Contract for work
A contract for work is a contract that obliges a contractor to build or repair a building for a client at a set price.
What is a contract for work?
A contract for work (zmluva o dielo) is a contract that obliges a contractor (zhotoviteľ) to perform a work for a client (objednávateľ). The client pays an agreed price. Civil Code § 631 says the contractor performs the work at the contractor's own risk. Commercial Code § 536 ods. 1 says the same and adds that the client pays the price.
Commercial Code § 536 ods. 2 says the work always includes the construction, assembly, maintenance, repair or alteration of a building or part of a building. A new house and a renovation both fit this definition. Under Commercial Code § 537 ods. 3 the contractor works independently and follows the client's instructions only if the contractor expressly agreed to follow them.
Which code governs a contract for work, the Civil Code or the Commercial Code?
It depends on who signs the contract. Two codes regulate the contract for work: the Civil Code (Občiansky zákonník, zákon č. 40/1964 Zb., § 631 and following) and the Commercial Code (Obchodný zákonník, zákon č. 513/1991 Zb., § 536 and following).
| Who signs | Code | Basis |
|---|---|---|
| A private household that does not act in a business, and a building firm | Civil Code § 631 and following | Commercial Code § 261 ods. 1 covers relations between entrepreneurs. Civil Code § 52 ods. 4 defines the consumer |
| Two entrepreneurs, when the contract relates to their business | Commercial Code § 536 and following | Commercial Code § 261 ods. 1 |
| Parties outside § 261 who agree in writing on the Commercial Code | Commercial Code, with limits for a consumer | Commercial Code § 262 ods. 1 and 2, Civil Code § 52 ods. 2, § 54 ods. 1 |
Commercial Code § 261 ods. 8 says the nature of the parties when the obligation arises decides which code applies. A private person who builds a family house outside a business is a consumer under Civil Code § 52 ods. 4. The firm is a trader (obchodník) under § 52 ods. 3.
Commercial Code § 262 lets parties outside § 261 agree in writing that the Commercial Code governs their relation. This choice does not remove consumer protection. Civil Code § 52 ods. 2 says consumer provisions apply whenever they favour the consumer, and Civil Code provisions take priority in every relation with a consumer. Civil Code § 54 ods. 1 forbids contract terms that depart from the Civil Code to the consumer's disadvantage. Ask a lawyer to read any contract that names the Commercial Code for a private client.
Civil Code § 648 applies the consumer purchase rules to made-to-order work only when the thing is movable. It does not cover a building.
What does the contract say, and what does the law add?
A contract for work states what the contractor builds, for what price and by when. Civil Code § 632 says that, unless the work is done on the spot, the contractor gives the client a written confirmation of the order. The confirmation states the object of the work, its scope, quality, price and time of completion.
Civil Code § 633 ods. 1 obliges the contractor to perform the work as the contract says, properly and at the agreed time. If a binding technical standard applies to the work, the work must conform to it. Commercial Code § 536 ods. 3 requires the contract to state the price or the method to set it, unless the parties show they want a contract without it.
For a house, name these items in the contract:
- the project documentation the contractor builds from
- the price and how it is set
- the start and completion dates
- how the client takes over the work
- the guarantee period and how the client reports defects (see defects liability period)
Can the contractor raise the price after signing?
It depends on how the price was set and on which code applies. Neither code lets a contractor raise a price at will.
| Topic | Civil Code | Commercial Code |
|---|---|---|
| When the client pays | § 634 ods. 2: after the work is finished unless agreed otherwise. If the work is done in parts or needs considerable costs, the contractor may ask for reasonable advances during the work | § 548 ods. 1: at the time agreed in the contract. The claim to the price arises when the work is performed |
| Price set by a budget | § 635 ods. 1: the price cannot rise without the client's consent. Extra work counts only if the client approved it in writing or ordered it later in writing | § 547 ods. 2 and 3: if the budget does not guarantee completeness or is non-binding, the contractor may claim a reasonable increase for unforeseeable work |
| Price set by an estimate | § 636 ods. 1 and 2: if the estimate will be exceeded considerably, the contractor warns the client in writing without delay. Otherwise the contractor loses the right to the difference. The client may withdraw | § 547 ods. 5 and 6: the contractor loses the right to an increase if the contractor does not report it without delay. The client may withdraw if the increase is more than 10 % above the budget price |
Commercial Code § 549 covers changes after signing. If the parties change the scope and do not agree the effect on the price, the price changes in proportion to the change.
Who bears the risk of damage during construction?
Under the Civil Code the contractor bears it until handover. Civil Code § 647 says the contractor answers for damage to a building made to order until the client takes it over. The exception is damage that would have happened anyway.
The Commercial Code sets a different default. Under § 542 ods. 1 the client bears the risk of damage and owns the work when the contractor builds on the client's plot, unless the contract says otherwise. Agree in the contract who insures the work. See construction insurance.
How does handover work, and is it the same as occupancy approval?
No. Handover is between the client and the contractor. Occupancy approval (kolaudácia) is a procedure before the building authority.
