Building Handover

Building handover is the transfer of a finished building from the contractor to the client under their contract, recorded in a handover protocol.

What is building handover?

Building handover (odovzdanie stavby) is the step in which the contractor hands the finished building to the client and the client takes it over. It belongs to contract law, not to the building procedure. The Commercial Code says how the contractor fulfils the duty. The contractor finishes the work properly and hands over the subject of the work (§ 554 ods. 1 of Act 513/1991 Zb.).

Handover is not occupancy approval (kolaudácia), which the page on occupancy fitness review also covers. Occupancy approval is a decision of the building authority. Handover is an act between two parties to a contract.

Which law governs handover between contractor and client?

The contract for work (zmluva o dielo) governs it. The Civil Code regulates this contract in § 631 and the following paragraphs. The Commercial Code regulates it in § 536 and the following paragraphs. Building, changing or repairing a structure is always a work under that code (§ 536 ods. 2).

A private person who hires a firm usually contracts under the Civil Code. Two businesses contract under the Commercial Code. Check which code the contract names. The page on contract for work explains the contract. The construction supervision, practical completion and final site inspection pages describe related steps.

Is a handover protocol mandatory?

The Commercial Code requires a protocol only on request. If either party asks, the parties write a protocol of the handover, and both sign it (§ 554 ods. 6). The Civil Code provisions on contract for work do not mention a protocol.

The Building Act makes the protocol relevant for the occupancy approval. The builder attaches the handover protocol (protokol o odovzdaní a prevzatí stavby) to the proposal for occupancy approval. The building authority may waive it in justified cases (§ 66 ods. 2 písm. e of Act 25/2025 Z. z., valid until 31 December 2026).

From 1 January 2027, Act 243/2026 Z. z. renames this attachment to zápis o odovzdaní a prebratí stavby. The record must then include a declaration of the contractor that the building conforms to the verified project.

What should a handover protocol contain?

The acts do not prescribe the content of the protocol. It is a document of practice. These items make the record useful if there is a later dispute:

  • the names of the client and the contractor, the contract and the building,
  • the date and place of handover and the persons present,
  • a list of defects and unfinished work, with a deadline to remove each,
  • the documents handed over, for example the as-built documentation and the construction diary,
  • a statement of whether the client accepts the building, with or without reservations,
  • the signatures of both parties.

What does the builder have to do at handover under the Building Act?

The Building Act gives the builder a duty. When the contractor calls, the builder must inspect the finished building and take it over (§ 30 ods. 4 písm. b). The builder must also attend the inspections of the building during construction (§ 30 ods. 4 písm. a).

The site manager keeps the construction diary until the day the building is handed over (§ 39 ods. 1). The site manager and the construction diary pages explain these roles.

Which documents does the client receive?

The act lists the documents that the builder attaches to the proposal for occupancy approval. The list depends on the type of building. Until 31 December 2026, it includes these items (§ 66 ods. 2):

  • the construction diary,
  • the final opinion of the site manager,
  • the as-built documentation (dokumentácia skutočného zhotovenia stavby),
  • the survey documents on the position of the building and a geometric plan,
  • the handover protocol,
  • the protocol on a trial operation, if it was permitted,
  • test results for building products taken from the site,
  • results of measurements and revisions of reserved technical equipment,
  • the survey of the as-built building,
  • the energy certificate of the building, if the building needs energy certification.

The client should ask the contractor for these documents at handover, because the client files them with the proposal. The occupancy approval certificate has the as-built documentation as an attachment (§ 67 ods. 2).

When do the risk of damage and the ownership pass to the client?

Suppose the contractor builds on the client's land. Then the client carries the risk of damage and owns the building during construction, unless the contract says otherwise (§ 542 ods. 1 of the Commercial Code). In other cases the contractor carries the risk and owns the building until handover. Handover then moves both to the client (§ 554 ods. 5).

The Civil Code states a related rule. The contractor answers for damage to a building made to order until the client takes it over. This does not apply if the damage would have happened anyway (§ 647). The contract can change the Commercial Code rule, so read the contract.

What happens if the client does not take over the building?

