Occupancy Approval Step by Step + Checklist

6 min read
A newly finished, empty room at handover, its floor still part-covered by protective sheeting

The house is standing, the facade is finished, the last worker has just packed up their tools — and only then does it sink in that one step still stands between you and moving in: occupancy approval, known in Slovakia as "kolaudácia." Since 1 April 2025, a new building act, No. 25/2025 Z. z., has been in force in Slovakia, and it changed not only the name of this procedure but also part of the documentation and steps involved. If you remember the old "kolaudačné rozhodnutie," you need to know what changed. If you're going through this for the first time, you need a clear, practical guide. That's exactly what this article is for.

Occupancy approval, old and new

Until 2025, building authorities issued what was called a "kolaudačné rozhodnutie" (occupancy decision) at the end of construction, under the now-repealed 1976 building act. The new building act introduced the term "kolaudačné osvedčenie" (occupancy certificate) — in substance a similar thing: official confirmation that the building matches its permit and can be safely used — but the form and part of the procedural requirements have changed. In everyday speech people still search for "kolaudácia," and that's fine — it's the same step in the process, just under a new legal framework. Older, legally valid occupancy decisions issued under the previous act remain valid; there's no need to "re-approve" them.

Without this official confirmation, a building cannot be legally used, cannot be assigned a house registration number, and cannot be entered into the land registry (cadastre). For buildings constructed without a permit after the new act took effect, the option of after-the-fact legalization no longer applies as loosely as it once did — all the more reason to keep your documentation in order from the start.

What you'll need — documentation

The biggest mistake homeowners make is leaving document collection until the last minute. Some documents — the energy performance certificate or the surveyor's plan, for example — have lead times measured in weeks, not days. Here's an orientation overview of what you'll typically need:

Document / taskWhat it's forTiming note
Application for occupancy approvalFormal request that starts the approval procedureFiled by the owner with the relevant building authority
As-built documentationConfirms how the building was actually constructed, including any deviations from the original designPrepared by the designer/site supervisor throughout construction
Surveyor's plan (geodetic survey)Precise measurement of the building's position on the plot, for the cadastreOrder 2-4 weeks in advance
Inspection reports (electrical wiring, lightning protection)Proof that the electrical installation is safeOnly possible once the wiring is finished
Water, sewage (and gas, if applicable) tightness testsVerifies utility connections function safely and without leaksDepends on which utilities the house uses
Chimney inspection (if applicable)Safety of the flue/exhaust pathRequired for houses with a fireplace or solid-fuel boiler
Energy performance certificateDemonstrates the building's energy performanceOrder at least a month ahead; requires an on-site inspection of the finished building
Proof of land ownership and the original building permitEstablishes legal title and consistency with the permitCopies from the original building-permit proceedings

The exact list of documents varies by building type, technical equipment (gas, chimney, wastewater treatment plant) and by the requirements of the specific building authority — it's worth confirming the precise list directly with the authority or with your architect ahead of time.

Occupancy approval, step by step

The procedure follows a clear logic — first you need complete documentation, then an on-site inspection, then the decision. In practice, it looks like this:

Protective film peeled halfway off a newly installed window frame, with plaster dust still on the sill
Occupancy approval is a check on the finished building against what was approved, not a snag list. Cosmetic defects do not block it.
  1. Check the building is actually finished. Staircases need railings, the facade needs to be complete, and every room needs finished surfaces and installed fixtures.
  2. Order the inspection reports and tests — electrical wiring, lightning protection, water and sewage tightness, and gas or chimney inspections where relevant.
  3. Arrange the surveyor's plan recording the building's actual position on the plot.
  4. Order the energy performance certificate — it requires an inspection of the finished building, so it can't be arranged earlier.
  5. Compile the as-built documentation, including records of any deviations from the original design.
  6. File the application for occupancy approval with the relevant building authority, together with all supporting documents, and pay the administrative fee.
  7. Wait for notice of the inspection date — the authority should give you reasonable advance notice before visiting the site.
  8. Attend the site inspection and be ready to show all inspection reports and documents on the spot.
  9. Fix any deficiencies the inspector identifies, and document this for the authority.
  10. Receive the occupancy certificate and keep it with the rest of your building documentation — you'll need it for the land registry entry and for any future sale of the property.

Common reasons for delay or rejection

In practice, occupancy approval gets complicated for a fairly repetitive set of reasons, most of which are avoidable with a bit of foresight:

  • Missing or unfinished railings on staircases, balconies, or galleries.
  • An unfinished facade or exterior surface treatment.
  • Deviations from the design documentation that were never properly recorded or approved.
  • Missing or incomplete inspection reports for technical installations.
  • Mismatches between the building's actual condition and the documents submitted to the authority.
  • An energy performance certificate ordered too late, delaying the whole application.

Most of this is avoidable through ongoing communication with your site supervisor and designer throughout construction — not just in the final weeks before completion.

Can I move in before occupancy approval?

Legal use of a building is tied specifically to the issuance of the occupancy certificate — moving in "on a trial basis" before it's issued isn't compliant with the law, even though it still happens in practice. The owner carries the risk: during an inspection, an insurance claim, or a future sale, a missing or delayed occupancy approval can create complications that patience in the final weeks before completion would have avoided entirely.

Conclusion

Occupancy approval isn't a bureaucratic hurdle — it's the final safeguard that a house is safe, functional, and legally habitable. The new building act changed the name and part of the formal requirements, but the substance is unchanged: gather your documents as you go, order inspections and certificates well ahead of time, and show up to the inspection prepared. If you're unsure exactly what your project requires, an architect or site supervisor who has been with the build from the start can put together a document list tailored to your house.

Frequently asked questions

What documents do I need for occupancy approval?
You'll typically need as-built documentation, a surveyor's plan, inspection reports (electrical wiring, and gas or chimney where relevant), water and sewage tightness tests, an energy performance certificate, and proof of ownership and the original building permit. The exact list varies by building type and equipment, so it's worth confirming it with the building authority in advance.
How long does occupancy approval take?
Once a complete application is filed, the authority's own procedure through to the occupancy certificate typically takes on the order of weeks. The full process, including preparing documents like the energy performance certificate and surveyor's plan, realistically takes months, so it pays to start ordering documents before construction is even finished.
What happens if something fails the inspection?
The inspector records the deficiencies found — most commonly missing railings, an unfinished facade, or missing inspection reports. The owner is given time to fix them and document the correction for the authority; only then can the procedure conclude with the occupancy certificate being issued.
Can I move in before occupancy approval is granted?
No — legal use of the building is tied specifically to the occupancy certificate being issued. Moving in before that isn't compliant with the law, and it can create serious complications during an inspection, an insurance claim, or a future sale.