Occupancy Approval Step by Step + Checklist

8 min read
A newly finished, empty room at handover, its floor still part-covered by protective sheeting

Occupancy approval (kolaudácia) is the last procedure before you live in a new house. Act 25/2025 Z. z. allows a finished building to go into permanent use only after kolaudácia (§ 66 ods. 1). This guide follows the act in the version valid from 1 November 2025 to 31 December 2026. It lists the attachments, the periods and the fee, and says what changes on 1 January 2027.

What is kolaudácia and does my building need it?

Kolaudácia is the procedure in which the building office checks a finished building. It checks that the building can run safely for the purpose it was designed for. It ends with the occupancy certificate (kolaudačné osvedčenie, § 67 ods. 1). Since 1 April 2025 the old "kolaudačné konanie" is now "kolaudácia" (§ 84 ods. 11 písm. c).

The act requires kolaudácia for three things (§ 66 ods. 1). They are a new building, a change of a finished building and a terrain work that needed a decision on the building intent. A change of a finished building is an upward extension, a side extension or an infill (nadstavba, prístavba, vstavba: § 5 ods. 1). Kolaudácia is not required for notified buildings. It is not required for building alterations either, unless an alteration comes with a change of use (§ 66 ods. 1).

The certificate states the building-technical fitness of the building for its designed purpose. It does not replace an operating permit under other rules (§ 67 ods. 2 and 3). You may use the building only for the purpose named in the certificate (§ 68 ods. 1).

Which documents do you attach to the application?

Kolaudácia starts with a proposal from the builder (stavebník). The act lists the attachments "according to the type of building" (§ 66 ods. 2). Your building office and your designer tell you which ones apply to your house. This table follows the act letter by letter.

AttachmentWhat the act saysLetter in § 66 ods. 2
Construction diaryThe site manager keeps it from the first day of the site until handover (§ 39 ods. 1)a
Final statement of the site managerCertifies that the finished building matches the verified project. Not needed for notified buildings and alterations (§ 10 ods. 3)b
As-built documentationA text and graphic record of how the building was built (§ 10 ods. 4)c
Survey documentsDocuments from staking out the position, a control protocol of the position measurement, a geometric plan for the cadastre, and a survey of the finished buildingd and i
Handover protocolThe protocol of handover and takeover. The office may waive it in justified casese
Trial operation protocolOnly if trial operation was permittedf
Product test recordsTests of samples of building products taken on the siteg
Technical equipment recordsResults of measurements and revisions of reserved technical equipment, and documents on its fitness for continuous and safe operationh
Energy certificateOnly if the building is subject to energy certification. The owner of a new building must have it on the day of filing, unless the office decides otherwise (Act 555/2005, § 8 ods. 1 písm. a)j
Binding opinions and statementsThose of affected authorities and affected legal persons that you obtained before you filedk
Local development feeProof of payment, or of an instalment due by the day of filing. Only if the fee arose and the municipality assessed itl

How does kolaudácia work step by step?

You prepare the attachments and file the proposal. After that the periods in the act set the pace.

  1. Finish the work. The building must be finished with its induced works, access and driveway (§ 66 ods. 4 písm. a).
  2. Collect the attachments. Several come from the surveyor, the energy certificate issuer and the revision technicians, so ask for them early.
  3. File the proposal with the building office responsible for the building.
  4. Receive the date of the inspection. The office announces it within 7 working days of a complete proposal. It sends the notice to you and to the affected authorities and invites the general designer and the general contractor (§ 66 ods. 3).
  5. Attend the inspection. It must take place within 30 days of the notice (§ 66 ods. 3).
  6. Remove the defects, if the office finds any. The office writes a protocol, sets a period and interrupts kolaudácia (§ 66 ods. 5). If you do not remove the defects in that period, the office stops kolaudácia (§ 66 ods. 6).
  7. Receive the certificate within 15 days of the inspection, if the building is fit for operation (§ 66 ods. 7). The office also tells the affected authorities that it issued the certificate (§ 67 ods. 4).

The parties are the builder, the owner of the building if that is another person, and the owner of the plot. If there are more than 20 parties, or a party or its address is unknown, the office announces kolaudácia by public notice (§ 66 ods. 9). The office also stops kolaudácia if the building was built against the verified project (§ 66 ods. 8). A deviation that fits the decision on the building intent and the conditions of the authorities is a different case. The designer marks it in the project and the site manager records it in the diary (§ 43 ods. 2).

