How to choose a building plot: checks before you buy

10 min read
An empty building plot marked out with survey stakes and string lines, with a trial pit exposing the subsoil

You can redraw a house. You cannot turn a plot to face the sun, and you cannot connect a network that is not in the street. So check the plot before you sign the contract. The law does not require a buyer to do this. You do it to protect yourself (land due diligence). The Building Act 25/2025 has applied since 1 April 2025. It no longer speaks of a building permit. It speaks of a decision on the building intent. Spatial planning is in Act 200/2022. This page follows both acts as they stand on 11 November 2026.

What does the municipal land-use plan allow you to build on a plot?

The answer is in the municipal land-use plan. Among other things, the plan sets the boundary of the built-up area and the way and intensity of land use. It also sets spatial and functional limits on development. Protection zones of transport and technical infrastructure are shown in it. Construction must follow the binding part of the plan, which the municipality issues as a generally binding regulation. The authority refuses an application for a decision on the building intent if the siting does not match the binding opinion of the planning authority.

So the words "building plot" in an advert are not enough. The Act means land that a planning document designates for development, and land with a building on it. Check which zone the parcel belongs to and which limits apply to it. The article How to read a municipal land-use plan explains how to read a plan.

You find an approved plan in the register of planning documents in the public part of the information system. A paper copy is at the seat of the planning authority. For a plan approved by 31 March 2024, the municipality issues on request a planning information sheet on land-use conditions and regulatives. It is not a binding opinion. Such an older plan stays valid as a basis until the municipality replaces it, and it must do so by 31 March 2032. Otherwise the plan expires on 1 April 2032. Ask the municipality whether a new plan is in preparation.

What does a land registry extract show and what should you check?

A land registry extract (list vlastníctva) has three parts, and each answers a different question.

  • Part A lists the plots and buildings that are the subject of rights. It gives area, land type, land-use code and whether the plot lies in the built-up area.
  • Part B lists the owner, the co-ownership share, the title of acquisition, plot leases and notes.
  • Part C lists easements, pledges, pre-emption rights that have the effect of property rights, and other rights agreed as property rights. It does not show the amount of the debt.

An easement tied to the ownership of a property passes with the ownership to the new owner. So it passes to the buyer. The page on the term easement and the article Protection zones and easements give details. If a plot has several co-owners, all co-owners act together in legal acts about the whole thing. If one co-owner sells only a share, the other co-owners have a pre-emption right, unless the buyer is a close person.

Ownership of real estate passes by registration in the cadastre, not by signing the contract. When the district office receives a contract for registration, it marks a plomba on the extract by the next working day. A plomba is a note that a change of rights is pending. Data from the public part of the cadastre are free but informative only. An extract issued by the district office is a public document. Data on rights, the parcel number and the land type are binding unless proved otherwise. The land type of a parcel of register "E" is not binding. The page on the land registry extract describes the document.

Can you build on arable land or near a forest?

Agricultural land may serve a non-agricultural purpose only on the basis of a decision on withdrawal. The agricultural land protection authority issues it. You need no decision to change the agricultural land type of a plot up to 1,000 m² inside the built-up area of a municipality. Even then the authority issues an opinion on the intent. An application for withdrawal includes a certificate of the soil-ecological unit (BPEJ) and the binding opinion of the planning authority.

The Act gives special protection to the best soil, which it places in quality groups 1 to 4 by BPEJ code, and to vineyards. A levy is paid for withdrawal. A government regulation sets the levy by BPEJ code, so find out the amount before you buy. The article Withdrawal of land from agricultural use describes the full procedure.

Next to a forest, a protection zone applies. It covers land up to 50 m from the boundary of the forest plot. A building in this zone needs the binding opinion of the forestry authority.

Which protection zones and limits reduce the buildable area?

Zones arise by law and apply even if the land registry extract does not list them. Check the exact position of a zone with the manager or operator.

