The final cost of a build can differ from the first offer. That does not always mean a dishonest firm. The differences have a few sources. This post shows where they come from and how the contract price divides the risk. It also covers written changes and the contingency.
Where do the extra costs on a build come from?
The gap between the contract price and the final price can be split into a few groups. Each has its own origin, its own moment when it shows up and its own way to keep it under control.
| Source of overrun | When it shows up | What limits it |
|---|---|---|
| Incomplete documentation | At the first detail missing from the project | A finished project and bill of quantities before the firm is chosen |
| Changes by the builder during construction | Any time during construction | Fittings decided in advance, changes only in writing |
| Unknown ground or condition of an old building | During earthworks and demolition | A survey and trial openings while the design is still on paper |
| Price changes | Between the offer and the purchase of materials | A short time from offer to start, and price rules in the contract |
| Items outside the offer | During finishing and moving in | A list of exclusions and a separate budget for them |
Documentation that never reached the detail
An offer is as precise as its basis. The act knows four levels of design documentation: the building intent, the project, the project for notification and the implementation project (§ 9 ods. 1 of act 25/2025). If a firm prices the house from documents that lack floor build-ups, window details or service routes, someone must decide them for the firm.
If that happens on site, the decision falls under programme pressure and without a comparison of alternatives. The designer is not responsible for changes and deviations from the verified project that the designer did not approve (§ 35 ods. 10). A decision on paper is cheaper.
Changes during construction
Every change has three price tags: the new work, the work that must be redone and the time of the other trades. The act separates two cases. First case: the deviation does not conflict with the decision on the building intent or with the conditions set by affected authorities and legal persons. Then the designer marks it in the project, and the site manager records it in the minutes and the construction diary. Second case: this route is not open. Then the building office decides that verification of a change of the project or new proceedings on the building intent are needed (§ 43 ods. 2 and 3). The change before completion entry describes the term.
Verification of a change of the project during construction costs 50 % of the verification rate. See the fee schedule of act 145/1995, item 59 b) point 7, version from 1 November 2026.
Ground and old structures
The builder arranges engineering-geological and hydrogeological surveys unless agreed otherwise with the designer (§ 30 ods. 2 písm. b). The designer sets the scope of the surveys (§ 35 ods. 6 písm. c). A geotechnical survey before the foundations are designed replaces an assumption about the ground with data. In a renovation, trial openings help while the house is still on paper.
Prices that move
Suppose the price was agreed under a price regulation and the regulation changes. The contractor must then tell you in writing without delay and state the new price. You may withdraw from the contract (Civil Code, § 635 ods. 2 and 3). The law has no special rule for other price movements, so regulate them in the contract.
What is often missing from the contractor's price, and what should you check?
The worst overrun is an item that was never in the offer. Before you sign, go through the offer and find out for each of these items whether it is in the offer or paid separately:
- the staircase, especially when a joiner or metalworker supplies it,
- terraces and balustrades,
- external works from paving to fencing,
- utility connections,
- the kitchen and fitted furniture.
The contractor may charge work and costs outside the budget only after written approval or a written order (§ 635 ods. 1). The article on shell, weathertight shell and turnkey explains what each level of supply includes.
Fixed sum, budget or estimate: who carries the risk?
The type of contract price does not decide what the build costs. It decides who pays when reality departs from the basis. The Civil Code distinguishes three ways to set the price in a contract for work.
| Question | Fixed sum | Price by budget | Price by estimate |
|---|---|---|---|
| Where in the Civil Code | § 631, § 636 ods. 1 (first sentence) | § 635 ods. 1 | § 636 ods. 1 and 2 |
| What the act says | The contractor does the work for the agreed price at their own risk | The price cannot rise without the client's consent, and work outside the budget only after written approval or order | If the estimate will be exceeded substantially, the contractor must tell the client in writing at once and state the new price. Otherwise there is no right to the difference |
| What the client should do | Describe the scope in writing (§ 632) | Ask for an itemised budget | After the notice, decide whether to withdraw (§ 636 ods. 2) |
Between businesses the Commercial Code may apply instead (§ 261 ods. 1). Under it a price set by a budget stays the price even when the budget is part of the contract (§ 547 ods. 1). Sometimes the contract shows that the budget is not guaranteed to be complete. Then the contractor may ask for a reasonable increase for unforeseeable work outside the budget (§ 547 ods. 2). The client may withdraw if the increase would exceed the budget price by more than 10 % (§ 547 ods. 5). The contractor must report the need for an increase without undue delay, or the claim lapses (§ 547 ods. 6).
