Binding Opinion

A binding opinion is a written position of an affected authority that sets requirements for a planned building and binds the building office.

What is a binding opinion?

A binding opinion (záväzné stanovisko) is a written position of an affected authority on a planned building. The building rules treat it as binding. The affected authority is the dotknutý orgán. It states which requirements of its own field the building must meet.

Since 1 April 2025 the rule is in the Building Act, zákon č. 25/2025 Z. z. (building act), § 21. The act allows building work only if it matches the binding part of the planning documents and the interests that special laws protect. Affected authorities state those interests in binding opinions (§ 21 ods. 1).

Who issues a binding opinion?

A public authority issues it when a new building, a change of a finished building or a demolition may affect an interest that the authority protects (§ 21 ods. 2). The Office for Spatial Planning and Construction (Úrad pre územné plánovanie a výstavbu SR) keeps the list of affected authorities in its information system.

  • The Ministry of the Interior is an affected authority when state-security buildings may be affected (§ 21 ods. 2).
  • The spatial planning authority is an affected authority for the match with the binding part of the planning documents (§ 21 ods. 5). Zákon č. 200/2022 Z. z. sets its procedure in § 24a.
  • The regional heritage office (krajský pamiatkový úrad) is an affected authority for heritage interests (zákon č. 49/2002 Z. z., § 30).

The Ministry of Defence joins this list from 1 January 2027 for areas and buildings that it names on its website (Art. I of zákon č. 243/2026 Z. z.).

When do you need a binding opinion?

You need one at four points. Within its field, each affected authority must issue the documents in the table (§ 21 ods. 3).

DocumentSlovak termUsed for
Binding opinion on the building intentzáväzné stanovisko k stavebnému zámeruThe building intent and its decision
Compliance clausedoložka súladuThe building design
Binding opinion for the final inspectionzáväzné stanovisko ku kolaudáciiThe final inspection
Binding opinion on a notified buildingzáväzné stanovisko k ohláseniuA notified building or alteration
  • For a building intent, the builder or the designer asks each authority through the information system (§ 20 ods. 1).
  • For a notified building, the opinions are attachments of the notification (§ 63 ods. 2).
  • For the final inspection, the builder attaches the opinions gathered before the application (§ 66 ods. 2 písm. k).

If the builder skipped a request that the content of the building intent called for, the builder must ask later (§ 21 ods. 10).

What must a binding opinion contain?

The authority must name the legal provision that gives it the power. It must state concrete requirements and give reasons that a reviewer can check (§ 21 ods. 6). It must also state whether the opinion replaces its opinion on the next design stage.

The authority may set requirements only within its legal powers and only to protect the interests that these powers give it (§ 21 ods. 6). Its separate right to issue a decision under a special law stays.

How long does an authority have to issue a binding opinion?

The default is 30 days from delivery of the request, or 60 days for a complex building (§ 21 ods. 9). A special law may set another limit. The act does not define a complex building.

IssuerTime limitSource
Affected authority, default30 days, 60 days for a complex building25/2025, § 21 ods. 9
Spatial planning authority30 days for notified and simple buildings, 90 days for reserved structures, 60 days for others200/2022, § 24a ods. 5
Compliance clause on the building design30 days, 60 days for a complex building25/2025, § 24 ods. 2

The time limit stops while the authority waits for the applicant to make the request more precise (§ 21 ods. 8). If the authority issues no opinion in time, the act presumes that it has no comments and no requirements on the building intent. The designer records this in the report on the discussion of the building intent (§ 21 ods. 9).

Why is a binding opinion binding?

The act says that an opinion that meets the content rules is binding (§ 21 ods. 11). The building office checks that the report on the discussion shows the opinions (§ 57 ods. 2 písm. e). For a notified building (see building permit for full permitting), the office verifies the design only if the opinions agree. If they do not, it returns the notification with reasons (§ 63 ods. 6).

If two opinions contradict each other, the building office first asks the authorities to agree. If they do not, it asks their superior bodies, then the Office, which decides within 30 days of receiving their positions (§ 54 ods. 2).

Can an authority change its binding opinion?

