Geodetic Survey
A geodetic survey is a measurement of land or a building that a geodet makes so designers, builders and authorities work from exact positions.
What is a geodetic survey?
A geodetic survey is a measurement of land or a building that a surveyor (geodet) makes for the building process. The Slovak name is geodetické zameranie.
Neither the building act nor the geodesy act defines this term. They name activities instead. The geodesy act lists selected geodetic activities, for example boundary staking, staking out of buildings and the measurement of finished buildings (act 215/1995 Z. z., § 6).
Engineering geodesy is the part of geodesy that serves construction (§ 2 ods. 17). It covers staking-out networks, staking out and control measurement of the position of structures. It also covers measurement of the site for the design and the geodetic part of the as-built documentation.
What does a geodet do at each stage of a building project?
A geodet works before design, before building, during building and after building.
| Stage | Work of the geodet | Source |
|---|---|---|
| Before design | Checks the base data, gets map bases and documents on rights to the land, sets the reference system and surveys the original terrain | Decree 209/2025, § 1 |
| Before building | Stakes out a new building, an extension or a terrain modification and writes a staking protocol | Act 25/2025, § 42 |
| During building | Takes control measurements of terrain, geometry and position of the building | Act 25/2025, § 40 ods. 3 písm. f |
| After building | Makes the geodetic part of the as-built documentation, the as-built survey and the cadastral survey plan | Act 25/2025, § 40 ods. 3 písm. h |
The contractor must survey new underground utilities before it covers them (act 25/2025, § 32 ods. 2 písm. o). The geodet also measures displacements and deformations of a structure. The designer sets the scope of these measurements when the type of building and its use require them (§ 35 ods. 6 písm. c, § 40 ods. 3 písm. g).
What is a pre-design survey?
A pre-design survey (predprojektové zameranie) is the set of geodetic base documents that the designer needs. The decree calls them geodetic base documents for design (decree 209/2025 Z. z., § 12 ods. 1 písm. a). People search for the first name. The decree does not use it.
First the geodet checks the base data against the cadastre, the geodetic information system, the lowest approved planning documentation and the terrain (§ 1 ods. 1). Then the geodet provides these items (§ 1 ods. 2):
- map bases of the area
- documents on rights to the land
- the reference system of the building
- staking of the site boundary and of the access roads
- documentation of utilities and underground structures on the site
- a survey of the original terrain before preparatory work
- geodetic bases to remove farmland or to use forest land for other purposes
The builder orders this work. The builder ensures the geodetic work and the base documents, unless the builder and the designer agree otherwise (act 25/2025 Z. z., § 30 ods. 2 písm. a). The designer uses them to prepare the building intent and the project (§ 35 ods. 6 písm. a, b).
What are polohopis and výškopis?
Polohopis refers to the horizontal position of features. Výškopis refers to their height. The acts do not define the two words.
Decree 209/2025 lists elements of polohopis and výškopis of the terrain around the building. They belong to the data set of the as-built documentation (§ 7 ods. 2 písm. b). The cadastral map is a large-scale polohopisná mapa (act 162/1995 Z. z., § 3 ods. 10). See topographic site survey.
Who can make a geodetic survey?
A geodet must meet the requirements of a special regulation (act 25/2025, § 40 ods. 1). To authorise the results of selected geodetic activities, the geodet must be in the list or register of authorised geodets and cartographers (§ 40 ods. 1).
An authorisation verification is a clause attached to the result. The decree lists the results that need it (decree 209/2025, § 12 ods. 1). They include the geodetic base documents for design, the staking protocol, the as-built elaborate and the cadastral survey plan. An electronic result carries a qualified electronic signature of the authorised geodet (§ 12 ods. 2).
The person who gives the authorisation needs a master's degree in geodesy and cartography. That person also needs five years of practice and a pass in the qualification exam (act 215/1995, § 7 ods. 2). The as-built measurement of a simple structure or a minor structure is not a selected activity (§ 6 písm. i).
The builder ensures a geodet for the whole construction period (act 25/2025, § 30 ods. 4 písm. e). On a reserved or large building a chief geodet coordinates several geodets (§ 40 ods. 2). From 1 January 2027 the chief geodet also has the right to give the authorisation (act 243/2026 Z. z., Art. I bod 103).
How is it different from staking out, boundary staking and a cadastral survey plan?
| Activity | What it does | Source |
|---|---|---|
| Staking out of a building (vytýčenie stavby) | Marks the position of the building in the field from the staking drawings. A notified minor structure needs none | Act 25/2025, § 42 |
| Boundary staking (vytyčovanie hraníc pozemkov) | Marks the break points of a parcel boundary in the field. The result holds a staking sketch, a report, a coordinate list and a protocol | Decree 461/2009, § 51, § 54 |
| As-built survey | Records the finished building | Decree 209/2025, § 8 |
| Cadastral survey plan | Is the technical basis for entering a change in the cadastre of real estate | Act 162/1995, § 67 |
Owners must agree to the permanent marking of the staked boundary points. Without agreement the points get a temporary mark (decree 461/2009, § 53).
Frequently asked questions
- What is a geodetic survey?
- A geodetic survey is a measurement of land or a building that a geodet makes for the building process. The acts name the activities but give no single definition of the term (act 215/1995 Z. z., § 6).
- What is a predprojektové zameranie?
- It is the set of geodetic base documents for the design, such as map bases, utilities and a survey of the original terrain. The decree lists them (decree 209/2025 Z. z., § 1 ods. 2).
- Who can make a geodetic survey in Slovakia?
- A geodet who meets the requirements of a special regulation. The geodet must be in the register of authorised geodets to authorise the results of selected activities (act 25/2025 Z. z., § 40 ods. 1).
- What is the difference between polohopis and výškopis?
- Polohopis refers to horizontal position and výškopis to height. The acts do not define the words, and the decree names both in the as-built data set (decree 209/2025, § 7 ods. 2 písm. b).
- Is a geodetic survey the same as an as-built survey?
- No. The as-built survey records the finished building (decree 209/2025, § 8). A geodetic survey is the wider term for the geodet's measurements in the building process.
- Does staking out of a building need a geodet?
- Yes. A geodet must stake out a new building, an extension or a terrain modification before work starts. The rule does not apply to a minor structure that needs only a notification (act 25/2025, § 42 ods. 1).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 30, § 32, § 35 ods. 6, § 40, § 42
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (Art. I from 1 January 2027) · Národná rada Slovenskej republiky, via Slov-Lex · Art. I bod 103
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky, ktorou sa ustanovujú podrobnosti o postavení a činnosti geodeta pri príprave, zhotovovaní stavby a užívaní stavby a o výkone geodetických a kartografických činností vo výstavbe (č. 209/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 1, § 7, § 8, § 12
- Zákon Národnej rady Slovenskej republiky č. 215/1995 Z. z. o geodézii a kartografii · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 17, § 6, § 7
- Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 3 ods. 10, § 67
- Vyhláška Úradu geodézie, kartografie a katastra Slovenskej republiky, ktorou sa vykonáva zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) (č. 461/2009 Z. z.) · Úrad geodézie, kartografie a katastra SR, via Slov-Lex · § 51, § 53, § 54