Pre-application consultation

A pre-application consultation is the discussion of a building intent with the bodies that give binding opinions and statements, before you file.

What is a pre-application consultation in Slovakia?

A pre-application consultation is the discussion of your building intent with the authorities and utilities that give binding opinions and statements before you file.

The page title is the old Slovak name "predbežná informácia stavebného úradu". Act 25/2025 has no document or step with that name. I searched the act (version 01.11.2025 to 31.12.2026) and the text of the amending Act 243/2026 and found none. The repealed Act 50/1976 (version 15.03.2025) has none either.

What the act has is the discussion of the building intent (prerokovanie stavebného zámeru, § 20 to 23). It is a formal step with deadlines and written results. It takes place with the authorities, not with the building office. This page explains that step and the one other document you can ask for before you file, the spatial planning information.

Can I ask the building office for a preliminary opinion?

You can ask for a talk, but Act 25/2025 gives you no right to one and sets no deadline or form for it. I found no provision on advice from the office before filing.

The office acts when it receives the application. It calls on you to complete a missing application within 15 days (§ 50 ods. 3). It tells the parties about the start of the proceedings within 7 days after the application is complete (§ 51 ods. 1). Nothing the office says in an informal talk binds it. The written binding opinions in the next section do bind it.

What is the discussion of the building intent?

The builder or the designer makes the project documentation available in the information system. Then they ask three kinds of body for a written position (§ 20 ods. 1).

You askYou getTime limitIf the body is silent
The planning authority (orgán územného plánovania)A binding opinion on the building intent30 days for notified and simple structures, 60 for other structures, 90 for reserved structures (Act 200/2022, § 24a ods. 5).The authority is inactive (Act 200/2022, § 24a ods. 13). The act presumes a binding opinion of compliance with the spatial plan (§ 35 ods. 1 písm. a).
An affected authority (dotknutý orgán), by the type of worksA binding opinion on the building intent30 days, or 60 days for a complex structure (§ 21 ods. 9).The office presumes it has no comments on the building intent (§ 21 ods. 9)
An affected legal person (dotknutá právnická osoba), for example a network operatorA binding statement with the requirements for the project30 days, at most 60 days for a complex structure (§ 22 ods. 5).The office presumes it has no comments and no requirements (§ 22 ods. 5)

Act 25/2025 sets 30 and 60 days for the planning authority too (§ 21 ods. 9). It does so only if a special act does not say otherwise. Act 200/2022 does say otherwise, so its periods apply to the planning authority.

The Office for Spatial Planning and Construction (Úrad pre územné plánovanie a výstavbu) keeps two lists in the information system. One lists the affected authorities and the other lists the affected legal persons (§ 21 ods. 2, § 22 ods. 1). The type of works decides which authorities you ask (§ 20 ods. 1 písm. b).

What do the authorities have to do when I ask?

An affected authority gives its opinion within its own powers. It names the legal rule behind each requirement and gives reasons (§ 21 ods. 6). If your request or the building intent is too vague for an opinion, the authority calls on you to make it more precise. The time limit stops until you do (§ 21 ods. 8).

A legal person such as a utility gives you the data you need for the building intent. It also names the concrete requirements for the project (§ 22 ods. 3). The legal person records the data on its networks in the information system. On the designer's request it provides data from the documentation of the building for a reasonable fee (§ 22 ods. 2).

If you did not ask an authority that you should have asked, you must ask later (§ 21 ods. 10).

What is the report on the discussion?

The builder or the designer writes the report (správa o prerokovaní stavebného zámeru, § 23 ods. 1). It evaluates every position and comment. It names the body that made each comment and says how you handled it. You attach all documents you collected.

The report goes with the building intent to the application (§ 50 ods. 2) and is a basis for the proceedings (§ 23 ods. 2). Decree 60/2025 sets its content (príloha č. 16). The content has five parts.

  • A list of the binding opinions and statements.
  • The date each request arrived.
  • The number and date of each position.
  • The comments and their evaluation.
  • The name of the body that made each comment.

