Office) directs the system. It issues guidelines and runs the training of the staff (§ 13 písm. e).

Which building authority is responsible for my building?

For most houses it is the building authority of the municipality where the building stands. Four other cases exist.

  • Small municipalities may form a joint municipal office. Their territories must belong to the same regional office (§ 15 ods. 2).
  • A special building authority handles roads, railways, airports, water works, mines and quarries. It is set by a separate act (§ 16 ods. 1).
  • Another building authority handles some state buildings. Examples are the Ministry of Defence for military sites and the nuclear regulator for nuclear installations (§ 16 ods. 2).
  • The regional office acts as building authority for projects such as state-supported rental housing and significant investments (§ 14 ods. 3).

If a building lies in the territory of two or more building authorities, the regional office names the one that decides (§ 14 ods. 1 písm. f). The regional office may also take over a technically demanding or unusual building (§ 14 ods. 1 písm. h). The reserved structure is a related term.

What does a building authority decide?

It decides on the building intent and notifications, verifies the project and issues the occupancy certificate. The list in § 15 ods. 5 reads as follows.

  • It issues the decision on the building intent (rozhodnutie o stavebnom zámere), see building intent proceedings.
  • It handles notifications (ohlásenie) of small works, see minor structure notification.
  • It verifies building projects (overenie projektu stavby).
  • It issues the occupancy certificate (kolaudačné osvedčenie), see occupancy approval.
  • It permits temporary and early use of a building.
  • It keeps data in the construction register and checks whether a building is fit for use.

The old names still appear in searches. The act maps them in § 84 ods. 11, as the table shows.

Name until 31 March 2025Name from 1 April 2025
územné konaniekonanie o stavebnom zámere
stavebné konanieoverenie projektu stavby
kolaudačné konaniekolaudácia
Slovenská stavebná inšpekciastavebný inšpektorát (a regional office)

The same authority that decides on the building intent also decides on the later steps and issues the occupancy certificate (§ 48 ods. 1). The building act sets the whole procedure. The building permit of the old regime is now the decision on the building intent plus the verified project.

How long does a building authority have to decide?

It has 30 days when no hearing or site visit is needed and 60 days otherwise. It has 90 days for a reserved structure, a linear structure, a case with many parties or a case that needs an expert opinion (§ 58 ods. 1 a 2). The period starts when the application is complete.

Other deadlines in the act are shorter.

StepDeadlineIf the office is silentSource
Notification of a small building30 daysThe act presumes the verification clause was issued§ 63 ods. 6 a 7
Occupancy certificate after the site inspection15 daysNo rule in the act§ 66 ods. 7
Site inspection after the notice30 daysNo rule in the act§ 66 ods. 3
Binding opinion of an affected authority30 days, or 60 for a complex buildingThe act presumes no comments§ 21 ods. 9

The act has no deadline of 40 working days. Silence counts as consent only for affected authorities and for notifications. A late decision on a building intent is not an approval.

What can I do if the building authority does nothing?

The Office may name another building authority to act for one that stays inactive for at least 90 days. The other municipality must be in the same regional office area, be the seat of a joint municipal office and agree (§ 13 písm. i). The inactive office then pays the administrative fee of the case to the office that took over (§ 15 ods. 4).

How do I appeal a decision of a building authority?

The regional office is the appeal body for decisions of a building authority (§ 14 ods. 1 písm. a). The Office decides on appeals against decisions of the regional office (§ 13 písm. f). An appeal cannot be made orally into the record (§ 82 ods. 2).

If the office returns a notification, the applicant may ask the appeal body to review the procedure. The request is due within 10 working days of delivery. The appeal body reviews it within 30 days (§ 63 ods. 8). The act sets no general appeal deadline. Read the appeal instructions in the decision.

Who supervises building authorities and building sites?

The regional office controls how building authorities carry out their state tasks (§ 14 ods. 1 písm. b). Acting as the building inspectorate (stavebný inšpektorát), it carries out state building supervision, deals with offences and imposes fines (§ 14 ods. 2). The building authority itself reports unlawful work to the inspectorate (§ 15 ods. 5).

How do I send documents to a building authority?

An application for a building intent goes to the building authority electronically on a set form (§ 50 ods. 1). The Office runs the information system for this, described under URBION information system. Any person may still act on paper until 31 March 2029, and a natural person may do so after that date too (§ 84 ods. 15).

What changes from 1 January 2027?

Amendment 243/2026 Z. z. changes § 15 ods. 5 from 1 January 2027. The building authority must then warn a builder who carries out unauthorised work and report it to the inspectorate. It also permits a change in the use of a building. The review of fitness for use no longer appears in this list (243/2026 Čl. I, body 50 a 51). Other parts of the amendment apply from 15 November 2026. Check the dated version before you rely on a rule.

Frequently asked questions

Which building authority is responsible for my building?
For most buildings it is the building authority of the municipality where the building stands. Roads, railways, water works and mines go to a special building authority, set by a separate act (25/2025 Z. z. § 15 ods. 1, § 16 ods. 1).
What does a building authority decide?
It issues the decision on the building intent, handles notifications, verifies the project and issues the occupancy certificate. It also permits temporary and early use of a building (25/2025 Z. z. § 15 ods. 5).
How long does a building authority have to decide?
It has 30 days for a case without a hearing or site visit, 60 days for other cases and 90 days for reserved or linear structures. The period starts when the application is complete (25/2025 Z. z. § 58).
Who decides an appeal against a building authority?
The regional office of the Office for Spatial Planning and Construction decides (25/2025 Z. z. § 14 ods. 1 písm. a). The act sets no general appeal deadline, so check the appeal instructions in the decision.
What happens if a building authority does not act?
After at least 90 days of inactivity, the Office may name another municipality as building authority for the case. The inactive office pays that office the administrative fee (25/2025 Z. z. § 13 písm. i, § 15 ods. 4).
Can I still submit documents on paper?
Yes. Any person may act on paper until 31 March 2029, and a natural person may do so after that date too. Electronic submission is the rule (25/2025 Z. z. § 84 ods. 15).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 13, 14, 15, 16, 21, 48, 50, 58, 63, 66, 82, 84, 85
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (vyhlásené znenie) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 50 and 51
  3. Portál výstavby · Úrad pre územné plánovanie a výstavbu SR