Building permit documentation

Building permit documentation (DSP) is the old name for the design documents that are now the building intent and the project of the building.

What is building permit documentation (DSP)?

Building permit documentation (dokumentácia pre stavebné povolenie, DSP) is the name for the design documents filed with a building permit application. It belongs to the rules valid until 31 March 2025. The Building Act 25/2025 Z. z. and the decree 60/2025 Z. z. do not use the name DSP. Since 1 April 2025 the act names the building intent (stavebný zámer) and the project of the building (projekt stavby). People still search for DSP, so this page shows which current document answers the same need.

Does a case started before 1 April 2025 still follow the old rules?

Yes, in the cases the act lists. The old rules still apply to a submission that reached the building office by 31 March 2025 (§ 84 ods. 4 písm. a). They also apply to a procedure that the office started by that date (§ 84 ods. 4 písm. b).

Take a case with a zoning decision (územné rozhodnutie) from the old regime. The old rules also apply to its later application for a building permit (§ 84 ods. 5). The same holds for a later application to change the structure before completion, for early use or for the occupancy decision. If a building permit was issued and no zoning decision was needed, the old rules apply to the same later steps (§ 84 ods. 6). A new case follows the new acts. The building permit page explains the old procedure.

Which documents replace DSP under the Building Act?

The act names four levels of project documentation (§ 9 ods. 1). The act does not map DSP to one level. The table shows each level with its definition.

LevelWhat the act says it isSource
Building intent (stavebný zámer)Text and drawings of the urban, architectural and basic building design. It covers fire safety, siting, and links to roads and utility networks. It is the basis for the procedure on the building intent.§ 9 ods. 2, decree annex 15
Project of the building (projekt stavby)Text and drawings of the architectural and building-technical design, in line with the building intent. It is the basis for building the structure.§ 9 ods. 3, decree annex 17
Project for notification (projekt stavby na ohlásenie)The same kind of text and drawings for a structure that needs a notification.§ 9 ods. 4, decree annex 14
Execution project (vykonávací projekt)Detailed elaboration of the verified project of the building. It is mandatory for a reserved structure (vyhradená stavba).§ 9 ods. 5, decree annex 18

When the designer asks affected bodies for binding opinions, the designer may share the building intent alone. The designer may also share it together with the project of the building (§ 20 ods. 2). The implementation project page covers the last level.

What does the building intent documentation contain?

The building intent documentation has five parts (decree 60/2025, annex 15). They are a list of documentation, a summary report, site drawings, documentation of building objects, and annexes. The scope depends on the place, the type and the size of the structure and on the requirements of affected bodies. The drawings of the building objects use scale 1:200 or 1:100, depending on the size of the structure. The site plan drawing page lists the site drawings. For the design stage before the building intent, see architectural study.

What does the project of the building contain?

The project of the building has five main parts (decree 60/2025, annex 17). It refines the design from the building intent and takes account of the conditions in the decision on the building intent.

  • A, list of documentation: the building ID if the information system assigned one, the name and place of the building, and the revision. The first list is revision 00. It names the designer responsible for each part.
  • B, summary report: identification data of the building, the builder and the designer. It also holds the purpose and size of the building, the compliance with the binding part of the land-use plan and the capacity figures. It adds the description, the effect on the environment and the expected total cost. The cost serves to set administrative fees and the condition for a work of art.
  • C, site drawings: SIT.001 to SIT.005.
  • D, documentation of each building object by profession: a technical report and drawings. Plans, sections and elevations use scale 1:100 or 1:50, or another scale suited to the structure. The structural part includes a calculation that a reviewer can test.
  • E, annexes: the geodetic survey of the original terrain, verified by an authorised geodesist and cartographer, and the fire safety solution. Where needed, the annexes also hold the energy assessment of the building and extra surveys.

How does the building office verify the project of the building?

The authority that issued the decision on the building intent verifies the project on the builder's request (§ 65 ods. 1). The builder attaches the project and the compliance clauses (doložky súladu) of affected bodies. The period for verification is 30 days (§ 65 ods. 2).

