Site analysis
A site analysis is a study of a plot's legal limits, ground, utilities and surroundings that an architect makes before design starts.
What is a site analysis?
A site analysis is a study of a plot's legal limits, ground, utilities and surroundings that an architect makes before design starts. No act defines the term. The Building Act 25/2025 describes the work that the analysis feeds. The designer answers for the fit of the building with the binding part of the planning documents. The designer also answers for its harmony with the surroundings and the character of the place (§ 35 ods. 6 písm. d and e).
The analysis gives the architect one file for one plot. It sorts what the law fixes, what a survey measures and what a visit shows. The result goes into the building intent (stavebný zámer). The building intent states how the building sits on the land and how it connects to roads and utility networks (§ 9 ods. 2).
A client does not need to own the plot to start. The act lets a builder hold another right to the land. Examples are a right of use under a contract and a right from an easement (§ 29 ods. 1 písm. a and b). A right that the cadastre records needs no further proof (§ 29 ods. 2 písm. a).
What does a site analysis cover?
The list follows the checks that the law and the designer's duties call for. Each line names the section of the act behind it.
- Ownership and burdens. The list vlastníctva shows the plot, its owners and its burdens in parts A, B and C (162/1995 § 8 ods. 1 písm. b bod 2). See land registry extract.
- Land type. The cadastre sorts land into 11 types (§ 9). Agricultural land may serve a non-agricultural purpose only on the basis of a decision on withdrawal (220/2004 § 17 ods. 1).
- Planning limits. The binding opinion of the planning authority judges the proposed building against the binding part of the planning documents (200/2022 § 24 ods. 1). See municipal land use plan, spatial planning information and buildability of land.
- Ground and groundwater. The geological act defines the engineering-geological survey as a survey of the engineering-geological and hydrogeological conditions of an area. It serves the design and foundation of buildings and includes the stability of land prone to sliding (569/2007 § 3 písm. g). See geotechnical survey and hydrogeological survey.
- Terrain. The builder orders the geodetic work and the geodetic base documents, unless the builder and the designer agree otherwise (25/2025 § 30 ods. 2 písm. a). See geodetic survey.
- Roads and utilities. The building office refuses the application if access from a public road is not secured. It also refuses it if a legal person's statement shows that the building cannot be connected to the utility networks (§ 59 ods. 1 písm. e and f). See utility connections.
- Trees and nature. The office refuses a building that conflicts with interests that a special act protects (§ 59 ods. 1 písm. c). The pages on tree removal permits and on bioregional corridors cover existing trees and nature protection.
- Sun, wind, views and noise. The architect records these during site visits. See also daylighting study.
Which zones and hazards can stop a house on the plot?
Several limits come from outside the cadastre and the plan. There is no single protection zone. Each act sets its own zone. The forest act, for example, makes the land within 50 m of forest land a forest protection zone (326/2005 § 10 ods. 1). It requires a binding opinion of the forestry authority for the siting of buildings in that zone (§ 10 ods. 2). Other acts set other zones and other distances. See protection zone.
Flood law sets a hard limit. In an inundation area it is forbidden to place residential buildings (7/2010 § 20 ods. 5 písm. a). The inundation area is the land beside a watercourse that a flood usually covers. A flood line with a return period of 100 years is one of the lines that mark its edge (§ 20 ods. 1). See flood-prone area.
Does a house need a radon survey?
The Building Act does not mention radon. The duties come from the radiation protection act 87/2018. They fall on three moments.
| Who | Duty | Section |
|---|---|---|
| Designer of a residential building with a basement or a first above-ground floor for long stay | Take preventive measures so that indoor radon stays at or below 300 Bq/m³ as an annual average | § 130 ods. 1 |
| Owner of that building | Have the radon measured within one year from the start of use | § 130 ods. 3 |
| Whoever measured | Send a result above 300 Bq/m³ without delay to the radiation protection authority | § 130 ods. 4 |
The act has an exception. It covers a building with a layer of freely flowing air between the ground and the first above-ground floor (§ 130 ods. 1 and 3). The act does not make a radon survey a condition of the building intent application. See radon survey.
Which surveys are mandatory before design?
The act gives no fixed list of surveys for every house. It splits the work between two people. Unless the builder and the designer agree otherwise, the builder arranges the geodetic work. The builder also arranges the engineering-geological, hydrogeological and other survey work and the assessment of the effect of the building on its surroundings. The builder obtains the statements of the affected legal persons too (25/2025 § 30 ods. 2 písm. a, b and e).
The designer sets the scope of the hydrogeological survey and of other surveys, if the nature of the structure requires them (§ 35 ods. 6 písm. c). The amendment 243/2026 changes the builder's list from 1 January 2027. Its Art. I deletes the word hydrogeological from § 30 ods. 2 písm. b. The designer's duty in § 35 does not change.
A geodet carries out the geodetic and cartographic work. The geodet must meet the requirements of a special regulation (§ 40 ods. 1).