Protective film peeled halfway off a newly installed window frame, with plaster dust still on the sill
The office checks the finished building against the verified project and the seven points of § 66 ods. 4.

How long does kolaudácia take?

The act gives three periods and no total time. They run one after the other.

StepPeriodCounted from
The office announces the inspection date7 working daysDelivery of a complete proposal
The inspection takes place30 daysThe announcement of the date
The office issues the certificate15 daysThe inspection

The time to remove defects is not in these periods. The office sets it case by case, and kolaudácia is interrupted meanwhile (§ 66 ods. 5). Silence of the office is not approval. The act has deemed consent only in the cases it names (§ 21 ods. 9, § 22 ods. 5, § 24 ods. 3 and § 63 ods. 7), and § 66 is not one of them.

What does the office check at the inspection?

The visit is the kolaudačná obhliadka, in English the final inspection. In § 66 ods. 4 the act lists seven points. The office finds out whether:

  • the building or its part is finished with induced works, access and driveway, and fit for separate and safe use under the verified project,
  • the defects found at the control inspections during construction were removed,
  • the technical building system and the other technical and operating equipment work,
  • the building is connected to working utility networks, where the municipality has them. This does not apply to a building that needs no connection,
  • rainwater is caught or drained so that it does not burden the surroundings,
  • the operation of reserved technical equipment is continuous and safe,
  • the building meets the required energy performance.

How much does kolaudácia cost?

The state fee for the certificate is 30 percent of the fee for the decision on the building intent for the same building type. A repeated inspection costs 20 percent of it (položka 59 písm. e and f of Act 145/1995, version from 1 November 2026). For a building with one or two flats the base fee is 300 euro (položka 59 písm. a bod 1). The certificate then costs 90 euro and a repeated inspection 60 euro. Other building types have other base fees in položka 59 písm. a.

The fee act sets a lower rate for a proposal filed by electronic means. It is 50 percent of the scheduled fee, with at most 50 euro off, unless the schedule says otherwise (§ 6 ods. 2). On top of the state fee, a municipality may assess a local development fee (§ 66 ods. 2 písm. l). The sources used here give no price for the surveyor, the energy certificate issuer or the technicians who revise the equipment. Ask each for a written quote.

What happens after you receive the certificate?

You may use the building for the purpose named in the certificate (§ 68 ods. 1). The as-built documentation is attached to the certificate (§ 67 ods. 2). The administrator of the information system sends the information about the certificate to the district office (cadastral department) (Act 162/1995, § 21 ods. 2). The cadastre enters a building that is bounded by outer walls and a roof. If the building has no súpisné číslo, the owner it enters is the person named in the certificate (§ 46 ods. 2).

Can you move in before kolaudácia?

No, not for permanent use (§ 66 ods. 1). The act makes it an offence to operate a building before the certificate is issued. The fine for a natural person is 30 to 3,000 euro (§ 79 ods. 2 písm. e and ods. 6 písm. b). Operating a building without a certificate or against it carries a fine of 30 to 15,000 euro (§ 79 ods. 3 písm. c and ods. 6 písm. c). An entrepreneur or a legal person that uses a building without a certificate faces 10,000 to 150,000 euro (§ 80 ods. 4 písm. c).

If you need a part of the building earlier, ask for early use. The office may allow it for up to 12 months. Extensions can bring it to 5 years in total (§ 70 ods. 4). Two conditions apply. Early use must not endanger the completion. The building must meet the basic requirements and the general technical requirements at its stage of work (§ 70 ods. 1). The office decides within 30 days of the application (§ 70 ods. 3). Trial operation (§ 69) serves to test the equipment. It may last up to 24 months, with extensions up to 4 years in total (§ 69 ods. 4).

What changes on 1 January 2027?

Act 243/2026 was promulgated on 7 October 2026. Its Article I changes the Building Act from 1 January 2027. These changes affect kolaudácia (Art. I, bod 149 to 162):

  • Kolaudácia covers also alterations and maintenance that were approved by a decision on the building intent (bod 149).
  • The final statement of the site manager leaves the list of attachments (bod 150).
  • The handover protocol becomes a "zápis o odovzdaní a prebratí stavby" that includes the contractor's declaration that the building matches the verified project (bod 151).
  • The owner of the building and the owner of the plot are invited to the inspection and become participating persons (bod 154 and 158).
  • In some cases the office does not assess induced works and access. One example is works that were not a condition of the permit, if you show safe use and access (bod 155).
  • A building built in stages may go through kolaudácia stage by stage, and the certificate lists the purposes with the shares of floor area. The certificate cannot be appealed (bod 160 and 162).