LimitWhat the law setsSource
ForestZone of 50 m from the boundary of the forest plot. A building in it needs the binding opinion of the forestry authority.Act 326/2005, § 10
Road outside the continuous built-up areaZone measured from the axis: 50 to 100 m for motorways and higher-class roads, 15 to 25 m for lower-class roads and local roads. The road authority may grant an exception.Act 135/1961, § 11 ods. 1, 2, 5
Overhead power lineMeasured from the outermost conductor. At 1 to 35 kV with bare conductors the zone is 10 m. It is 15 m at 35 to 110 kV, 20 m at 110 to 220 kV and 25 m at 220 to 400 kV. Buildings are banned in the zone.Act 251/2012, § 43 ods. 2, 4
Public water main and sewer outside the built-up areaZone of 1.8 m from the axis on each side for pipes up to and including 500 mm diameter, 3.0 m for larger pipes.Act 442/2002, § 19 ods. 2
Inundation areaBan on residential buildings.Act 7/2010, § 20 ods. 5
Protected deposit areaBuildings unrelated to mining may not be placed there without a binding opinion. The district mining office is an affected authority.Act 44/1988, § 18 ods. 1, § 19

A zone is not always an absolute ban. More zones are in the entry on the protection zone.

Is the plot in a flood area or on undermined ground?

An inundation area is land next to a watercourse that floodwater usually covers in a flood. Away from the channel, its edge is the flood line or a flood-protection line structure. The flood line belongs to a flood whose peak flow is reached or exceeded on average once in 100 years. For an unembanked watercourse, the district office sets the extent by regulation. Sometimes the area is not set and there is no flood hazard map. Then the authority judges the siting of a building against the probable 100-year flood line or the largest known flood. More is in the entry on the flood risk zone.

The acts do not use the term "undermined territory". The Mining Act knows the protected deposit area and old mine workings. The Ministry of the Environment keeps a register of old workings. A person who finds an old working or its effects on the surface must report it. The report goes to the Ministry of the Environment and the Ministry of the Economy.

What does the flood hazard map show?

The map shows where water can flood the land in three kinds of flood. A flood with a low probability returns once in 1,000 years or less often, or has an exceptionally dangerous course. A flood with a medium probability returns once in 100 years. A flood with a high probability returns once in 10 years. The map shows the flood line, the water depth or level and, where needed, the flow speed. These data are indicative. If water goes beyond the line on the map in a real flood, no claim for compensation arises. So the line is a basis for a decision, not a guarantee. The administrator of the water courses of water-management significance prepares the map and updates it at set intervals.

Must you deal with the seismic zone when you buy a plot?

The Building Act gives you no such duty, because it does not mention earthquakes. The designer sets the structural design to Eurocode 8 (EN 1998-1). In it each state marks seismic zones on a national map. Inside one zone the reference peak ground acceleration is the same. The ground type adjusts that acceleration. It follows from the shear-wave velocity in the top 30 m or from other soil parameters, so from a survey. The values for Slovakia come from a national annex, which this page does not print. More is in the entry on the seismic zone. Your designer can tell you.

How do you find out whether the plot is an environmental burden?

The Act on environmental burdens relies on an information system of environmental burdens. The ministry enters a burden there once it has identified it. Anyone who suspects a burden may report it to the Ministry of the Environment or to the district office in the region's seat. The originator must remove the burden. The originator may be unknown, or may have ceased to exist or died with no legal successor. Then the district office in the region's seat names the owner of the property as the obligated person. Among other cases, it does not name the owner who proves two things. In the first, the owner proves that he inherited the property and did not continue the activity. In the second, the owner proves that he did not continue it after he acquired the property and could not know of the burden then. For a plot of a former factory, landfill or petrol station, ask the seller and the district office whether a burden is on record. Do this before you sign.

Does the plot need a ground survey and a radon check?

Unless the builder and the designer agree otherwise, the builder arranges the engineering-geological, hydrogeological and other survey work needed for the design documents. The designer sets the extent of the hydrogeological and other surveys if the character of the building requires it. So the Act does not speak of a survey for every house. It speaks of the work that the design needs. From 1 January 2027, Amendment 243/2026 removes the word "hydrogeological" from this provision. The article Plot geology, groundwater and radon explains when a survey pays off. For a slope, see A house on a slope.

