Building Intent
A building intent (stavebný zámer) is the first level of project documentation that shows a planned structure and its site under the Building Act 25/2025.
What is a building intent (stavebný zámer)?
A building intent (stavebný zámer) is the first level of project documentation. It shows a planned structure, its site and its connections (§ 9 ods. 2 of zákon č. 25/2025 Z. z.).
It consists of text and drawings. They express the urban, architectural and basic building solution. This covers fire safety, the placement on the land and the connection to roads and utility networks. The Building Act applies from 1 April 2025. The building intent is the basis for the proceedings on the building intent. The next levels are the project (projekt stavby), the project for notified works and the execution project (§ 9 ods. 1). Decree 60/2025 sets the content and scope of the building intent in its Annex 15 (§ 6 ods. 2).
Which old procedure does it replace?
The proceedings on the building intent took the place of the old territorial proceedings (územné konanie) (§ 84 ods. 11 písm. a). The old building proceedings (stavebné konanie) became the verification of the project (overenie projektu stavby, § 84 ods. 11 písm. b). The new act therefore still has two steps. Until 31 December 2026 the office may do both together when the builder files positive compliance declarations (doložky súladu, § 57 ods. 3). From 1 January 2027 the office decides on the intent first and verifies the project after the decision is final (§ 57 ods. 3 as amended by zákon č. 243/2026 Z. z.). The old building permit has its own page.
| Term | English name | What it is | Who handles it |
|---|---|---|---|
| Stavebný zámer | Building intent | The documentation | The designer (§ 35 ods. 6 písm. a) |
| Konanie o stavebnom zámere | Building intent proceedings | The proceedings at the building office | The building office (§ 15 ods. 5 písm. a) |
| Rozhodnutie o stavebnom zámere | Decision on the building intent | The result of the proceedings | The building office (§ 60) |
Who prepares a building intent?
A designer (projektant) prepares it. The designer answers for drawing up the intent to the builder's requirements (§ 35 ods. 6 písm. a). The office rejects an application when a designer did not prepare the intent (§ 59 ods. 1 písm. b).
Design is a reserved activity. Only people with the legally required qualification or authorisation may do it, within their scope (§ 34 ods. 1 and 2). One exception covers documentation of a simple structure. It does not cover a residential building with more than three flats or a structure for public use (§ 34 ods. 4 písm. a). A simple structure is, for example, a residential building with up to three flats. It has up to 300 m² of built-up area and up to two above-ground floors (§ 2 ods. 6 písm. a).
How does a building intent move through the procedure?
- The designer or the builder shares the project documentation in the information system of the Úrad pre územné plánovanie a výstavbu. They ask the planning authority and the affected authorities for binding opinions. They ask the affected legal persons, such as owners of roads and utility networks, for binding statements (§ 20 ods. 1, § 22 ods. 1).
- An authority has 30 days to answer, or 60 days for a complex structure. If it stays silent, the law presumes it has no remarks on the intent (§ 21 ods. 9).
- The designer or the builder writes the report on the negotiation of the building intent (§ 23 ods. 1).
- The builder files the application electronically with the documentation and the report (§ 50 ods. 1 and 2).
- The office announces the start of the proceedings within 7 days of a complete application (§ 51 ods. 1). From 1 January 2027 the period is 7 working days. It decides within 30 days, or 60 days when the case needs a hearing or site inspection. The period is 90 days for reserved and linear structures, for cases with many parties and for cases that need an expert opinion (§ 58).
- The office approves the intent in a decision on the building intent. It decides on objections and sets the plots of the building site and the time allowed for construction (§ 60 ods. 1).
How long does a decision on the building intent last?
The validity runs from the day the decision becomes final (§ 61 ods. 1). The office may set a longer period.
| Subject of the decision | Validity |
|---|---|
| Ordinary structure | 2 years |
| Linear structure or reserved structure | 3 years |
| Information structure or assembled product | 1 year |
The decision does not lapse if the builder filed a request for the verification of the project within that period. The builder may ask for an extension before the period ends. The office extends it by at most two years on request. It may extend it again, and the total is at most seven years. The seven-year limit does not apply to linear structures (§ 62 ods. 3).
How does a building intent differ from the project (projekt stavby)?
The building intent is the first level of project documentation and the project is the second (§ 9 ods. 1). The intent shows the urban, architectural and basic building solution. The project shows the architectural and building-technical solution, the technical and energy equipment and the fire safety equipment (§ 9 ods. 2 and 3).
The designer prepares the project on the basis of the decision on the building intent and in line with the intent (§ 24 ods. 1). The builder may share the intent and the project together for binding opinions (§ 20 ods. 2 písm. b). The office then verifies the project in 30 days after the application (§ 65 ods. 2). See building permit documentation for the project level.
Does environmental impact assessment affect the building intent?
Yes, when an environmental impact assessment preceded the intent. The office examines whether the works comply with the decision of the assessment authority (§ 57 ods. 2 písm. b). It rejects the application if the siting conflicts with that decision (§ 59 ods. 1 písm. a). It announces the proceedings by public notice when an assessment preceded them (§ 51 ods. 3).
When does a house need a building intent?
Every structure, change of a completed structure, demolition and alteration needs a decision on the building intent. The act names exceptions (§ 18 ods. 2). A new family house goes through this decision.
A small structure (drobná stavba) needs only a notification (ohlásenie). Examples are a shed or a garage up to 50 m² and 5 m high (§ 2 ods. 4 písm. a, § 18 ods. 3). Listed maintenance works, such as repairing a façade or replacing a roof covering, need neither (§ 18 ods. 5). Amendment 243/2026 changes these definitions from 1 January 2027. This page describes zákon č. 25/2025 Z. z. in the version in force on 1 November 2026.
What does the decision cost?
The state fee for a decision on a single-flat or two-flat building is 300 euro (položka 59 písm. a bod 1 of zákon č. 145/1995 Z. z.). Verifying the project costs 30% of that rate when the office assesses it together with the intent, and 50% when it assesses it alone (písm. b bod 1 and 2). A filing by electronic means pays 50% of the fee, and the reduction is at most 50 euro (§ 6 ods. 2).
Frequently asked questions
- What is a building intent (stavebný zámer)?
- A building intent is the first level of project documentation under zákon č. 25/2025 Z. z. It shows the urban, architectural and basic building solution of a planned structure. The building office decides on it in the proceedings (§ 9 ods. 2).
- Who prepares a building intent?
- A designer (projektant) prepares it and answers for drawing it up to the builder's requirements (§ 35 ods. 6 písm. a). Design is a reserved activity, with an exception for simple structures (§ 34).
- Does a family house need a building intent?
- Yes. A new structure needs a decision on the building intent unless the act says otherwise (§ 18 ods. 2). Small structures such as sheds need only a notification (§ 18 ods. 3).
- How long does the building office have to decide?
- It has 30 days from a complete application, or 60 days when the case needs a hearing or site inspection. It has 90 days for reserved or linear structures, cases with many parties and cases that need an expert opinion (§ 58).
- How does a building intent differ from the project?
- The building intent is the first level of project documentation and the project is the second (§ 9 ods. 1). The designer prepares the project after the decision on the building intent and in line with it (§ 24 ods. 1).
- Does an environmental impact assessment change the building intent proceedings?
- Yes, if an assessment preceded the intent. The office examines whether the works comply with the assessment decision. It also announces the proceedings by public notice (§ 57 ods. 2 písm. b, § 51 ods. 3).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9, 15, 18, 20 to 24, 34, 35, 50, 51, 57 to 62, 65, 84
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 6 ods. 2
- Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59, § 6 ods. 2
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex