The handover of the house sets the start of the warranty period. This article covers that step of the process of building a house in Slovakia. It explains the handover, the warranty period and the way to claim a defect. The legal basis is the Civil Code (40/1964), the Commercial Code (513/1991) and Building Act 25/2025.
What is the handover and how does it differ from kolaudácia?
Building handover is a step of the contract for work. The contractor performs the contract by finishing the work properly and handing it over to the client (Commercial Code § 554 ods. 1). If either side asks, the parties write a handover protocol and both sign it (§ 554 ods. 6). Building Act 25/2025 adds that the contractor hands over the finished building and its documentation to the builder (§ 32 ods. 2 písm. l).
Kolaudácia is a different step. It is a procedure before the building office. The office checks the seven points of § 66 ods. 4, and the certificate states that the building is fit for its designed purpose (§ 67 ods. 2). Kolaudácia does not settle your claims against the contractor. Those come from the contract and the codes.
The handover comes first, because the handover protocol is an attachment to the proposal for kolaudácia. The office may waive it in justified cases (§ 66 ods. 2 písm. e). From 1 January 2027 the protocol becomes a "zápis o odovzdaní a prebratí stavby". It includes the contractor's declaration that the building matches the verified project (243/2026, Art. I, bod 151). The article on kolaudácia step by step covers the rest of that procedure.
| Aspect | Handover | Kolaudácia |
|---|---|---|
| Who takes part | The client and the contractor. Both sign the protocol (Commercial Code § 554 ods. 6) | The builder and the building office, with the invited persons (§ 66 ods. 3) |
| Basis | The contract, the codes and the verified project (Building Act § 32 ods. 1) | The seven points of § 66 ods. 4 |
| Result | A handover protocol | An occupancy certificate (§ 67 ods. 1) |
| What it starts | The warranty period (Commercial Code § 563 ods. 1) | The right to use the building permanently (§ 66 ods. 1) |
What goes into the handover protocol?
The codes read do not prescribe the content of the protocol. The contract should say what it contains. A protocol that serves you well records the following:
- the date, the parties and the building or the part you take over,
- each defect and each unfinished item, with its place and a deadline for the contractor to fix it,
- the documents the contractor hands over, for example the construction diary, the as-built documentation and the test and revision records,
- your reservations in writing, if you do not accept an item.
The construction diary is kept until handover (§ 39 ods. 1). The contractor must arrange the as-built documentation for kolaudácia and record agreed changes in the diary (§ 32 ods. 3). Ask for these documents at the handover, because you need them for the proposal. Do not sign under pressure. If you cannot agree on a defect, write that you do not accept it.
Which documents should you ask for at handover?
The application for kolaudácia has these attachments, depending on the type of structure (§ 66 ods. 2):
- the construction diary and the final opinion of the site manager
- the as-built documentation
- the survey of the structure as built and the geometric plan to update the cadastre
- records of tests on product samples taken on site and the results of measurements and inspections of reserved technical equipment
- the handover protocol
- the energy certificate, if the building needs one
The list has more items, such as the receipt for the local development fee. At handover, ask the contractor for every document he issued or prepared. You will see what is still missing, and late searching will not delay kolaudácia. From 1 January 2027 the final opinion leaves the list (Act 243/2026, Art. I, bod 150).
Who attends the handover and how do you prepare?
The contractor ensures that an authorised site manager (stavbyvedúci) leads the building (§ 32 ods. 2 písm. c, § 37). On your side, the construction supervisor (stavebný dozor) is the person you authorise. The supervisor monitors the works against the verified project. The supervisor checks the installation of technical equipment and the suitability of building products. The supervisor also asks the contractor to remove deviations (§ 36 ods. 1). The designer may also supervise the works against the project (§ 35 ods. 10). Both can attend the handover.
Before the date:
- Ask for the list of documents the contractor will hand over.
- Read the entries in the construction diary and look at the places where it records problems.
- Bring the contract and the verified project. You compare the building with them, not with an impression.
- Plan several hours in daylight, and bring a straightedge, a torch, a folding rule and a phone for dated photos.
What should you check at the handover?