From 1 January 2027 Act 243/2026 rewrites § 20 ods. 2. You then make available the documentation of the building intent or of the project of the building (Čl. I bod 71).

What is the spatial planning information?

It is the one document the municipality offers on request before you file. The spatial planning information (územnoplánovacia informácia) states the conditions for the use of the area and for siting a building. It also states the planning principles and the spatial and functional regulations of the binding part of the plan (Act 200/2022, § 40 ods. 13).

Two limits apply. The municipality issues it only for planning documentation approved up to 31 March 2024. It is not issued for the siting or approval of a building, and it is not a binding opinion. The paragraph sets no time limit. I found no fee item for it in the fee schedule of Act 145/1995 (version from 1 November 2026).

For a plan approved later, or for the formal answer, you use the binding opinion of the planning authority in the table above. The public part of the information system also shows planning documentation. It shows the information on the area that the planning authorities publish (Act 200/2022, § 25 ods. 2). Look there first. Then check the buildability of the land.

Which of these answers binds the building office?

AnswerEffect on the building officeSource
Binding opinion of an affected authorityBinding, if it meets the content rules. The authority itself is bound by it, unless the law or the facts change§ 21 ods. 7, 11
Binding opinion of the planning authorityThe office rejects an application whose siting does not match it§ 59 ods. 1 písm. a
Binding statement of a legal personThe office rejects an application if the statement shows that the building cannot be connected to the networks, with exceptions§ 59 ods. 1 písm. f
Spatial planning informationNot bindingAct 200/2022, § 40 ods. 13
Informal talk with the officeNo basis in the actNo provision found

Ask for every answer in writing.

What should I prepare before the discussion?

Work from the building intent. You need a designer, because the office checks that a designer made it (§ 57 ods. 2 písm. g). You also give the designer a technical brief on the purpose, the operation and the scope of the building (§ 30 ods. 1).

A site analysis helps you see which authorities and networks touch the plot. The act does not require it. Then make the documentation available and send the requests. Plan the time from the table above, and note that the planning authority and the other bodies each have their own clock.

Frequently asked questions

Is a pre-application consultation required in Slovakia?
The application needs the report on the discussion of the building intent (§ 50 ods. 2 of Act 25/2025). An informal talk with the building office is not in the act.
Can the building office give me a preliminary opinion?
Act 25/2025 has no such document and no duty to give one. Binding positions come from the planning authority, the affected authorities and the affected legal persons (§ 20 ods. 1).
What is the spatial planning information and how do I get it?
It is a document that the municipality issues on request. It states the conditions of use and siting from a plan approved up to 31 March 2024 (Act 200/2022, § 40 ods. 13). It is not binding. The act sets no time limit.
How long do the authorities take to answer?
An affected authority has 30 days, or 60 days for a complex structure (§ 21 ods. 9). A utility has 30 days, at most 60 (§ 22 ods. 5). The planning authority has 30, 60 or 90 days by structure (Act 200/2022, § 24a ods. 5).
What happens if an authority does not answer?
The office presumes that an affected authority has no comments (§ 21 ods. 9). It presumes that a legal person has no requirements (§ 22 ods. 5). The planning authority is inactive (Act 200/2022, § 24a ods. 13). The act then presumes that it has no comments and has issued a binding opinion of compliance with the spatial plan (§ 35 ods. 1 písm. a).
Does the opinion bind the building office?
A binding opinion does (§ 21 ods. 11 and § 59 ods. 1 písm. a of Act 25/2025). The spatial planning information and an informal talk do not.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 20 to 23, § 30 ods. 1, § 50, § 51 ods. 1, § 57 ods. 2, § 59 ods. 1
  2. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 24, § 24a ods. 5, 13, § 25 ods. 2, § 40 ods. 13, § 35 ods. 1 and 2
  3. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 6 ods. 3, príloha č. 16
  4. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Národná rada Slovenskej republiky, via Slov-Lex · sadzobník (word search)
  5. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 71