The Building Act does not mention radon. The Radiation Protection Act applies to a residential building with an underground floor or a first above-ground floor meant for long stays. The designer of such a building must apply preventive measures. Radon in indoor air must not exceed the reference level of 300 Bq/m³ as an annual average during long stays. The owner must arrange a measurement within one year of the start of use. So the reference level applies to the air in the house, not to the soil. The entry on the radon survey explains the background.

How do you check access and utilities?

When it decides on the building intent, the authority refuses the application if the building has no access from a public road with enough capacity. It also refuses it if an affected legal person states that the building cannot connect to the public water main, sewer or electricity network. This does not apply if the building needs no connection or the networks are not within reach.

The network manager issues a binding statement with specific requirements for the design. The period is 30 days, and at most 60 days for complex structures. If the manager issues no statement, it is presumed to have no comments. The builder requests the statements, unless the builder and the designer agree otherwise, and they relate to the building intent. So before you buy, ask the operators at least for written information on the networks and their capacity. On the designer's request, an affected legal person must provide data on its networks for a reasonable fee. The entry on utility connections and the article A plot without utility connections cover connections.

If access crosses another person's land, an easement arises by a written contract, and the right is acquired by registration in the cadastre. A verbal agreement with the neighbour is not enough. The law allows a court to create a right of way for the owner of a building who has no other access. This provision does not mention an empty plot. A road authority decides on the connection of a driveway to a road. For a building this is part of the proceeding on the building intent. Also find the owner of the road: municipalities own local roads, but private persons may own purpose-built roads.

How do you tie the purchase contract to the result of your checks?

The Civil Code allows the creation of a right or duty to depend on a condition. A suspensive condition means that its fulfilment decides whether the legal effects start. So you can write a condition into the contract, for example a positive result of the access or utility check. Leave the wording to a lawyer or a notary. You do not need to own the plot to build on it. A builder can also be a person who holds another right to the plot, such as a contractual right of use or an easement.

What does an architect assess that the registers do not show?

Registers do not show sun, shade, slope or the shape of the parcel. You see them on a site visit, best after rain and in winter. The designer is responsible for the match of the building with the binding part of the plan. The designer is also responsible for its fit with the surroundings and the character of the place. The designer also sets the extent of the surveys. So ask the designer before you sign what house fits the parcel. The article Orienting a house to the compass points covers orientation. The article A house in town or in a satellite? helps you compare a town plot with a location outside town.

In what order should you do the checks?

  1. Read the municipal land-use plan and find which zone the parcel belongs to and which development limits apply.
  2. Download the land registry extract and the cadastral map. Go through part C and have a surveyor stake out the boundaries.
  3. Find the land type, the protection zones, the flood area and the protected deposit area.
  4. Ask the network managers for written information on the networks and their capacity.
  5. Check the legal access and the owner of the access road.
  6. Walk the plot with an architect and sign the contract with a suspensive condition. The article How building a house works in Slovakia describes the whole path from plot to occupancy.