If your kolaudácia may run across the turn of the year, ask your building office which text applies.

What if the building was permitted under the old act or has no kolaudácia?

Suppose the siting decision or the building permit came under the old act 50/1976. A proposal for kolaudácia filed after 31 March 2025 then still follows the old rules (§ 84 ods. 5 and 6). From 1 January 2027 the new § 66 ods. 5 on induced works applies to these buildings too (§ 84a ods. 5, added by 243/2026, bod 226).

A building that was built and used without kolaudácia is another case. For such buildings § 84 ods. 7 písm. a keeps the old review of fitness for use, if the building meets the old conditions and the owner files by 31 March 2029. From 1 January 2027 that date is 31 December 2040 (243/2026, bod 224). Your building office tells you which route fits. For the step before kolaudácia see the article on handover and defect claims.

Frequently asked questions

What documents do I need for occupancy approval?
The act lists up to twelve attachments to the proposal, according to the type of building (§ 66 ods. 2). The main ones are the construction diary, the as-built documentation, the survey documents and the handover protocol. Others are the revisions of reserved technical equipment, the energy certificate and the binding opinions. The table in this article lists all of them. Your building office tells you which ones apply to your house.
How long does occupancy approval take?
The act sets three periods and no total. The office announces the inspection within 7 working days of a complete proposal. The inspection takes place within 30 days of the announcement, and the office issues the certificate within 15 days of the inspection (§ 66 ods. 3 and 7). The time to remove defects comes on top, because the office interrupts kolaudácia and sets a period.
How much does occupancy approval cost for a family house?
The state fee is 90 euro for a building with one or two flats. A repeated inspection costs 60 euro (položka 59 písm. a, e and f of Act 145/1995, version from 1 November 2026). A proposal filed by electronic means pays 50 percent of the scheduled fee. The discount is at most 50 euro, unless the schedule says otherwise (§ 6 ods. 2). A municipality may add a local development fee.
Do I need occupancy approval for an extension or a renovation?
An extension needs it, and an ordinary renovation does not. An upward or side extension and an infill are a change of a finished building (§ 5 ods. 1), and the act requires kolaudácia for such a change (§ 66 ods. 1). Building alterations need kolaudácia only if they come with a change of use. From 1 January 2027 it also covers alterations approved by a decision on the building intent (243/2026, bod 149).
Can I move in before occupancy approval?
No, not for permanent use (§ 66 ods. 1). The fine for a natural person who operates a building before the certificate is issued is 30 to 3,000 euro (§ 79 ods. 2 písm. e and ods. 6 písm. b). If you need a part of the building earlier, ask the office for early use (§ 70). It may last up to 12 months.
Is late occupancy approval possible for a house built without it?
For buildings built and used without kolaudácia, the act keeps the old review of fitness for use. The owner must file by 31 March 2029 (§ 84 ods. 7 písm. a). From 1 January 2027 that date is 31 December 2040 (243/2026, bod 224). The building must meet the old conditions, so ask your building office which route fits.
Who comes to the kolaudácia inspection?
The office announces the date to you and to the affected authorities, and it invites the general designer and the general contractor. For a reserved structure it also invites the person who did the site supervision and the future operator. It may invite other persons. It does so if it needs them to find the real state of the building. It also does so to check the suitability of the building products (§ 66 ods. 3).
Do I need an energy certificate for the kolaudácia?
Yes, if the building is subject to mandatory certification. The owner of a new building must have the certificate on the day the kolaudácia proposal is filed. The building office may decide otherwise (Act 555/2005, § 8 ods. 1 písm. a). It is an attachment to the proposal (§ 66 ods. 2 písm. j) and is valid for at most ten years (§ 7 ods. 7). At the inspection the office also checks the energy performance of the building (§ 66 ods. 4 písm. g).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 5, 10, 21, 22, 24, 39, 43, 63, 66, 67, 68, 69, 70, 79, 80, 84
  2. Zákon č. 555/2005 Z. z. o energetickej hospodárnosti budov a o zmene a doplnení niektorých zákonov · Slov-Lex · § 7 ods. 7, § 8 ods. 1 písm. a
  3. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Slov-Lex · § 21 ods. 2, § 46 ods. 2
  4. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59 písm. a, e, f, § 6 ods. 2
  5. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · čl. I bod 149 až 162, 224, 226