How do the findings reach the building office?
The builder or the designer makes the project documentation available in the information system. They then ask the planning authority and the affected authorities for binding opinions, and the affected legal persons for binding statements (§ 20 ods. 1). See binding opinion and binding statement.
The answers follow fixed periods. If a legal person does not answer in time, the act presumes that it has no comments and no requirements (25/2025 § 22 ods. 5).
| Who answers | Document | Period from a complete request | Source |
|---|---|---|---|
| Affected legal person, for example a utility operator | Binding statement | 30 days, at most 60 days for a complex structure | 25/2025 § 22 ods. 5 |
| Planning authority | Binding opinion | 30 days for structures that need only a notification and for simple structures, 60 days for other structures, 90 days for a reserved structure | 200/2022 § 24a ods. 5 |
A binding opinion of the planning authority is valid for two years from delivery for a house (200/2022 § 24a ods. 6).
The application for the decision on the building intent carries the project documentation and the report on the discussion (25/2025 § 50 ods. 2). See pre-application consultation.
How does a site analysis differ from site due diligence?
Land due diligence comes before a purchase and asks whether the plot is worth buying. A site analysis comes before design. It asks how to design on a plot the client chose. The two share many checks, such as the list vlastníctva, the plan and the utilities. One result often serves both. Only the architect's reading differs. The buyer's lawyer reads the title, and the architect reads the siting.
How does a site analysis relate to the architectural study?
The Building Act has four levels of project documentation. They are the building intent, the project of the structure, the project of a notified structure and the implementation project (§ 9 ods. 1). The act does not name an architectural study. The architectural study is a first design sketch that many architects make before the building intent. The site analysis comes first and sets the limits of that sketch.
The act speaks of the character of the place and not of genius loci. The designer answers for the harmony of the building with that character (§ 35 ods. 6 písm. e). The architect's record of how the plot looks, sounds and feels in different seasons is the practical side of that duty.
How do you place a house on a plot by the compass directions?
No act fixes a compass direction for a house. The Building Act and the Spatial Planning Act 200/2022 do not use the words for compass directions. The position must fit the binding part of the planning documents, the protection zones, the access and the ground. Inside those limits the architect weighs sun, wind, views and noise. See house orientation on the plot.
Frequently asked questions
- How do I place a house on a plot by the compass directions?
- No act fixes a compass direction for a house. The position must fit the binding part of the planning documents, the protection zones, the access and the ground. Inside those limits the architect weighs sun, wind, views and noise.
- What does a survey of position and height give the designer?
- It gives the designer the ground positions (polohopis) and heights (výškopis) of the plot and the objects on it. The builder orders it from a geodet, unless the builder and the designer agree otherwise (25/2025 § 30 ods. 2 písm. a). Prices differ by contractor, so ask for quotes.
- Which surveys are mandatory before design?
- The act gives no fixed list. The builder arranges the geodetic, geological and other survey work that the design needs. The designer sets the scope of the hydrogeological survey and of other surveys if the structure requires them (25/2025 § 30 ods. 2, § 35 ods. 6 písm. c).
- Is a radon survey mandatory before the building intent application?
- No. The Building Act does not mention radon. The radiation protection act puts duties on the designer and on the owner of a residential building (87/2018 § 130). The owner measures within one year from the start of use.
- When should an architect start a site analysis?
- The analysis starts when the client has a plot in mind and ends before the architectural study. The legal checks overlap with land due diligence, so the client can order both together before the purchase.
- Who does a site analysis?
- The architect leads it. A geodet does the geodetic work (25/2025 § 40 ods. 1). The builder orders the geological and other surveys. The designer sets their scope (§ 30 ods. 2, § 35 ods. 6 písm. c).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9 ods. 1 a 2, § 20 ods. 1, § 22 ods. 5, § 29 ods. 1 a 2, § 30 ods. 2, § 35 ods. 6, § 40 ods. 1, § 50 ods. 2, § 59 ods. 1
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 88
- Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 24 ods. 1, § 24a ods. 5 a 6
- Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 8 ods. 1 písm. b bod 2, § 9
- Zákon č. 220/2004 Z. z. o ochrane a využívaní poľnohospodárskej pôdy a o zmene zákona č. 245/2003 Z. z. · Národná rada Slovenskej republiky, via Slov-Lex · § 17 ods. 1
- Zákon č. 569/2007 Z. z. o geologických prácach (geologický zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 3 písm. g)
- Zákon č. 326/2005 Z. z. o lesoch · Národná rada Slovenskej republiky, via Slov-Lex · § 10 ods. 1 a 2
- Zákon č. 7/2010 Z. z. o ochrane pred povodňami · Národná rada Slovenskej republiky, via Slov-Lex · § 20 ods. 1 a 5
- Zákon č. 87/2018 Z. z. o radiačnej ochrane a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 130 ods. 1, 3 a 4