The budget rests on a bill of quantities. It describes what a fixed sum covers. It also gives a budget a list of items, and changes are priced against that list. The act does not list a bill of quantities among the levels of documentation, so agree on it in the contract with the designer.
What does the documentation say about cost, and what does the budget say?
The expected total cost in the documentation is not a price from a contractor. Decree 60/2025 Coll. requires it in the summary report of the building intent (annex 15) and of the building project (annex 17). Its purpose is to set the administrative fees and the conditions for placing a work of art.
The decree does not list a budget or a bill of quantities among the compulsory parts of the documentation. Only annex 24 mentions them, in its list of codes for file names. There the bill of quantities (VYV) and the budget (ROZ) are two separate documents. The contract with the designer or the contractor therefore decides what a budget contains. For a price by budget, state in it that the budget is itemised and which bill of quantities it comes from. Only then do you know what is outside the budget (Civil Code § 635 ods. 1).
How should extra and omitted work be agreed?
Extra work is work beyond the contract. Omitted work is contract work that is not carried out. The procedure has five steps:
- A written proposal before the work. Whoever proposes the change describes it so that it can be priced. The note "different tiles in the bathroom" is not enough. You need the product, the area and the laying method.
- Pricing from the rates in the offer. If the item exists in the priced budget, its rate applies. New items are priced separately and checked by comparison.
- Effect on the programme. A change that moves completion must say so at once, not in the final invoice.
- Deduction of omitted work. If new work replaces the original, the original is deducted at the contract price.
- Signatures of both parties and a list of changes. A numbered list with a running total shows the state of the budget at any time.
The Civil Code already requires writing (§ 635 ods. 1). If a change affects the verified project, the builder may call an extraordinary inspection before the work. The site manager, the designer or the person appointed for construction supervision can propose it (§ 43 ods. 2). If the office did not attend, the builder sends it the minutes. The office approves them within three days of delivery. From 1 January 2027 it will be seven working days (act 243/2026, Art. I point 106).
During the works the designer may supervise conformity with the project (§ 35 ods. 10). The designer may approve changes of the project only after preliminary approval by the fire protection specialist for the affected part (§ 35 ods. 11). The designer does not approve the price. You decide whether to pay for a change.
Which design choices need a separate price line?
Distinctive materials must not hide under ordinary alternatives in the budget. The rule is the same for each of them. Draw it in detail in the project and price it as a separate item of the bill of quantities. Ask a firm that has built it before.
- Exposed concrete is structure and surface, so state the required surface quality in the project.
- Facing brick should be drawn with its details. Do not price it as ordinary masonry.
- Natural stone cladding should be designed with its fixings and priced for the chosen stone and format.
How large a contingency should you keep?
No act that we read sets a contingency percentage. A contingency is not a fixed percentage added to the bottom of the budget. It is the sum of the risks that are not yet resolved. Its size depends on the stage you are at.
| Stage | What is still unknown | What the contingency should cover |
|---|---|---|
| Building intent | Structure, standard, ground, prices | Almost everything, which is why the estimate is only a range |
| Project | Details, fittings, real offers | Refining the project and choosing the firm |
| Implementation project, bill of quantities and contract | Ground, old structures, your own changes | Risks that the contract does not pass to the contractor |
| During construction | Only the remaining open risks | Whatever is left. Release the contingency step by step |
The method is simple. For each open risk, write down what it could cost, and the contingency is the sum. Then you know what it is for, and when a risk closes you know how much to release. Keep it outside the contract price.
Why count life-cycle cost when cutting?
When the budget does not add up, every item looks like a candidate for a cut. Life-cycle costing counts the purchase together with operation, maintenance and replacements. So before a cut, ask what the item costs during use.
It is easier to reduce the floor area, simplify the shape or postpone what you can add without touching the structure. Examples are floor tiles, the kitchen, fitted furniture and external works. The cost of the design is covered in how much an architect costs, and the price per square metre in house build cost per m².
In short: a build does not overrun all at once but through small decisions made late or only verbally. A finished project, a priced bill of quantities and changes agreed in writing help. So does a contingency built from a list of risks. Together they make the overrun an item you can manage.