Site Geology, Groundwater and Radon

8 min read
A small geotechnical drilling rig on an empty grassy building plot, with soil core samples laid out in a wooden core box in the foreground

What does a geological survey of a plot find?

The Geological Act knows two surveys that meet on a family house. The engineering-geological survey studies the ground and water conditions of an area. It serves documentation and foundations of buildings. It includes the stability of land prone to sliding (569/2007 § 3 písm. g). The hydrogeological survey studies groundwater, its quantity and its quality (§ 3 písm. f). Each has three stages: search or orientation, detailed and supplementary (§ 2 ods. 3 písm. b and c).

A contractor for geological works carries out the survey, for example a business with a geological authorisation (§ 4 ods. 1 písm. a). The contractor sums up the result in a final report (§ 16 ods. 1). If the report verified groundwater quantities, it contains their calculation (§ 16 ods. 5). The orderer hands the report over free of charge to the State Geological Institute of Dionýz Štúr. The time limit is one month from approval or takeover (§ 19 ods. 1). The entries geotechnical survey and hydrogeological survey explain the terms. The survey is also part of the site analysis.

Who orders the survey and who sets its scope?

The builder arranges the engineering-geological, hydrogeological and other survey work for the design, unless the builder and the designer agree otherwise (25/2025 § 30 ods. 2 písm. b). The designer sets the scope of the hydrogeological and other surveys if the nature of the structure requires it (§ 35 ods. 6 písm. c). Agree the scope with the designer before you order the survey.

From 1 January 2027, Act 243/2026 removes the word "hydrogeological" from § 30 ods. 2 písm. b (Art. I point 88). The engineering-geological survey stays there. Before you buy, you are not yet the builder and the plot is not yours. Agree access and test pits with the owner in writing.

Can you use older geological reports?

Final reports count as environmental information (569/2007 § 19 ods. 5). When the orderer hands a report over, the orderer tells the State Geological Institute of Dionýz Štúr the conditions for access to it, including fees. Those conditions bind for ten years (§ 19 ods. 2). They do not apply to reports financed from public sources. They also do not apply to a report in which land prone to sliding was found and verified (§ 19 ods. 3 písm. b, e). An older report from the area may show the conditions found there. It speaks about your plot only if the report covered its area.

When do you need a permit to pump groundwater?

The Water Act counts pumping groundwater to lower its level as special water use (364/2004 § 21 ods. 1 písm. b bod 3). It also counts pumping and discharging groundwater when founding structures, and during a hydrogeological survey with a pumping test longer than five days (písm. g). A permit is needed unless the use is general use under § 18 to 20. The state water authority issues it (§ 21 ods. 2).

If the excavation reaches below the groundwater level, ask the water authority before pumping starts. The survey report states the water level and its measurement. The designer derives the foundation and the waterproofing from it.

What does the decree say about excavation, foundations and sealing?

Decree 532/2002 on general technical requirements for construction stays in force. It applies until the new implementing rules take effect, at the latest until 31 March 2027 (25/2025 § 84 ods. 23). A plot meant for building must have properties that allow the structure to be built and used safely. These are mainly its position, shape, size and foundation conditions (decree 532/2002 § 5 ods. 1).

An excavation must be secured against sliding (§ 22 ods. 2). An underground structure that separates the interior from the soil must be sealed against ground moisture and groundwater. Where needed, it must also be sealed against radon and other harmful substances (§ 23 ods. 3). Foundations are protected, as needed, against aggressive water and substances that damage them (§ 23 ods. 4). The site survey supplies the data on ground and water for these solutions.

Is a radon survey required before building?

The Radiation Protection Act does not mention a survey before building in § 130. It sets duties for the designer and the owner. The designer of a residential building with a basement or a ground floor meant for long stays applies preventive measures. Indoor radon must not exceed the reference level of 300 Bq/m³ as an annual average during long stays (87/2018 § 130 ods. 1).

The duty does not apply to a residential building whose ground floor is separated from the ground by a layer of freely flowing air. It also does not apply to a non-residential building built after 26 June 1992. That building needs a basement under its whole footprint, sealed against air from the basement. The owner arranges an indoor radon measurement within one year of the start of use (§ 130 ods. 3). If the result exceeds 300 Bq/m³, the owner sends it to the radiation protection authority (ods. 4). Above that level, the owner must take corrective measures (§ 132). The entry radon survey gives more.

