Why Builds Overrun and How Much Contingency to Hold

8 min read
A site table in daylight with printed construction drawings, a tape measure and a calculator, a half-built masonry wall softly out of focus behind

The final cost of a build can differ from the first offer. That does not always mean a dishonest firm. The differences have a few sources. This post shows where they come from and how the contract price divides the risk. It also covers written changes and the contingency.

Where do the extra costs on a build come from?

The gap between the contract price and the final price can be split into a few groups. Each has its own origin, its own moment when it shows up and its own way to keep it under control.

Source of overrunWhen it shows upWhat limits it
Incomplete documentationAt the first detail missing from the projectA finished project and bill of quantities before the firm is chosen
Changes by the builder during constructionAny time during constructionFittings decided in advance, changes only in writing
Unknown ground or condition of an old buildingDuring earthworks and demolitionA survey and trial openings while the design is still on paper
Price changesBetween the offer and the purchase of materialsA short time from offer to start, and price rules in the contract
Items outside the offerDuring finishing and moving inA list of exclusions and a separate budget for them

Documentation that never reached the detail

An offer is as precise as its basis. The act knows four levels of design documentation: the building intent, the project, the project for notification and the implementation project (§ 9 ods. 1 of act 25/2025). If a firm prices the house from documents that lack floor build-ups, window details or service routes, someone must decide them for the firm.

If that happens on site, the decision falls under programme pressure and without a comparison of alternatives. The designer is not responsible for changes and deviations from the verified project that the designer did not approve (§ 35 ods. 10). A decision on paper is cheaper.

Changes during construction

Every change has three price tags: the new work, the work that must be redone and the time of the other trades. The act separates two cases. First case: the deviation does not conflict with the decision on the building intent or with the conditions set by affected authorities and legal persons. Then the designer marks it in the project, and the site manager records it in the minutes and the construction diary. Second case: this route is not open. Then the building office decides that verification of a change of the project or new proceedings on the building intent are needed (§ 43 ods. 2 and 3). The change before completion entry describes the term.

Verification of a change of the project during construction costs 50 % of the verification rate. See the fee schedule of act 145/1995, item 59 b) point 7, version from 1 November 2026.

Ground and old structures

The builder arranges engineering-geological and hydrogeological surveys unless agreed otherwise with the designer (§ 30 ods. 2 písm. b). The designer sets the scope of the surveys (§ 35 ods. 6 písm. c). A geotechnical survey before the foundations are designed replaces an assumption about the ground with data. In a renovation, trial openings help while the house is still on paper.

Prices that move

Suppose the price was agreed under a price regulation and the regulation changes. The contractor must then tell you in writing without delay and state the new price. You may withdraw from the contract (Civil Code, § 635 ods. 2 and 3). The law has no special rule for other price movements, so regulate them in the contract.

What is often missing from the contractor's price, and what should you check?

The worst overrun is an item that was never in the offer. Before you sign, go through the offer and find out for each of these items whether it is in the offer or paid separately:

  • the staircase, especially when a joiner or metalworker supplies it,
  • terraces and balustrades,
  • external works from paving to fencing,
  • utility connections,
  • the kitchen and fitted furniture.

The contractor may charge work and costs outside the budget only after written approval or a written order (§ 635 ods. 1). The article on shell, weathertight shell and turnkey explains what each level of supply includes.

Fixed sum, budget or estimate: who carries the risk?

The type of contract price does not decide what the build costs. It decides who pays when reality departs from the basis. The Civil Code distinguishes three ways to set the price in a contract for work.

