Cost estimate for the building application
A cost figure for the application is the expected total cost that the designer states in the building intent and the form repeats.
What is a cost estimate for the building application?
A cost figure for the application is a number, not a priced budget, that Decree 60/2025 asks for in the building intent.
The page title is the old Slovak name "Predbežný rozpočet pre stavebné konanie". Neither Act 25/2025 nor Decree 60/2025 uses it. I found no priced budget or cost estimate among the documents that the building office asks for. The term "stavebné konanie" also belongs to the past. Since 1 April 2025 it is project verification (overenie projektu stavby), as § 84 ods. 11 of the Building Act says.
The decree asks for one figure. It calls it "predpokladané celkové náklady stavby alebo súboru stavieb", the expected total cost of a building or a set of buildings. The rest of this page says where the figure goes and what it does. I did not find the old name in the text of the repealed Act 50/1976 (version 15.03.2025). Its document rules sat in a decree that I did not read, so this page does not describe the old requirement.
Does the building office require a cost estimate?
No budget is on the list of attachments. Under § 50 ods. 2 of Act 25/2025 the applicant attaches two things to the application. They are the project documentation made by an authorised person and the report on the discussion of the building intent. The act names no other document.
The only cost item is the expected total cost inside the building intent. It is one point of the summary report, not a separate document. Decree 60/2025 sets no method to calculate it and no accuracy. The decree names a bill of quantities (code VYV) and a budget (code ROZ) only in its file-naming scheme (príloha č. 24). It does not list either as content of the building intent or of an application.
Where does the cost figure appear?
| Document | What it asks for | Decree 60/2025 |
|---|---|---|
| Application for the decision on the building intent | Part F "Údaje o správnom poplatku": the expected cost of the building for the fee, rounded to whole euro | príloha č. 2 |
| Application for project verification | The same part F | príloha č. 5 |
| Application to verify a change of the project | The same part F | príloha č. 6 |
| Application for temporary or early use | The same part F | príloha č. 7 |
| Application for kolaudácia | The same part F | príloha č. 8 |
| Building intent, summary report, point 9 | Expected total cost of the building or set of buildings, and the way of financing if public money pays in whole or in part | príloha č. 15 |
| Project of the building, summary report, point 9 | The same two items | príloha č. 17 |
The form for a notification (príloha č. 11) has no cost field. A notified minor structure pays a fixed fee instead.
Point 9 of the summary report gives two purposes for the cost. The first is to set the administrative fee. The second is to set the conditions for placing a work of art. The sections below explain both.
How does the cost change the administrative fee?
Only for an engineering structure. Item 59 of the fee schedule in Act 145/1995 prices a building by its number of dwellings or its floor area, not by cost. A house with one or two dwellings pays 300 eur whatever it costs.
For an engineering structure the fee follows the estimated cost of the building intent without VAT. Up to 60 000 eur the fee is 300 eur. Over 60 000 eur up to 200 000 eur it is 800 eur. The upper bands rise to 20 000 eur for a cost above 50 000 000 eur. The full list is on administrative fees for building procedures.
What is the work of art rule?
A public authority that builds a new publicly funded building for public use sets aside part of the money for a work of art. The share is at least 0.5 % of the expected value, with a ceiling of 500 000 eur per building (§ 30 ods. 7 of Act 25/2025).
The rule applies from a minimum value (§ 30 ods. 8). The minimum is 500 000 eur for buildings for education, health care, culture and social affairs, and for buildings that are public space. For other buildings it is 1 000 000 eur. Buildings for state security and defence are outside the rule (§ 30 ods. 9). A private client who builds a house does not meet this rule.
Who prepares the figure?
The designer prepares the building intent, and so the figure in it (§ 57 ods. 2 písm. g). The builder files the application electronically on the official form (§ 50 ods. 1). The designer works from your brief. Under § 30 ods. 1 you give the designer a technical brief (technické zadanie) that states the purpose, the operation and the scope of the building.
The act does not say which cost method to use. A designer can agree the method and the level of detail with you in the design contract. Slovak law sets no tariff for design work. See the architect's fee.
How is this figure different from a construction budget?
The figure in the application is one number. The other documents on this site are longer and have a different job.
| Document | What it contains | In Decree 60/2025 |
|---|---|---|
| Cost figure for the application | One number, the expected total cost | Asked for in the forms and in point 9 of the summary report |
| Indicative cost estimate (orientačný rozpočet) | An early estimate, made before the drawings are detailed | Not asked for |
| Bill of quantities (výkaz výmer) | The work items with measured quantity and unit, no price | A file-name code only (príloha č. 24) |
| Construction budget (rozpočet stavby) | A priced list of the work items, with quantity and unit price for each | A file-name code only (príloha č. 24) |
You can use an indicative cost estimate or a budget to find the number for the application. The decree does not require either.
Does a bank need a budget?
A bank sets its own conditions for a loan, so ask the bank what it needs. Neither Act 25/2025 nor Decree 60/2025 mentions a loan. This page covers only what the building office asks for.
Which documents does the building office ask for instead?
The office works from the building intent and the report on its discussion (§ 57 ods. 1, 2). The page on building permit documentation explains the old name "dokumentácia pre stavebné povolenie" (DSP). The decree sets the content of each level of the documentation in its annexes.
Frequently asked questions
- Do I need a cost estimate to apply for a building permit?
- No. Act 25/2025 lists only the project documentation and the report on the discussion as attachments (§ 50 ods. 2). The building intent states the expected total cost as one figure (Decree 60/2025, príloha č. 15, B bod 9).
- What is the expected total cost in the application?
- It is one number, not a priced budget. You enter it on the form, rounded to whole euro, for the administrative fee. The designer also states it in the summary report of the building intent.
- Does the cost change the fee for a family house?
- No. A building with one or two dwellings pays 300 eur whatever its cost (Act 145/1995, item 59 písm. a bod 1). Cost sets the fee only for an engineering structure (bod 13).
- What is the difference between a cost estimate and a bill of quantities?
- A bill of quantities lists the work items with measured quantity and unit, and no price. A budget adds a unit price to each item. The application asks for neither, only a single total.
- Which authority checks the cost figure?
- I found no rule that sets a method or a tolerance for the figure. The decree names the figure and its purpose, the fee and the work of art condition. Ask the building office how it uses it in your case.
- Does a public building need a work of art?
- Only if a public authority builds it, with public money, for public use, above a minimum value. The set-aside is at least 0.5 % of the expected value, up to 500 000 eur per building (§ 30 ods. 7 to 9 of Act 25/2025).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 30 ods. 1, 7 to 9, § 50 ods. 1, 2, § 57 ods. 1, 2, § 84 ods. 11
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · príloha č. 2, 5 to 8 časť F, príloha č. 11, príloha č. 15 a 17 časť B bod 9, príloha č. 24
- Zákon č. 145/1995 Z. z. o správnych poplatkoch · Národná rada Slovenskej republiky, via Slov-Lex · sadzobník položka 59 písm. a bod 1, 13