The contractor answers to the builder for the finished building. It must match the basic requirements for buildings, the technical rules and the verified project (§ 32 ods. 1). The Commercial Code defines a defect as a result that differs from what the contract sets (§ 560 ods. 1). The Civil Code adds that where a binding technical standard applies to the work, the work must meet it (§ 633 ods. 1). So you compare the building with the contract, the project and the diary, and you test what you can test.
| Where | What to look at | How |
|---|---|---|
| Facade and openings | Any crack, especially at the corners of windows and doors | Photograph it with a folding rule beside it and mark its ends in pencil |
| Joints | Whether the sealant at windows and sills is continuous and sticks on both sides | Look from outside and inside, ideally after rain |
| Terrace and balcony | The slope away from the wall and the drip edge on the slab edge | Look at the edge from below and pour a bucket of water on the surface |
| Floors and tiles | Flatness, hollow spots and the joints at the walls | Use the straightedge and tap the tiles |
| Windows and doors | Opening, closing and damp in the reveals | Operate each one |
| Equipment | Heating, hot water, electricity and rainwater drainage | Run each one and ask for the revision and test records |
Some defects show only later, for example damp patches or mould in the first winter. Photograph the doubtful places now. The photographs help you show later how the place looked on the day of handover. Kolaudácia checks two of these items too. They are the connection to utility networks and the drainage of rainwater, so that it does not burden the surroundings (§ 66 ods. 4 písm. d and e).
What happens if kolaudácia finds defects?
The office announces the date of the inspection within seven working days of a complete application. The inspection must take place within 30 days of the announcement (§ 66 ods. 3). Suppose the structure cannot operate because it is unfinished or does not comply. The office then draws up a protocol and sets a time limit to remove the defects. It suspends the proceeding meanwhile (§ 66 ods. 5). If you do not remove them in time, it ends the proceeding (§ 66 ods. 6). It also ends it when the structure was built against the verified project (§ 66 ods. 8). If the structure can operate, the office issues the certificate within 15 days of the inspection (§ 66 ods. 7).
How long is the warranty period for a house?
The warranty period depends on the code that governs your contract. The Commercial Code governs contracts between entrepreneurs about their business (§ 261 ods. 1). Other parties may choose it in writing (§ 262 ods. 1 and 2). Otherwise the Civil Code applies. If you are a consumer, the Civil Code provisions always apply when they favour you. This holds even if you chose the Commercial Code (Civil Code § 52 ods. 2). So a contract does not take away the three years under § 646 ods. 3.
| Contract | Warranty period | Source |
|---|---|---|
| Civil Code, building | Three years from the day the client should have taken over the building. A regulation may set a shorter period for parts of a building, but not below 18 months | § 646 ods. 3 |
| Commercial Code, work | The period in the contract or in the guarantee statement. It starts with the handover | § 563 ods. 1, § 429 ods. 2 |
| Commercial Code, hidden defects outside the guarantee | Notice without undue delay, and at the latest five years from the handover for a building | § 562 ods. 2 písm. c |
Under the Civil Code, a defect that shows within 24 months is presumed to have existed at the takeover (§ 646 ods. 2). The 24 months run from the day you should have taken over the building. The presumption does not apply if the opposite is shown, or if it does not fit the nature of the item or the defect. A contractor who refuses liability gives the reasons in writing (§ 646 ods. 5). Read your contract and any guarantee letter, because the period written there applies under the Commercial Code. As a consumer you also keep the three years under the Civil Code. Separate limitation periods exist too (Civil Code § 101, Commercial Code § 397). The texts read do not settle how they interact with the warranty period for a building, so ask a lawyer about a late claim. The page on the defects liability period explains the terms.
How do you document and claim a defect?
You must inspect the work, or arrange its inspection, as soon as possible after handover. The court does not grant rights from a defect that you did not notify without undue delay (Commercial Code § 562 ods. 1 and 2). Follow these steps:
- Document the defect. Take dated photographs, a wide shot and a close-up, and write down the day you found it.
- Describe what you see, not the cause. "A damp patch the size of a palm in the corner below the balcony" is a better claim than your own diagnosis.
- Notify the defect in writing without undue delay. Send a registered letter or an email with delivery confirmation and refer to the contract.
- Say which right you choose. Under the Commercial Code the remedies are removal of the defect, a price discount and, in the cases the code names, withdrawal. Which ones you have depends on how serious the breach is (§ 436, 437 and 564). For a serious breach, state your choice in the notice or without delay after it. You cannot change it without the contractor's consent (§ 436 ods. 2).
- Keep all correspondence and propose a date for an inspection of the defect.
The Civil Code provisions on the contract for work (§ 631 to 648) name the warranty period. They do not list the client's remedies for a finished building. Put the remedies into the contract.
Can you hold back part of the price until the defects are fixed?
Under the Civil Code the price is due after the work is finished, unless the parties agree otherwise (§ 634 ods. 2). Under the Commercial Code you need not pay the part of the price that matches your discount claim. This holds until the defects are removed (§ 439 ods. 4, applied by § 564). Neither code uses the term retention money (zádržné). If you want to hold back a part, agree it in the contract. Set the amount and the conditions for release. State what happens if the contractor misses the deadline, for example the right to have another firm fix the defect at the contractor's cost. Negotiate this before you sign the contract, not at the handover.