Civil Code § 645 ods. 1 says the client takes over the work within one month after the planned completion time. If the contractor finished later, the month runs from the actual completion. Commercial Code § 554 ods. 1 says the contractor meets the obligation by finishing the work properly and handing it over. The client takes over the finished work (§ 537 ods. 2). If the client appointed a construction supervisor, the supervisor can join the inspection. If either party asks, both sign a protocol of the handover (§ 554 ods. 6). If the contract requires tests, the work counts as finished when the tests succeed (§ 555 ods. 2).
Stavebný zákon (zákon č. 25/2025 Z. z.) § 66 ods. 1 says a completed building can go into permanent use only after kolaudácia. The authority issues a kolaudačné osvedčenie (§ 67). See building handover and occupancy approval.
Can the client or the contractor withdraw from the contract?
Yes, in the cases the codes list. Civil Code § 642 ods. 1 lets the client withdraw until the work is finished. The client then pays for the work already done, unless the contractor can use the result elsewhere, and the reasonable costs.
Under § 642 ods. 2 the client may also withdraw if the work will clearly be late or improper. This applies only if the contractor does not remedy it in a reasonable period. Commercial Code § 550 gives a similar right. The client may inspect the work. The client may withdraw if the contractor does not remedy the breach in a reasonable period and the breach would be substantial.
The contractor may withdraw under Civil Code § 638 ods. 1 if the work needs the client's cooperation. The contractor sets a reasonable period and warns of the consequence. The contractor may withdraw after the period passes without result.
Is the contractor liable for subcontractors?
Yes. Commercial Code § 538 says the contractor answers for a work done by another person as if the contractor did it. Civil Code § 633 ods. 2 says the contract and the nature of the work decide whether the contractor works personally or has the work done under the contractor's responsibility.
Does public procurement law apply to a private client?
Not by default. Zákon č. 343/2015 Z. z. § 7 lists the contracting authorities: the state, municipalities, higher territorial units, public-interest bodies and their associations. A private person who pays from own funds is not on that list. Under § 8 ods. 1 a person who is not a contracting authority follows the rules in one case. A contracting authority provides more than 50 % of the funds for certain works contracts. See contractor tender.
Frequently asked questions
- What is a contract for work (zmluva o dielo)?
- A contract for work is a contract in which a contractor performs a work for a client at an agreed price. Civil Code § 631 and Commercial Code § 536 define it. Under Commercial Code § 536 ods. 2 the work always includes construction, assembly, maintenance, repair or alteration of a building.
- Which code applies to a contract with a building firm?
- For a private household that does not act in a business, the Civil Code (§ 631 and following) applies. For two entrepreneurs, the Commercial Code (§ 536 and following) applies when the contract relates to their business (Commercial Code § 261 ods. 1). The nature of the parties when the obligation arises decides (§ 261 ods. 8).
- Can a private client and a firm choose the Commercial Code?
- Commercial Code § 262 lets parties outside § 261 agree in writing that the Commercial Code governs. The choice does not remove consumer rights. Civil Code § 52 ods. 2 and § 54 ods. 1 keep the consumer's protection. Have a lawyer read such a clause.
- What is the statutory warranty period for building work?
- For a building made to order under the Civil Code the záručná doba is three years (§ 646 ods. 3). It runs from the day the client should have taken the building over. The Commercial Code sets no statutory period. Its § 562 ods. 2 písm. c sets the latest time to notify later defects, five years for buildings. See the defects liability period page.
- Can the contractor raise the price after signing?
- Not at will. Under the Civil Code a budget price cannot rise without the client's consent (§ 635 ods. 1). Under the Commercial Code the contractor may claim an increase only for a budget that does not guarantee completeness or is non-binding (§ 547 ods. 2 and 3). The client may withdraw if the increase is more than 10 % (§ 547 ods. 5).
- What should the contract say about defects?
- State the guarantee period, the day it starts and how the client reports a defect. Commercial Code § 429 ods. 2 says a period named in the contract applies. Under § 563 ods. 1 the záručná doba starts at handover. Civil Code § 646 ods. 5 says a contractor who refuses liability gives the reasons in writing.
Sources
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 52 to 54, § 100, § 101, § 631 to 648, § 652 to 655
- Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261, § 262, § 392, § 397, § 429 to 431, § 436 to 441, § 536 to 565
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 66 ods. 1, § 67 ods. 1 and 2
- Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 7 ods. 1, § 8 ods. 1
- Financing a House Build: Mortgage and ŠFRB
- Choosing a Builder and Comparing Quotes
- House Handover and Defect Claims
- Why Builds Overrun and How Much Contingency to Hold
- Shell, Holodom or Turnkey: What You Buy
- Design Phases and the Payment Schedule
- House Build Cost per m²: What Sets the Price
- What to Build a House From: Masonry, Timber or CLT
- How Much Does an Architect Cost, and What Do You Get?
- Construction Budget and Bill of Quantities: Why Bids Differ