Site Manager
A site manager is the person who organizes, leads and checks the building work on site and keeps the construction diary.
What is a site manager?
A site manager (Slovak: stavbyvedúci) is the person who organizes, leads, coordinates and checks the building work on site. The site manager also runs the site and keeps the construction diary (§ 37 ods. 1 of act 25/2025 Z. z., the Stavebný zákon).
The contractor must ensure that a qualified site manager leads the building (§ 32 ods. 2 písm. c). The site manager answers for the professional leadership of the building (§ 37 ods. 2). The work follows the verified project and the decision on the building intent (see building permit for the older permit terms). The act uses the word stavbyvedúci, not stavbyvedenie.
What does a site manager do?
The site manager decides the order and timing of the work, checks safety and quality, and manages deliveries and the site. The act lists these duties for the organization of work (§ 37 ods. 3).
- Set the order of the building work and the start and end of each stage.
- Stop the work when an unforeseen fact prevents work according to the verified project.
- Give instructions on timing and method, depending on weather, supply of products and the work plan of the contractor's staff.
- Check that the work follows safety, hygiene and technical rules and the instructions of the product makers.
- Coordinate, receive, check and record deliveries of building products and the removal of waste.
- Keep the certificates that show products suit their use.
- Protect trees, works of art and other protected items, and order a stop of work if ammunition or human remains are found.
- Keep out people with no right to enter the site, and send away anyone under the influence of alcohol or drugs.
The site manager also keeps the site fenced, signed and equipped to meet minimum safety and health rules (§ 38 ods. 1).
Who appoints the site manager?
The contractor ensures that a qualified site manager leads the building (§ 32 ods. 2 písm. c). The contractor must also follow the site manager's instructions on organization, coordination and timing of the work (same paragraph).
On a self-build, the builder does the coordination and answers for all duties of the act (§ 26 ods. 4). Such a builder must have the work guided by a qualified person (§ 26 ods. 3).
Who can be a site manager?
Leading the building work is a reserved activity (vyhradená činnosť). Only a person with the legal qualification, authorization or other entitlement may do it (§ 34 ods. 1 and 2 písm. c).
The rule depends on the structure.
| Structure | Who may lead the work | Source |
|---|---|---|
| Reserved structure (vyhradená stavba) | An authorized chief site manager (autorizovaný stavbyvedúci), an engineer or technician on the list kept by the chamber | § 37 ods. 5, act 138/1992 Zb. § 3 ods. 7 and § 5b |
| Other structure | Also a person with a trade licence for this activity who is qualified under the rules on regulated professions | § 34 ods. 3 |
| Building alteration, minor structure or structure under a notification, built by the builder personally | A person with a university degree in a building field, or secondary vocational education in one and three years of practice | § 26 ods. 3 |
A reserved structure is a building or civil structure that is technically demanding or structurally unusual (§ 2 ods. 8). See reserved structure.
What is the chief site manager?
A chief site manager (hlavný stavbyvedúci) is the site manager who answers for a large structure as a whole. The chief site manager appoints deputy site managers for sections or parts of the structure when one person cannot lead it (§ 37 ods. 4).
The deputies answer for the section given to them. On a reserved structure, the person acting as chief site manager must hold the authorization (§ 37 ods. 5).
What is the final statement of the site manager?
The final statement (záverečné stanovisko stavbyvedúceho) certifies that the finished structure matches the verified project, including approved changes (§ 37 ods. 2 and § 10 ods. 3). It is a document for the final inspection (kolaudácia). The builder attaches it to the application "according to the type of structure" (§ 66 ods. 2 písm. b).
The statement is not needed for building alterations and structures under a notification (§ 10 ods. 3). Read more about the procedure in occupancy approval.
What does the site manager write in the construction diary?
The site manager keeps the diary from the first day of the site until the handover of the structure (§ 39 ods. 1). The diary records the progress of the work from the takeover of the site until handover (§ 10 ods. 2).
The site manager must allow entries from other parties. These include the designer, the builder, the surveyor, the construction supervisor and the person who carries out state building supervision (§ 39 ods. 2). The act expects an electronic diary in most cases (§ 10 ods. 2).
How does a site manager differ from a construction supervisor?
The site manager leads the building work for the contractor. The construction supervisor (stavebný dozor) checks it for the builder (§ 36 ods. 1).
| Question | Site manager | Construction supervisor |
|---|---|---|
| Works for | The contractor ensures the site manager leads the building (§ 32 ods. 2 písm. c) | The builder appoints the supervisor (§ 36 ods. 1) |
| Main task | Organize, lead and coordinate the work (§ 37 ods. 1) | Check the work against the verified project (§ 36 ods. 1 písm. a) |
| Construction diary | Keeps it (§ 39 ods. 1) | Checks it and may write in it |
| Required | On every structure the contractor builds, a qualified site manager | On a reserved structure and on a self-build (§ 30 ods. 5 and 6) |
What changes from 1 January 2027?
Act 243/2026 Z. z. amends the Stavebný zákon from 1 January 2027. It removes the final statement of the site manager from the documents of the building (§ 10 ods. 3 is deleted). It also removes the last sentence of § 37 ods. 2 and deletes the final statement from the list of annexes to the application for kolaudácia (§ 66 ods. 2 písm. b).
The annex list then includes a record of handover with a declaration of the contractor that the structure matches the verified project. Until 31 December 2026 the text of 1 November 2025 applies.
Frequently asked questions
- What does stavbyvedúci mean in English?
- Stavbyvedúci means site manager. The act defines the role as the person who organizes, leads, coordinates and checks building work and keeps the construction diary (§ 37 ods. 1 of act 25/2025 Z. z.).
- Who appoints the site manager?
- The contractor ensures that a qualified site manager leads the building (§ 32 ods. 2 písm. c of act 25/2025 Z. z.). The builder appoints the construction supervisor, which is a different role.
- Is an authorized site manager required?
- On a reserved structure, yes. The chief site manager must hold the authorization (§ 37 ods. 5 of act 25/2025 Z. z.). On other structures, a qualified person with a trade licence may lead the work (§ 34 ods. 3).
- Who can lead the work on a minor structure that I build myself?
- A person with a university degree in architecture and urbanism, civil, mechanical or electrical engineering may lead it. So may a person with secondary vocational education in these fields and three years of practice (§ 26 ods. 3). The builder may do it if the builder meets the same conditions.
- What is the construction diary and who keeps it?
- The construction diary (stavebný denník) records the progress of the building work from the takeover of the site until handover. The site manager keeps it (§ 39 ods. 1 and § 10 ods. 2 of act 25/2025 Z. z.).
- Does the site manager write a final statement for the final inspection?
- Yes, until 31 December 2026, except for building alterations and structures under a notification (§ 37 ods. 2 and § 10 ods. 3 of act 25/2025 Z. z.). Act 243/2026 Z. z. removes the statement from 1 January 2027.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 8, § 10, § 26, § 30, § 32, § 34, § 36 to 39, § 66
- Zákon č. 138/1992 Zb. o autorizovaných architektoch a autorizovaných stavebných inžinieroch · Slovenská národná rada, via Slov-Lex · § 3 ods. 7, § 5b
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I body 41, 42, 100, 150, 151