Frequently asked questions

What does it mean that a plot is a building plot?
The Act defines a building plot as land that a planning document designates for development, and land with a building on it. It is not a single field in a register. Access from a public road and the ability to connect the building to networks also decide. Without them, the authority refuses the application for a decision on the building intent.
Can you build a house on arable land?
Agricultural land may serve a non-agricultural purpose only on the basis of a decision on withdrawal, and the house must match the land-use plan. The agricultural land protection authority issues the decision, and a levy by BPEJ code is paid for withdrawal. Inside the built-up area, no decision is needed to change the land type of a plot up to 1,000 m².
Can you buy a plot in a municipality with no land-use plan?
Every municipality must have a municipal land-use plan, unless its whole territory is in a microregion plan. A municipality with no plan must approve one by 31 March 2032, and the self-governing region issues its binding opinion. If it still has no plan after that date, a building may be sited only in the built-up area. The cadastre record of 1 January 1990 defines that area. A family house is not among the exceptions outside it.
How do you find out whether a utility line crosses the plot if the land registry extract does not show it?
An easement is in part C of the land registry extract if it is registered. Protection zones, however, arise by law even if the extract does not list them. An affected legal person must keep data on its networks and, on the designer's request, provide them for a reasonable fee. So ask the operators and have the line position checked on site.
Is it enough that the neighbour lets you cross his land?
No. An easement arises by a written contract, and the right is acquired by registration in the cadastre. An agreement without registration does not create the right. If the building has no access from a public road, the authority refuses the application for a decision on the building intent.
Is a ground survey required for every house?
The Act does not say so. The builder arranges the engineering-geological, hydrogeological and other survey work needed for the design, unless the builder and the designer agree otherwise. The designer sets the extent of the surveys if the character of the building requires it. A radon measurement in the house is a separate duty of the owner under the Radiation Protection Act.
Who is responsible for an environmental burden on a plot you bought?
The originator is responsible for the burden. The originator may be unknown, or may have ceased to exist or died with no legal successor. Then the district office in the region's seat names the owner of the plot as the obligated person. Among other cases, it does not name the owner who proves one of two things. Either he inherited the plot and did not continue the activity. Or he did not continue it after acquiring the plot and could not know of the burden then. So ask before you buy whether a burden is on record.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 7 ods. 1, § 21 ods. 1, § 22 ods. 2, 3 a 5, § 29 ods. 1, § 30 ods. 2, § 35 ods. 6, § 59 ods. 1, § 49 ods. 1, Čl. IV
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 88
  3. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 22 ods. 1, 3, 4 a 5, § 24 ods. 5, § 31 ods. 5, § 34 ods. 5 a 8, § 40 ods. 2 až 4 a 13, § 40e ods. 1
  4. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 8 ods. 1 písm. b bod 2, § 44 ods. 1, § 68 ods. 4, § 69 ods. 3, § 70 ods. 2
  5. Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 36 ods. 1 a 2, § 133 ods. 2, § 139 ods. 1, § 140, § 151n ods. 2, § 151o ods. 1 a 3
  6. Zákon č. 220/2004 Z. z. o ochrane a využívaní poľnohospodárskej pôdy a o zmene zákona č. 245/2003 Z. z. · Národná rada Slovenskej republiky, via Slov-Lex · § 12 ods. 1 a 2 písm. a a l, § 17 ods. 1, 2, 3 a 5
  7. Zákon č. 326/2005 Z. z. o lesoch · Národná rada Slovenskej republiky · § 10 ods. 1 a 2
  8. Zákon č. 135/1961 Zb. o pozemných komunikáciách (cestný zákon) · Národná rada Slovenskej republiky · § 3b ods. 1 a 3, § 3d ods. 3 a 4, § 11 ods. 1, 2 a 5
  9. Zákon č. 251/2012 Z. z. o energetike a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 43 ods. 2 a 4
  10. Zákon č. 442/2002 Z. z. o verejných vodovodoch a verejných kanalizáciách a o zmene a doplnení zákona č. 276/2001 Z. z. o regulácii v sieťových odvetviach · Slov-Lex · § 19 ods. 2
  11. Zákon č. 7/2010 Z. z. o ochrane pred povodňami · Národná rada Slovenskej republiky, via Slov-Lex · § 6 ods. 1 až 4, § 20 ods. 1, 2, 5 a 9
  12. Zákon č. 87/2018 Z. z. o radiačnej ochrane a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 130 ods. 1 a 3
  13. Zákon č. 44/1988 Zb. o ochrane a využití nerastného bohatstva (banský zákon) · Slovenská národná rada, via Slov-Lex · § 18 ods. 1, § 19, § 35 ods. 2 a 3
  14. Eurocode 8: Seismic Design of Buildings, Worked examples, EUR 25204 EN (2012), chapter 1 by E. C. Carvalho · Joint Research Centre of the European Commission · 1.2.2.1, 1.2.2.2, 1.2.3, 1.2.4
  15. Zákon č. 409/2011 Z. z. o niektorých opatreniach na úseku environmentálnej záťaže a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 3, 8, § 3 ods. 1, 2, § 4 ods. 3, 5

Topic

  • Building plot