Construction warranty period

A construction warranty period is the time after takeover in which a contractor answers for defects of a building, three years under the Civil Code.

What is a construction warranty period in Slovakia?

A construction warranty period is the time after takeover in which a contractor answers for defects of a building. Slovak law calls it záručná doba. The Building Act 25/2025 sets no warranty period. The rules sit in the Civil Code and the Commercial Code, and they depend on which code governs the contract for work.

Under the Civil Code the contractor is liable for defects the thing has at takeover (§ 646 ods. 1). For a building the contractor is also liable for defects that appear later in the záručná doba (§ 646 ods. 3). The Commercial Code works differently, as the next sections show.

How long is the warranty period for a building?

For a Civil Code contract the period is three years from the day the client should have taken the building over (§ 646 ods. 3). The table lists each period with its paragraph. It matches the page defects liability period.

SituationSourcePeriod
Civil Code contract, building made to orderCivil Code § 646 ods. 3Three years from the day the client should have taken the building over
Civil Code contract, parts of a buildingCivil Code § 646 ods. 3An implementing regulation may set a shorter period for some parts, but not shorter than eighteen months
Civil Code contract, defect shows earlyCivil Code § 646 ods. 2A defect that shows within 24 months of the takeover day is presumed to have existed at takeover, unless the contractor proves otherwise
Civil Code contract, repair or alteration of a thingCivil Code § 654 ods. 1Three months unless agreed or set otherwise by a special regulation. For building works at least eighteen months
Commercial Code contract, buildingCommercial Code § 562 ods. 2 písm. cNo statutory záručná doba. A later defect must be notified without delay and at the latest five years after handover
Commercial Code contract, other workCommercial Code § 562 ods. 2 písm. cThe same notice rule with a latest limit of two years after handover

No implementing regulation under § 646 ods. 3 that shortens the period for a part of a building, such as a roof, was found in the sources read. Check your contract for any shorter or longer period.

Is there a five-year warranty under the Commercial Code?

No. The five years in Commercial Code § 562 ods. 2 písm. c are not a guarantee period. They are the latest time to notify a defect that could be found only later, when the work is a building. A court does not grant the client a right from a defect that the client did not notify in time.

Where a guarantee covers the defect, the záručná doba of the guarantee applies instead of that limit (§ 562 ods. 2 písm. c). Commercial Code § 560 ods. 2 makes the contractor liable for defects the work has at handover. The contractor is also liable for later defects if a breach of the contractor's duties caused them (§ 560 ods. 3).

When does the warranty period start?

It starts at takeover of the building. Under Civil Code § 646 ods. 3 the three years run from the day the client should have taken the building over. Under Commercial Code § 563 ods. 1 the záručná doba of a work starts with the handover of the work.

Kolaudácia is a separate step. Under Building Act § 66 ods. 1 a new building may go into permanent use only after kolaudácia. The warranty period does not wait for it. See building handover and occupancy approval.

The period can pause. Under a Commercial Code guarantee the period stops while the client cannot use the item. This applies to defects the contractor is liable for (§ 430, applied by § 563 ods. 2). For a repair or alteration under the Civil Code, the time from the claim to the repair does not count (§ 655 ods. 2).

What is the difference between statutory liability and a guarantee?

Statutory liability is the contractor's liability for defects that the law sets. A guarantee (záruka) is a written promise that the work stays fit for use for a set time (Commercial Code § 429 ods. 1). It can come from the contract or from a statement such as a záručný list. If the contract or statement names a different period, that period applies (§ 429 ods. 2).

Commercial Code § 563 ods. 2 applies § 429 to 431 to the quality guarantee of a work. Civil Code § 654 ods. 3 lets a contractor who repairs or alters a thing give a guarantee that goes beyond the statutory one in a záručný list. Both can apply to the same building. Ask for any guarantee in writing.

Which code governs my contract for work?

The Commercial Code governs obligations between entrepreneurs when it is clear from the circumstances that they concern their business (§ 261 ods. 1). Parties outside that rule can agree in writing that the Commercial Code governs (§ 262 ods. 1 and 2). A consumer keeps the Civil Code rules whenever they help the consumer (Civil Code § 52 ods. 2). The page contract for work explains the choice in more detail.