The authority verifies that the text and drawings agree with the decision and with the conditions of affected bodies (§ 65 ods. 3). If the clauses do not agree or the project differs from the decision, the authority returns the request with reasons. A verification clause records the result (§ 65 ods. 5). It loses effect if work does not start within two years, unless the authority set a longer period (§ 65 ods. 6). The application form for verification is in annex 5 of the decree (§ 4 ods. 5).

Who prepares the documentation and who answers for it?

A designer (projektant) may prepare every level of project documentation (§ 35 ods. 1). Only an authorised person can be a designer or general designer (§ 35 ods. 4). If several designers work on one project, the general designer coordinates them (§ 35 ods. 3). The general designer answers to the builder for completeness and usability (§ 35 ods. 5). The designer answers for the building intent as the builder requires. The designer answers for the project of the building as the decision requires (§ 35 ods. 6 písm. a, b). The designer of record page explains the role.

In what form does the builder submit the documentation?

As a rule, the designer prepares the documentation in electronic form. It goes into the information system of the Office for Spatial Planning and Construction (§ 8 ods. 3). Files are stored by stage of the procedure, by building, by profession and by revision (decree § 6 ods. 12). If a submission is on paper, two complete copies go to the building office (decree § 6 ods. 14). Each text title page and each drawing frame shows the name of the drawing and of the building. It also shows the builder, the level of documentation, the designer and the date. A drawing frame also shows the scale (decree § 6 ods. 11).

What changes from 1 January 2027?

Act 243/2026 Z. z. amends the Building Act. Articles I to XIII apply from 1 January 2027. Two changes touch this topic.

  • A new § 65 ods. 4 applies if the procedure covered the project of the building under § 20 ods. 2. If the decision needs no rework, the authority verifies the project after the decision becomes final.
  • In § 9 ods. 4, a simplified drawing or the maker's assembly documentation is enough in three cases. The cases are a small structure that is not a building, works that do not touch the load-bearing structure, and outdoor works.

The Building Act page lists the other changes.

Frequently asked questions

What is DSP in Slovakia?
DSP is the abbreviation of dokumentácia pre stavebné povolenie, the design documents filed for a building permit under the rules valid until 31 March 2025. The Building Act 25/2025 Z. z. and the decree 60/2025 Z. z. do not use the name. Since 1 April 2025 the documents are the building intent and the project of the building.
What does the project for a building permit contain under the new act?
The new act has no building permit. The project of the building has five parts: list of documentation, summary report, site drawings, documentation of building objects and annexes (decree 60/2025, annex 17). The building intent has the same five parts in a less detailed form (annex 15).
What must I attach to the request to verify the project?
Attach the project of the building and the compliance clauses of affected bodies (§ 65 ods. 2 of Act 25/2025 Z. z.). The request uses the form in annex 5 of the decree 60/2025 Z. z. The authority verifies the project within 30 days.
Does a case filed before 1 April 2025 still use the old documentation?
Yes. The old rules apply to a submission that reached the building office by 31 March 2025. They also apply to a procedure started by that date (§ 84 ods. 4). They also apply to later steps after a zoning decision or a building permit issued under the old rules (§ 84 ods. 5, 6).
How long does verification of the project of the building take?
The period is 30 days (§ 65 ods. 2). The authority may verify the project together with the decision on the building intent if the procedure covered both documents (§ 65 ods. 2). A verification clause loses effect if work does not start within two years, unless the authority set a longer period (§ 65 ods. 6).
Is there a fixed price for the documentation?
No fixed price appears in the act on architects. Architects and engineers provide services for a fee (§ 11 ods. 1 of Act 138/1992 Zb.). Ask the designer for a written offer that names the documents in scope.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 8, § 9, § 20 ods. 2, § 35, § 65, § 84 ods. 4 to 6
  2. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, Slov-Lex · § 4 ods. 5, § 6 ods. 11 to 14, annex 14, 15, 17
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated text) · Národná rada Slovenskej republiky, Slov-Lex · Art. I points 40, 143 to 148
  4. Zákon č. 138/1992 Zb. o autorizovaných architektoch a autorizovaných stavebných inžinieroch · Slov-Lex · § 11 ods. 1