An authority is bound by its own opinion. It may depart from it only if the law it applied changed, or if the facts or documents behind it changed substantially (§ 21 ods. 7). A new opinion on the same matter must say if it confirms, supplements, changes or replaces the earlier one, and why.

How long is a binding opinion valid?

The Building Act sets no validity period for the opinion of an affected authority in § 21. The opinion of the spatial planning authority is valid for two years from delivery. It is valid for five years for transport infrastructure, technical infrastructure, nuclear installations and significant investments (zákon č. 200/2022 Z. z., § 24a ods. 6). It does not expire if the builder files the application that uses it within that period.

What can a builder do if the builder disagrees with a binding opinion?

The builder may object to an affected authority's opinion within 15 days from delivery. The builder objects at the authority above the issuer (§ 21 ods. 13). The builder objects to an opinion of the spatial planning authority at the Office (§ 21 ods. 14). Other parties to the proceedings object by appealing against the decision on the building intent (§ 21 ods. 15).

From 1 January 2027, the appeal body asks the authority above the issuing authority for its view on the appeal. If the authority has no superior, it asks the issuing authority itself (Art. I of zákon č. 243/2026 Z. z.).

What is the difference between a binding opinion and a binding statement?

A binding opinion (záväzné stanovisko) comes from an affected authority. A binding statement (záväzné vyjadrenie) comes from an affected legal person, such as the owner or operator of a network (§ 22 ods. 1). Both are binding, both are requested for the building intent, and both have a 30-day limit (§ 20 ods. 1, § 22 ods. 5).

What was a binding opinion called before 1 April 2025?

The act maps the old names to the new ones (§ 84 ods. 11). The old binding opinion on the zoning proceedings is now the binding opinion on the building intent. The old binding opinion on the building proceedings is now the compliance clause. The binding opinion for the final inspection keeps its name. See building intent proceedings and building office.

Frequently asked questions

What is a binding opinion in Slovak building law?
A binding opinion (záväzné stanovisko) is a written position of an affected authority on a planned building. The building rules treat it as binding. It states the requirements of the authority's own field (25/2025 Z. z., § 21).
Who is an affected authority?
An affected authority (dotknutý orgán) is a public authority that protects an interest by law and that the building may affect (§ 21 ods. 2). The Office for Spatial Planning and Construction keeps the list in its information system.
What must a binding opinion contain?
It must name the legal provision that gives the authority its power, state concrete requirements and give reasons that a reviewer can check. It must also say whether it replaces the opinion on the next design stage (§ 21 ods. 6).
How long does an authority have to issue a binding opinion?
The default is 30 days from delivery of the request, or 60 days for a complex building (§ 21 ods. 9). The spatial planning authority has 30, 60 or 90 days depending on the building type (200/2022, § 24a ods. 5).
What happens if the authority does not answer in time?
The act presumes that the authority has no comments and no requirements on the building intent, unless a special law says otherwise (§ 21 ods. 9). The designer records this in the report on the discussion of the building intent.
Can a builder ignore a binding opinion?
No. The building may be built only in line with the interests that the opinions state (§ 21 ods. 1). A builder who disagrees may object within 15 days at the authority superior to the issuing authority (§ 21 ods. 13).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon), version 01.11.2025 to 31.12.2026 · Národná rada Slovenskej republiky (Slov-Lex) · § 20, § 21, § 24, § 54, § 57, § 63, § 66, § 84 ods. 11
  2. Zákon č. 200/2022 Z. z. o územnom plánovaní, version from 01.03.2026 · Národná rada Slovenskej republiky (Slov-Lex) · § 24a
  3. Zákon č. 49/2002 Z. z. o ochrane pamiatkového fondu, version from 01.04.2025 · Národná rada Slovenskej republiky (Slov-Lex) · § 30
  4. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. (promulgated text) · Národná rada Slovenskej republiky (Slov-Lex) · Art. I, points 72 to 82
  5. Dotknuté orgány (Úrad pre územné plánovanie a výstavbu SR, stavebný portál) · Úrad pre územné plánovanie a výstavbu SR