How does a client report a defect?

The client reports the defect to the contractor without delay. The steps below follow the Commercial Code.

  1. Inspect the work as soon as possible after handover, or arrange an inspection (§ 562 ods. 1).
  2. Record visible defects in the handover protocol. Either party can ask for a protocol (§ 554 ods. 6). If the client appointed a construction supervisor, the supervisor can join the inspection.
  3. Notify each defect without delay after finding it, or after the inspection should have found it (§ 562 ods. 2 písm. a and b).
  4. Notify a defect found later without delay, within the limits of § 562 ods. 2 písm. c.

Neither code sets a number of days for the repair or for the acknowledgement of a complaint. Send the notice in writing so the date can be proved. For a repair or alteration under the Civil Code, the client must claim the right in the záručná doba, or it lapses (§ 655 ods. 2). If the contractor refuses liability, the contractor gives the reasons in writing (Civil Code § 646 ods. 5).

What can the client demand for a defect?

Commercial Code § 564 applies §§ 436 to 441 to a work. The client keeps the claim for damages and for a contractual penalty if the contract sets one (§ 436 ods. 4).

BreachClient may demandSource
SubstantialRepair if the defect is repairable, a reasonable discount, or withdrawal from the contract§ 436 ods. 1
Not substantialRemoval of the defects or a discount§ 437 ods. 1

Until the contractor removes the defects, the client need not pay the part of the price that matches the discount claim (§ 439 ods. 4). The client cannot withdraw if the client did not notify the defects in time (§ 565). For a repair or alteration under the Civil Code, the client has the right to free removal of the defect (§ 655 ods. 1).

When is the contractor not liable?

The contractor is not liable if the client's material or instructions caused the defect and the contractor warned the client (Civil Code § 646 ods. 4). Commercial Code § 561 adds that the contractor is also not liable if the contractor could not have found the problem with professional care. A contractor who uses a subcontractor is liable as if the contractor did the work (§ 538).

How long can a client enforce a claim in court?

A general limitation period also applies. Civil Code § 101 sets three years from the day the right could first be exercised, and § 100 ods. 1 says a court considers limitation only if the debtor objects. Commercial Code § 397 sets four years unless the law says otherwise. A lawyer decides how these periods apply to a given defect claim. For insurance questions see construction insurance.

Frequently asked questions

How long is the statutory warranty period for a building in Slovakia?
For a Civil Code contract it is three years from the day the client should have taken the building over (Civil Code § 646 ods. 3). A regulation may set a shorter period for some parts, but not below eighteen months.
Is the warranty on a building five years under the Commercial Code?
No. Five years in Commercial Code § 562 ods. 2 písm. c is the latest time to notify a defect found later. The Commercial Code sets no statutory záručná doba for a building.
Can you claim defects after the warranty period ends?
Not in the same way. Under the Civil Code the rights for a repair or alteration lapse if not claimed in the záručná doba (§ 655 ods. 2). Under the Commercial Code a court does not grant a right from a defect not notified in time (§ 562 ods. 2).
What is the difference between statutory liability and a guarantee?
Statutory liability comes from the law. A guarantee is a written promise from the contractor for a set time (Commercial Code § 429 ods. 1). A different period in the contract or statement applies (§ 429 ods. 2).
How do you report a building defect to the contractor?
Notify it in writing without delay after you find it (Commercial Code § 562 ods. 2). Record visible defects in the handover protocol (§ 554 ods. 6). Neither code sets a number of days for the repair.
Does the warranty period start at handover or at kolaudácia?
It starts at takeover, not at kolaudácia. Civil Code § 646 ods. 3 uses the day the client should have taken the building over. Kolaudácia is a separate step (Building Act § 66 ods. 1).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 66 ods. 1
  2. Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 52 ods. 2, § 100, § 101, § 646, § 654, § 655
  3. Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261, § 262, § 397, § 429 to 431, § 436, § 437, § 439, § 538, § 554, § 560 to 565