Bill of quantities
A bill of quantities (výkaz výmer) is a list of the work items of a building with the measured quantity and unit of each item.
What is a bill of quantities?
A bill of quantities (Slovak: výkaz výmer) is a list of the work items of a building with the measured quantity of each item. Each line has a description, a unit such as m², m³ or pieces, and a quantity taken from the drawings.
A budget (rozpočet) adds a unit price to each line. Decree 60/2025 lists the two as separate documents, with the file-name codes VYV for výkaz výmer and ROZ for rozpočet. See construction budget for the priced version.
Where do the quantities come from?
The quantities come from the drawings. Annex 18 of Decree 60/2025 says the drawings of a execution project (vykonávací projekt) list the proposed materials and the products and elements.
The annex adds that the drawings must be detailed enough to derive volume, area and linear specifications of materials from them. A bill of quantities is therefore a measured extract of the drawings, not a separate design.
The quality of the list depends on the quality of the drawings. If a detail is not drawn or not described, nobody can measure it. The item is then missing from the list and from every price built on it.
Does Slovak law require a bill of quantities for a house?
No. The content of every level of documentation is set out in annexes 14 to 23 of Decree 60/2025. None of them lists a výkaz výmer or a budget as a required part.
The decree names the documents only in Annex 24, in the code list for file names. A designer may deliver the list and upload it under the code VYV, but the decree does not make it a condition of a permit.
The levels of documentation are set in § 9 of Act 25/2025. They are the building intent (stavebný zámer) and the building project (projekt stavby). They also include the building project for a notified building (projekt stavby na ohlásenie) and the execution project. The execution project is mandatory only for a reserved structure (vyhradená stavba), see reserved structure.
| Level | Source | Required content on cost |
|---|---|---|
| Building intent (stavebný zámer) | Decree 60/2025, Annex 15 | Estimated total cost of the building, in the summary report |
| Building project (projekt stavby) | Decree 60/2025, Annex 17 | Estimated total cost of the building, in the summary report |
| Execution project (vykonávací projekt) | Decree 60/2025, Annex 18 | Drawings from which material quantities can be derived |
Does public procurement require a výkaz výmer?
The Public Procurement Act 343/2015 does not use the term výkaz výmer. It does mention an item budget (položkový rozpočet) of a bid.
Under § 53 ods. 1, the evaluation committee may correct an item budget. The total price of the bid must stay the same, and the correction must not affect another evaluation criterion.
The act binds the contracting authorities listed in § 7 ods. 1, such as the state and municipalities. A private person who builds a house is not bound by it, and may set the form of the tender freely.
How does a bill of quantities help when you compare contractor offers?
If every contractor prices the same list, the offers differ in unit prices and not in scope. This is the use of the list in a contractor tender.
Without a common list, each contractor measures the work on their own. One offer may then leave out an item that another includes, and the totals do not compare.
What happens to work that is not in the list?
The contract decides. If a household client and a firm agree a price by budget, the Civil Code applies in most cases. Under § 635 ods. 1 the price may not rise without the client's consent.
The same paragraph says the contractor may charge work and costs outside the budget only in two cases. The client approved them in writing, or ordered the work later in writing.
The Commercial Code applies instead if both parties are businesses and the contract relates to their business (§ 261 ods. 1). Under § 547 ods. 1 the use of a budget does not change the price. Paragraph 2 lets the contractor claim an increase for unforeseeable work if the budget was stated as not guaranteed to be complete.
Check which code governs your contract for work before you rely on the list to cap the price.
What should you check in a bill of quantities?
Check that the list covers every part of the building you see in the drawings. Check that each line has a unit and that the unit matches the item.
Ask the preparer which drawings and which version the quantities come from. If the drawings change, the list must change with them.
Who prepares the bill of quantities?
None of the acts cited here assigns the task to a profession. The design contract should say who delivers it, in which form, and from which level of drawings.
The architect of the practice prepares the drawings from which the quantities are measured. Ask in the architect's offer whether the list is part of the fee. See architect fee.
Frequently asked questions
- What is a bill of quantities?
- A bill of quantities (výkaz výmer) is a list of the work items of a building with the measured quantity of each. Each line has a description, a unit and a quantity taken from the drawings.
- What is the difference between a výkaz výmer and a rozpočet?
- A výkaz výmer lists items and quantities. A rozpočet adds a unit price to each item and gives a total. Decree 60/2025 lists them as separate documents with the codes VYV and ROZ.
- Do I need a výkaz výmer to get a permit?
- No. The annexes of Decree 60/2025 set the content of the building intent, building project and execution project. They do not list a výkaz výmer or a budget as a required part.
- Does the public procurement act require a výkaz výmer?
- Act 343/2015 does not use the term. It only allows the committee to correct an item budget of a bid if the total price stays the same (§ 53 ods. 1). The act does not bind a private client.
- Can the contractor charge for work that is missing from the list?
- It depends on the contract. Under the Civil Code a price agreed by budget may not rise without the client's consent. Extra work needs written approval or a written order (§ 635 ods. 1). Between businesses the Commercial Code § 547 applies.
- Who prepares a bill of quantities?
- The acts cited here do not name a profession. Agree in the design contract who delivers it. It is measured from the drawings, for example from an execution project.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 9 ods. 1, 3 a 5
- Vyhláška č. 60/2025 Z. z. o informačnom systéme a o obsahu dokumentácie · Slov-Lex · § 6, prílohy č. 15, 17, 18, 24
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 634 ods. 1, § 635, § 636 ods. 1
- Zákon č. 513/1991 Zb. Obchodný zákonník · Slov-Lex · § 261 ods. 1, § 536 ods. 1, § 546, § 547
- Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Slov-Lex · § 6 ods. 1, § 7 ods. 1, § 53 ods. 1
- Financing a House Build: Mortgage and ŠFRB
- Choosing a Builder and Comparing Quotes
- Why Builds Overrun and How Much Contingency to Hold
- Shell, Holodom or Turnkey: What You Buy
- Design Phases and the Payment Schedule
- From Study to Implementation Project: Documentation Stages
- House Build Cost per m²: What Sets the Price
- Construction Budget and Bill of Quantities: Why Bids Differ