General contractor
A general contractor is a builder who signs one contract with the client to build the whole structure and answers for the work.
What is a general contractor?
A general contractor is a zhotoviteľ stavby who signs a contract with the builder to build the whole structure.
The act uses the term generálny zhotoviteľ stavby. Section 31 ods. 3 of Act 25/2025 Z. z. gives it this meaning for the purposes of the act. The market name generálny dodávateľ stavby means the same in practice.
| Market term | Term in Act 25/2025 Z. z. | Source |
|---|---|---|
| generálny dodávateľ stavby | generálny zhotoviteľ stavby | § 31 ods. 3 |
| subdodávateľ | zmluvný dodávateľ | § 31 ods. 3 |
| stavebný dozor, supervisor | osoba poverená stavebníkom vykonávať stavebný dozor | § 36 ods. 1 |
| na kľúč | no term in the act | not found in § 26 to § 39 |
If the whole structure needs work types the general contractor does not do, the general contractor arranges them with subcontractors. The act calls them zmluvní dodávatelia. Each one answers to the general contractor for the results of its work.
Who may act as a general contractor in Slovakia?
A zhotoviteľ is a person who has the authorisation to build or demolish structures under a contract (§ 31 ods. 1). The person arranges the needed work with people who hold the authorisation for each type of work.
Under § 31 ods. 2, the zhotoviteľ needs the authorisation for the reserved activities of stavebný dozor and of managing the building work. The person also needs education and practice in one of these combinations:
- a master's degree in architecture and urbanism or in building engineering
- a bachelor's degree in one of those fields and at least three years of practice in construction
- full secondary vocational education in building and at least five years of practice in construction
Subcontractors of a general contractor must also meet § 31 ods. 1. For a reserved building (vyhradená stavba), the zhotoviteľ must also meet the conditions of a national certification scheme (§ 31 ods. 5).
The act does not use the phrase "bound-trade licence" in § 31 and does not require professional liability insurance. Insurance can be a term of the contract.
What does a general contractor have to do?
The zhotoviteľ answers to the builder that the finished structure follows the verified project and the legal requirements for buildings. This is § 32 ods. 1.
Section 32 ods. 2 lists the duties. The main ones are:
- build in line with the verified project
- arrange that an authorised stavbyvedúci leads the site, and follow the stavbyvedúci's instructions on schedule and order on site
- arrange a surveyor and name a chief surveyor
- use building products that suit their purpose and install them as the maker states
- use only workers with the needed skills, health fitness and authorisation
- follow the safety plan and the instructions of the safety coordinator
- clear the site after the work ends
Section 32 ods. 3 adds two duties. The zhotoviteľ records agreed changes to the project in the construction diary. The zhotoviteľ also arranges the as-built documentation (dokumentácia skutočného zhotovenia) for the final inspection of the building.
The zhotoviteľ hands the building and its documentation to the builder and records the handover in the information system (§ 32 ods. 2 písm. l)).
How does the general contractor differ from the site manager and the supervisor?
The general contractor builds. The stavbyvedúci leads the building work on site, and a person for stavebný dozor watches the work for the builder.
| Role | Task in the act | Source |
|---|---|---|
| Builder (stavebník) | Orders the building, hands over the verified project and the plots, and tells the building office who the zhotoviteľ is | § 30 ods. 3 |
| General contractor | Builds the whole structure and answers to the builder for it | § 31 ods. 3, § 32 ods. 1 |
| Stavbyvedúci | Organises, directs, coordinates and checks the building work, manages the site and keeps the construction diary | § 37 ods. 1, § 39 ods. 1 |
| Person for stavebný dozor | Authorised by the builder to watch the work against the verified project | § 36 ods. 1 |
| Subcontractor (zmluvný dodávateľ) | Answers for its work to the general contractor | § 31 ods. 3 |
The stavbyvedúci answers for the professional management of the building work and for the position of the building on the plot (§ 37 ods. 2).
A stavebný dozor is compulsory for the whole building time on a reserved building (§ 30 ods. 5 písm. a)). Section 2 ods. 8 lists such buildings by size, for example a single-storey building with a roof span over 30 m.
What is the difference between a general contractor and building by own effort?
If the builder builds by own effort (svojpomocou), the builder takes the general contractor's place. The builder coordinates the work, signs separate contracts with each supplier and answers for all duties under the act (§ 26 ods. 4).
A builder without the authorisation may build a simple building by own effort. An authorised person must lead the work (§ 26 ods. 3). See owner-executed construction.
The phrase "na kľúč" (turnkey) is a market term. The contract states what the contractor delivers.
How do you hire a general contractor and what does the contract say?
The builder usually asks several firms for priced offers and then signs a contract for work. See contractor tender for the steps.
The Civil Code describes the contract for work in § 631. The contractor builds the work for the agreed price at its own risk. The Commercial Code does the same in § 536 and § 537 ods. 1 for contracts between businesses (§ 261 ods. 1). See contract for work.
If the price is not agreed, the client owes a fair price (Civil Code § 634 ods. 1). No Slovak act sets a margin or fee for a general contractor. A percentage quoted on the market is a price agreement and not a legal rate.
How long does the general contractor answer for defects?
Under § 646 ods. 3 of the Civil Code, a building made to order has a warranty period of three years. It runs from the day the client should have taken the building over.
A regulation may set a shorter period for parts of a building, but not below 18 months. The contractor also answers for damage to the building until the client takes it over (§ 647).
In a contract between businesses, a court does not grant a right from a defect if the client does not report it in time. The latest time is five years after handover for buildings (Commercial Code § 562 ods. 2 písm. c)). For defects covered by a guarantee, a different period applies.
Frequently asked questions
- What is a general contractor?
- A general contractor is a zhotoviteľ stavby who signs a contract with the builder to build the whole structure. Act 25/2025 Z. z. calls this person generálny zhotoviteľ stavby (§ 31 ods. 3).
- What qualifications must a general contractor have in Slovakia?
- Under § 31 ods. 2 of Act 25/2025 Z. z., the zhotoviteľ needs the authorisation for stavebný dozor and for managing building work. The person also needs a degree, or secondary vocational education, and set years of practice in construction.
- What is the difference between a general contractor and a stavbyvedúci?
- The general contractor is the firm that builds under the contract. The stavbyvedúci is the authorised person who leads the work on site and keeps the construction diary (§ 37, § 39). The general contractor must arrange that such a person leads the site (§ 32 ods. 2 písm. c)).
- Can a homeowner act as their own general contractor?
- Yes, if the homeowner builds by own effort. A builder with the authorisation may build for themselves (§ 31 ods. 4). A builder without it may build a simple building only if an authorised person leads the work (§ 26 ods. 3).
- How much does a general contractor charge?
- The price is whatever the contract states. No Slovak act sets a general contractor's fee or margin. Compare offers on the same scope before you sign.
- How long is the warranty on a house built by a contractor?
- Under Civil Code § 646 ods. 3, a building made to order has a three-year warranty period. It starts on the day the client should have taken the building over. A regulation may set a shorter period for some parts, not below 18 months.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 2 ods. 8, § 26, § 30, § 31, § 32, § 36, § 37, § 39
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon · Slov-Lex · Čl. I
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 634 ods. 1, § 646 ods. 3, § 647
- Zákon č. 513/1991 Zb. Obchodný zákonník · Slov-Lex · § 261 ods. 1, § 536, § 537 ods. 1, § 562 ods. 2