Under the Civil Code, the client takes over the thing within one month. The month starts on the date the thing should have been made, or on the date it was made if that was later. If the client does not take it over, the client pays an agreed storage fee (§ 645 ods. 1). If the client does not take over within six months, the contractor may deal with the thing freely (§ 645 ods. 2). For a building, the contractor always keeps the right to the price of the finished building (§ 645 ods. 2).

Which defects can the client claim after handover?

The contractor answers for defects that the work has at handover (Commercial Code § 560 ods. 2, Civil Code § 646 ods. 1). The client should inspect the work as soon as possible after handover, and should report defects without undue delay after finding them. A court does not grant rights for defects that the client did not report in time (Commercial Code § 562 ods. 1 and 2).

For hidden defects the Commercial Code sets an outer limit. The client must report them at the latest within two years of handover, and for buildings within five years (§ 562 ods. 2 písm. c). A warranty period replaces this limit for defects covered by a warranty.

Under the Civil Code, a defect that shows within 24 months probably existed at takeover, unless the contractor proves otherwise (§ 646 ods. 2). For a building, the warranty period is three years from the day the client should have taken it over. A regulation may set a shorter period, not less than 18 months, for some parts of buildings (§ 646 ods. 3). The warranty period under the Commercial Code starts at handover (§ 563 ods. 1). The pages on the defects liability period and the construction warranty period give more detail.

When does the client pay the final price?

Under the Civil Code, the client pays the price after the work is finished, unless the parties agree otherwise. If the work is done in parts, or needs high costs, the contractor may ask for reasonable advances during the work (§ 634 ods. 2). The acts do not set a retention amount. A holdback of part of the price after handover is a term of the contract, and its size is a matter of agreement.

What should the client check at handover?

The Building Act lists what the building authority checks at the occupancy inspection. It is a sound basis for the client's own check before signing the protocol (§ 66 ods. 4):

  • the building is finished and fit for safe use in line with the verified project,
  • the defects found at the construction inspections are removed,
  • the technical systems of the building and other equipment work,
  • the building is connected to the utility networks, if they exist in the municipality,
  • rainwater is collected or drained so that it does not burden the surroundings,
  • reserved technical equipment runs smoothly and safely,
  • the building meets the required energy performance.

Write every defect into the protocol before you sign it. A client who signs without reservation can find it harder to prove later that a defect existed at handover.

Frequently asked questions

What is building handover?
Building handover is the step in which the contractor hands over the finished building and the client takes it over. It is a matter of the contract for work, not of the building procedure (Commercial Code § 554 ods. 1). It differs from occupancy approval, which is a decision of the building authority.
Is a handover protocol (zápisnica) mandatory?
Under the Commercial Code, the parties write a protocol if either party asks, and both sign it (§ 554 ods. 6). The Building Act lists the protocol among the attachments to the proposal for occupancy approval, and the authority may waive it (§ 66 ods. 2 písm. e).
What is the difference between handover and kolaudácia?
Handover is between the contractor and the client under their contract. Kolaudácia is a procedure of the building authority. The authority decides if the building is fit for use (Building Act § 66, § 67). The handover protocol is one attachment to the proposal for kolaudácia.
When does the warranty period start?
Under the Commercial Code, the warranty period starts at handover (§ 563 ods. 1). Under the Civil Code, a building has a warranty period of three years. It starts on the day the client should have taken over the building (§ 646 ods. 3).
What should I do if I find a defect at handover?
Write it into the handover protocol with a deadline for removal. The contractor answers for defects the work has at handover (Commercial Code § 560 ods. 2, Civil Code § 646 ods. 1). Report any later defect to the contractor without undue delay (Commercial Code § 562 ods. 2).
Who carries the risk of damage before handover?
It depends on the contract. If the contractor builds on the client's land, the client carries the risk unless the contract says otherwise (Commercial Code § 542 ods. 1). Under the Civil Code, the contractor answers for damage to the building until the client takes it over (§ 647).

Sources

  1. Zákon č. 513/1991 Zb. Obchodný zákonník · Slov-Lex · § 536 ods. 2, § 542, § 554, § 560, § 562, § 563
  2. Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 634 ods. 2, § 645, § 646, § 647
  3. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 30 ods. 4, § 39 ods. 1, § 66, § 67 ods. 2
  4. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon · Slov-Lex · čl. I, body 150 a 151