How is the radon index of a plot determined?

The radon index of a plot measures the risk that radon migrates from the geological ground into the air (87/2018 § 2 ods. 1 písm. bj). Decree 57/2024 (annex 6 ods. 1) uses three inputs. They are the radon activity concentration in soil air, the gas permeability of the foundation soils and the local geology. The sampler takes soil air at 0.8 m below the original ground surface (ods. 5). On the planned footprint, the method needs at least 15 samples in a grid of 10 m × 10 m or denser (ods. 7). If the siting is unknown, it needs at least 15 samples and at least 100 sampling points per 10 000 m² (ods. 8). The result is the third quartile of the measured values (ods. 9).

Gas permeability of the soilLow index (kBq/m³)Medium index (kBq/m³)High index (kBq/m³)
Highbelow 1010 to below 3030 and more
Mediumbelow 2020 to below 7070 and more
Lowbelow 3030 to below 100100 and more

Only a person with a registration may provide the service of determining the radon index of a plot (87/2018 § 25 ods. 2 písm. d).

Which radon measures does the decree list?

Under decree 57/2024 (§ 6 ods. 1), the preventive measures in a residential building are:

  • determining the radon index of the plot and taking it into account in the other measures,
  • a measure against radon entering the building from the ground,
  • venting soil radon from the ground to outside the building,
  • tighter contact structures and underpressure under the building,
  • other building-technical measures.

The decree lists the measures and does not assign them to individual indexes. A measurement of indoor radon checks that they work (§ 6 ods. 3). Corrective measures after 300 Bq/m³ is exceeded reduce the radon supply into the building or raise the air exchange (§ 6 ods. 2). A radon barrier is part of radon protection.

How do you find out whether a plot lies in an inundation area?

An inundation area is land next to a watercourse that usually floods during a flood, with water spilled from the channel. Away from the channel, the flood line of a flood with medium probability bounds it. That flood reaches or exceeds its peak flow on average once in 100 years. A linear flood-protection structure can also bound it (7/2010 § 20 ods. 1). For an unembanked watercourse, the district office sets the extent by decree (§ 20 ods. 2).

The flood hazard map shows the flood line and the water depth or level, as an indication. It shows floods of low, medium and high probability (§ 6 ods. 2, 3). If water goes beyond the line on the map, no claim for compensation arises (§ 6 ods. 4).

It is forbidden to place residential buildings in an inundation area (§ 20 ods. 5 písm. a). Fences that worsen water runoff are forbidden there too. So are terrain adjustments that can worsen runoff during a flood (§ 20 ods. 6 písm. a, c). This applies by an unembanked watercourse. Where no inundation area is set or no flood hazard map is made, assess a structure against the probable flood line of a 100-year flood. The line of the largest known flood serves too (§ 20 ods. 9). See the entry flood-prone area.

Which other site risks should you check before buying?

For land with a complex geological structure or poor engineering-geological conditions, the Ministry of the Environment defines the risks of use. It does so in its opinion on the planning documentation (§ 20 ods. 3).

An old mine working is an abandoned underground mine working whose original operator and legal successor do not exist or are unknown. The Ministry of the Environment finds old mine workings and keeps their register (44/1988 § 35 ods. 1, 2). Anyone who finds an old mine working or its effects on the surface must report it at once. The report goes to the Ministry of the Environment and the Ministry of Economy (§ 35 ods. 3). The entry undermined territory gives the context. The entry seismic zone covers earthquakes.

What if the plot is on a slope?

The engineering-geological survey includes the study of the stability of land prone to sliding (569/2007 § 3 písm. g). Planning authorities must act in line with the results of geological works, also for landslide areas and radon risk (§ 20 ods. 1). A retaining wall up to 3 m high above the lowest level of the adjacent terrain is a simple structure (25/2025 § 2 ods. 6 písm. e). The text on a house on a slope and the entry retaining wall cover the context.

In what order should you proceed?

  1. Before you buy, get the owner's written consent to enter the plot and dig test pits.
  2. Agree the scope of the surveys with the designer.
  3. Order an engineering-geological survey, and a hydrogeological survey if needed, from a contractor with a geological authorisation.
  4. Have a registered person determine the radon index of the plot and give it to the designer.
  5. Check whether the plot lies in an inundation area and whether old mine workings exist nearby.
  6. If water will be pumped from the excavation, ask the water authority about a permit and check the buildability of the land.