QuestionFixed sumPrice by budgetPrice by estimate
Where in the Civil Code§ 631, § 636 ods. 1 (first sentence)§ 635 ods. 1§ 636 ods. 1 and 2
What the act saysThe contractor does the work for the agreed price at their own riskThe price cannot rise without the client's consent, and work outside the budget only after written approval or orderIf the estimate will be exceeded substantially, the contractor must tell the client in writing at once and state the new price. Otherwise there is no right to the difference
What the client should doDescribe the scope in writing (§ 632)Ask for an itemised budgetAfter the notice, decide whether to withdraw (§ 636 ods. 2)

Between businesses the Commercial Code may apply instead (§ 261 ods. 1). Under it a price set by a budget stays the price even when the budget is part of the contract (§ 547 ods. 1). Sometimes the contract shows that the budget is not guaranteed to be complete. Then the contractor may ask for a reasonable increase for unforeseeable work outside the budget (§ 547 ods. 2). The client may withdraw if the increase would exceed the budget price by more than 10 % (§ 547 ods. 5). The contractor must report the need for an increase without undue delay, or the claim lapses (§ 547 ods. 6).

The budget rests on a bill of quantities. It describes what a fixed sum covers. It also gives a budget a list of items, and changes are priced against that list. The act does not list a bill of quantities among the levels of documentation, so agree on it in the contract with the designer.

What does the documentation say about cost, and what does the budget say?

The expected total cost in the documentation is not a price from a contractor. Decree 60/2025 Coll. requires it in the summary report of the building intent (annex 15) and of the building project (annex 17). Its purpose is to set the administrative fees and the conditions for placing a work of art.

The decree does not list a budget or a bill of quantities among the compulsory parts of the documentation. Only annex 24 mentions them, in its list of codes for file names. There the bill of quantities (VYV) and the budget (ROZ) are two separate documents. The contract with the designer or the contractor therefore decides what a budget contains. For a price by budget, state in it that the budget is itemised and which bill of quantities it comes from. Only then do you know what is outside the budget (Civil Code § 635 ods. 1).

How should extra and omitted work be agreed?

Extra work is work beyond the contract. Omitted work is contract work that is not carried out. The procedure has five steps:

  1. A written proposal before the work. Whoever proposes the change describes it so that it can be priced. The note "different tiles in the bathroom" is not enough. You need the product, the area and the laying method.
  2. Pricing from the rates in the offer. If the item exists in the priced budget, its rate applies. New items are priced separately and checked by comparison.
  3. Effect on the programme. A change that moves completion must say so at once, not in the final invoice.
  4. Deduction of omitted work. If new work replaces the original, the original is deducted at the contract price.
  5. Signatures of both parties and a list of changes. A numbered list with a running total shows the state of the budget at any time.

The Civil Code already requires writing (§ 635 ods. 1). If a change affects the verified project, the builder may call an extraordinary inspection before the work. The site manager, the designer or the person appointed for construction supervision can propose it (§ 43 ods. 2). If the office did not attend, the builder sends it the minutes. The office approves them within three days of delivery. From 1 January 2027 it will be seven working days (act 243/2026, Art. I point 106).

During the works the designer may supervise conformity with the project (§ 35 ods. 10). The designer may approve changes of the project only after preliminary approval by the fire protection specialist for the affected part (§ 35 ods. 11). The designer does not approve the price. You decide whether to pay for a change.

Which design choices need a separate price line?

Distinctive materials must not hide under ordinary alternatives in the budget. The rule is the same for each of them. Draw it in detail in the project and price it as a separate item of the bill of quantities. Ask a firm that has built it before.

  • Exposed concrete is structure and surface, so state the required surface quality in the project.
  • Facing brick should be drawn with its details. Do not price it as ordinary masonry.
  • Natural stone cladding should be designed with its fixings and priced for the chosen stone and format.

How large a contingency should you keep?

No act that we read sets a contingency percentage. A contingency is not a fixed percentage added to the bottom of the budget. It is the sum of the risks that are not yet resolved. Its size depends on the stage you are at.

StageWhat is still unknownWhat the contingency should cover
Building intentStructure, standard, ground, pricesAlmost everything, which is why the estimate is only a range
ProjectDetails, fittings, real offersRefining the project and choosing the firm
Implementation project, bill of quantities and contractGround, old structures, your own changesRisks that the contract does not pass to the contractor
During constructionOnly the remaining open risksWhatever is left. Release the contingency step by step

The method is simple. For each open risk, write down what it could cost, and the contingency is the sum. Then you know what it is for, and when a risk closes you know how much to release. Keep it outside the contract price.

Why count life-cycle cost when cutting?