The wider steps of choosing a plot are in the text on the check of a plot before purchase.

Frequently asked questions

Is a radon survey required before building?
The Act does not mention a survey before building in § 130. The designer of a residential building with a basement or a ground floor for long stays must apply preventive measures. Radon must stay under 300 Bq/m³ as an annual average (87/2018 § 130 ods. 1).
When is radon measured in a finished house?
The owner arranges the measurement within one year of the start of use (87/2018 § 130 ods. 3). If the result exceeds 300 Bq/m³, the owner sends it to the radiation protection authority (ods. 4).
Does a high radon index mean you should not buy the plot?
The decree does not link an index to a ban on building. It allows for measures designed for a high index (57/2024 § 6 ods. 1 písm. a). Decide after the designer assesses the plot.
Do I need a permit to pump water from an excavation?
Possibly. Pumping groundwater to lower its level and pumping when founding structures are special water use (364/2004 § 21 ods. 1 písm. b bod 3, písm. g). Unless it is general use under § 18 to 20, you need the water authority's permit.
Who hands the final report of the survey to whom?
The contractor hands the report to the orderer (569/2007 § 16 ods. 1). The orderer hands it free of charge to the State Geological Institute of Dionýz Štúr. The time limit is one month from approval or takeover (§ 19 ods. 1).
Can I build a house in an inundation area?
The Flood Protection Act forbids placing residential buildings in an inundation area (7/2010 § 20 ods. 5 písm. a). A residential building is a building in which at least half of the floor area is meant for permanent living (25/2025 § 3 ods. 2).
Whom do I tell about an old mine working on the plot?
Anyone who finds an old mine working or its effects on the surface must report it at once. The report goes to the Ministry of the Environment and the Ministry of Economy (44/1988 § 35 ods. 3).
Can I look into an older geological report?
Reports handed to the State Geological Institute of Dionýz Štúr are made available on conditions that the orderer set for ten years. The conditions do not apply to reports from public sources or to reports on land prone to sliding (569/2007 § 19 ods. 2, 3).

Sources

  1. Zákon č. 569/2007 Z. z. o geologických prácach (geologický zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 3, § 3 písm. f) a g), § 4 ods. 1, § 16, § 19 ods. 1 až 3 a 5, § 20 ods. 1 a 3
  2. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 6, § 3 ods. 2, § 30 ods. 2 písm. b), § 35 ods. 6 písm. c), § 84 ods. 23
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 88
  4. Zákon č. 364/2004 Z. z. o vodách a o zmene zákona Slovenskej národnej rady č. 372/1990 Zb. o priestupkoch (vodný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 21 ods. 1 a 2
  5. Zákon č. 87/2018 Z. z. o radiačnej ochrane a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 1 písm. bj), § 25 ods. 2 písm. d), § 130 ods. 1, 3 a 4, § 132
  6. Vyhláška Ministerstva zdravotníctva Slovenskej republiky č. 57/2024 Z. z., ktorou sa ustanovujú podrobnosti o obmedzovaní ožiarenia pracovníkov a obyvateľov z prírodných zdrojov ionizujúceho žiarenia · Ministerstvo zdravotníctva SR, via Slov-Lex · § 6, príloha č. 6
  7. Vyhláška Ministerstva životného prostredia Slovenskej republiky č. 532/2002 Z. z., ktorou sa ustanovujú podrobnosti o všeobecných technických požiadavkách na výstavbu a o všeobecných technických požiadavkách na stavby užívané osobami s obmedzenou schopnosťou pohybu a orientácie · Ministerstvo životného prostredia Slovenskej republiky, via Slov-Lex · § 5 ods. 1, § 22 ods. 2, § 23 ods. 3 a 4
  8. Zákon č. 7/2010 Z. z. o ochrane pred povodňami · Národná rada Slovenskej republiky, via Slov-Lex · § 6 ods. 2 až 4, § 20 ods. 1, 2, 5, 6 a 9
  9. Zákon č. 44/1988 Zb. o ochrane a využití nerastného bohatstva (banský zákon) · Slovenská národná rada, via Slov-Lex · § 35 ods. 1 až 3

Topic

  • Building plot