When the budget does not add up, every item looks like a candidate for a cut. Life-cycle costing counts the purchase together with operation, maintenance and replacements. So before a cut, ask what the item costs during use.

It is easier to reduce the floor area, simplify the shape or postpone what you can add without touching the structure. Examples are floor tiles, the kitchen, fitted furniture and external works. The cost of the design is covered in how much an architect costs, and the price per square metre in house build cost per m².

In short: a build does not overrun all at once but through small decisions made late or only verbally. A finished project, a priced bill of quantities and changes agreed in writing help. So does a contingency built from a list of risks. Together they make the overrun an item you can manage.

Frequently asked questions

Can the builder raise the price if we agreed a fixed sum?
Only as far as the contract and the law allow. For a fixed sum the contractor does the work for the agreed price at their own risk (Civil Code, § 631). If the price regulation on which the price was agreed changes, the contractor must notify you and you may withdraw (§ 635 ods. 2 and 3). Before signing, read the clauses on price changes.
Who pays for extra work caused by an error in the design?
Towards the contractor the client usually pays when the work is outside the basis and the budget. The rules on a price by budget and by estimate apply (§ 635, § 636). The designer's liability depends on the contract with the designer and on the case. Act 25/2025 lists what the designer is responsible for (§ 35 ods. 6) and excludes unapproved changes (§ 35 ods. 10).
Should I tell the builder how large my contingency is?
You do not need to. The contingency is your tool for risks that are not yet priced. It is not part of the contract price, so it belongs neither in the contract nor in the budget the contractor sees. You may tell the designer who helps you assess changes.
Is a geotechnical survey worth it even for a small house?
A survey replaces an assumption about the ground with data before the foundations are designed. Unless you agree otherwise with the designer, the builder arranges it (§ 30 ods. 2 písm. b) and the designer sets its scope (§ 35 ods. 6 písm. c). The size of the house does not change this.
What should I do when the builder invoices extra work after it was done?
Ask for its description and pricing from the rates in the offer, as if it were a proposal. For a price set by budget, work outside it is charged only after written approval or a written order (Civil Code, § 635 ods. 1). Also check whether the work was already in the scope of the contract.
When can I start releasing the contingency?
When the risk it covered is closed. Once the foundations are finished, the uncertainty about the ground disappears. Once the main materials are bought, so does the risk of their prices moving. Once the kitchen and tiles are chosen, so does the risk of undecided items. Release the contingency after these steps, not by the calendar, and keep part of it until the final account.
Is a bill of quantities the same as a budget?
Decree 60/2025 Coll. lists them in annex 24 as two separate documents (VYV and ROZ) and does not make them a compulsory part of the documentation. The contract therefore sets their content. A budget can be the basis of the price under the Civil Code (§ 635) and the Commercial Code (§ 547).
How can I get a better price for a build?
Quotes can be compared only if the firms price the same scope. Send all of them the same documents and the same bill of quantities. A private client need not follow the public procurement act (§ 7 ods. 1 of Act 343/2015 Coll.), so it may ask for revised quotes. If the quotes exceed your budget, change the scope or the standard and let the firms price the revised bill. Under a Commercial Code contract, the price must be agreed, or at least the way to determine it (§ 536 ods. 3).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9 ods. 1, § 30 ods. 2, § 35 ods. 6, 10 a 11, § 43 ods. 2 a 3
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 106
  3. Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 631, § 632, § 634 ods. 1, § 635, § 636
  4. Zákon č. 513/1991 Zb. Obchodný zákonník · Slov-Lex · § 261 ods. 1, § 536 ods. 3, § 547 ods. 1, 2, 5 a 6
  5. Zákon Národnej rady Slovenskej republiky č. 145/1995 Z. z. o správnych poplatkoch · Národná rada Slovenskej republiky, via Slov-Lex · Sadzobník, položka 59 písm. b) bod 7
  6. Vyhláška č. 60/2025 Z. z. o informačnom systéme a o obsahu dokumentácie · Slov-Lex · prílohy č. 15, 17 a 24
  7. Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 7 ods. 1

Topic

  • Costs and fees