Choosing a Builder and Comparing Quotes

8 min read
A site-office table with two thick stacks of paper, a pencil and a ruler, next to a calculator, a tape measure and a hard hat, scaffolding out of focus behind the window

Why are two lump-sum prices not two quotes for the same house?

The price depends on what the firm prices. If each firm reads the drawings its own way, you get sums for different scopes. A shared bill of quantities sets the quantities, and the firms add unit prices. The difference then shows on a specific line.

The base document must be detailed enough. The verified project of the building is the basis for building the structure (§ 9 ods. 3 of the Building Act). The act requires the execution project, which develops it in detail, only for a reserved structure (§ 9 ods. 5). For a family house, therefore, ask the architect whether the project is detailed enough for pricing or whether an execution project is needed.

How do you run a tender for a house builder?

A private client does not have to follow the public procurement act. It binds contracting authorities, which include the state and municipalities (§ 7 ods. 1 of Act 343/2015 Z. z.). A private contractor tender is therefore a matter of agreement. To work, every bidder needs the same documents and the same question.

  1. The same document package. The project of the building or the execution project and the bill of quantities in an editable format. Add a draft contract, the required dates and a list of what you will arrange yourself.
  2. A considered list of firms. Invite only firms you would trust with the build. Decide whether you want a general contractor for the whole house (§ 31 ods. 3) or separate firms by stage.
  3. One deadline for all. The law sets no period for a private client. Set one long enough for the firm to collect prices from its subcontractors.
  4. Questions in writing, answers to everyone. When one firm finds an error in the bill of quantities, send the question and the answer to all firms without the firm's name. Otherwise each firm prices a slightly different project.
  5. A site visit. A firm that has not seen the plot guesses its conditions. The client then hands the contractor the land for the site (§ 30 ods. 3 písm. b).
  6. Variants only alongside the base offer. If a firm proposes a cheaper solution, it should price it separately. The base offer must follow the project, or you lose comparability.

When you evaluate, first check whether a firm changed the quantities or descriptions in the bill of quantities. If it corrected an error in the documents, apply the correction to all offers.

How do you read a quote line by line?

The total is the last thing to look at. First find out which type of price the quote uses. The Commercial Code distinguishes a budget whose completeness the contract does not guarantee from a non-binding budget. With the first, the contractor may claim a reasonable price increase for activities that were not foreseeable (§ 547 ods. 2). With the second, the contractor may claim an increase by the amount by which expedient costs necessarily exceed the budgeted ones (§ 547 ods. 3). The contractor must report the need to exceed the budget without undue delay, or the claim lapses (§ 547 ods. 6).

The Civil Code is stricter. A price agreed by budget may not rise without the client's consent (§ 635 ods. 1). Take a price set by estimate. If it must rise substantially, the contractor must warn in writing without delay. Otherwise the contractor loses the right to the difference (§ 636 ods. 1). Which code applies depends on the parties. The Commercial Code governs relations between entrepreneurs when they concern their business activity (§ 261 ods. 1).

The Building Act assigns the contractor several items. The table shows what the act sets.

ItemWhat the Building Act saysReference
Fencing, marking and safety of the siteThe site manager ensures the site is fenced, marked and meets safety and health requirements§ 38 ods. 1 písm. a) to c)
Water and electricityThe site manager ensures a supply of water and electricity, except for a linear structure§ 38 ods. 1 písm. f)
Waste removalThe site manager ensures disposal or removal of waste from the site and from the structure§ 38 ods. 1 písm. g)
Site equipmentThe contractor provides equipment for the works, for running machines and for people on site§ 32 ods. 2 písm. d)
Surveyor on siteBoth the client and the contractor must arrange a surveyor. The contract should say who pays§ 30 ods. 4 písm. e), § 32 ods. 2 písm. a)
Site diary and as-built documentationThe contractor records agreed changes in the diary and arranges the as-built documentation for the kolaudácia§ 32 ods. 3

The law does not say who pays for what, so check for each item whether it is in the price. The Building Act does not mention scaffolding, so its price and rental period should appear as a separate line. If a quote shows any of the following, ask:

  • A lump item without quantities: which quantities and unit prices make up the sum.
  • One item far below the others: what exactly it contains and whether the firm reads the specification the same way.
  • Changed quantities or descriptions in the bill of quantities: why they changed and whether it is an error in the documents.
  • "To be specified" on a major item: when, and with what price ceiling.

How do you check a firm before signing?

The law says who may build. The contractor is a person entitled to build structures as a supplier (§ 31 ods. 1). The contractor must ensure that an authorised site manager leads the construction (§ 32 ods. 2 písm. c). The site manager organises and checks the works, manages the site and keeps the site diary (§ 37 ods. 1). Ask who the site manager will be and what authorisation the person holds. For a reserved structure, the contractor must meet the conditions of the certification scheme and hold a certificate (§ 31 ods. 5 and 7).

References only help when they are verifiable. Ask for contacts of owners of houses finished some years ago. Ask about the deadline, extra work and complaints. You can check the firm's data in public registers:

  • The Commercial Register (orsr.sk) and the Trade Register (zrsr.sk): search for the firm by name or company ID.
  • The register of pre-insolvency, liquidation and insolvency proceedings (ru.justice.sk): it shows bankruptcy, restructuring and other insolvency proceedings against a party.
  • The list of tax debtors, which the Financial Directorate publishes under § 52 ods. 1 písm. a) of Act 563/2009 Z. z.
  • The register of financial statements (registeruz.sk): the official source of information on the finances of businesses.

Neither the Building Act nor the Commercial Code in § 536 to 565 requires the contractor to hold insurance. Asking for the policy and agreeing who will insure the structure is a matter for the contract. Under the Civil Code the contractor answers for damage to the structure until takeover (§ 647).

What must the contract you send with the bill of quantities contain?

The draft contract for work belongs in the tender documents. The firms then price the terms as well. The contract should set:

  • The price. The price must be agreed, or the contract must at least set a way to determine it (Commercial Code § 536 ods. 3). A lump sum, a budget and an estimate have different consequences, as § 547 above and Civil Code § 635 and 636 show.
  • Instalments. Under the Civil Code the price is paid after the work is finished unless agreed otherwise. For work in parts or with considerable costs, reasonable advances may be requested (§ 634 ods. 2). Under the Commercial Code the claim to the price arises when the work is done, unless the contract says otherwise (§ 548 ods. 1). Instalments by stage therefore need an express agreement.
  • Retention. Neither the Civil Code in § 631 to 656 nor the Commercial Code in § 536 to 565 mentions retention. It exists only if the contract agrees it, so state the amount, the purpose and the release conditions.
  • Handover. At the request of either party, a protocol of the handover is drawn up and signed by both (Commercial Code § 554 ods. 6). The handover protocol is an annex to the application for the kolaudácia (Building Act § 66 ods. 2 písm. e).
  • Extra work. Work outside the budget may be charged only after the client's written approval or a later written order (Civil Code § 635 ods. 1). For an agreed change of scope the Commercial Code sets the price by the difference in work and expedient costs (§ 549).

What is the warranty period for a building?

Under the Civil Code it is three years from the day the client should have taken over the building. An implementing regulation may set a shorter period for some parts of buildings, but not below 18 months (§ 646 ods. 3). A defect may appear within 24 months of the day the client should have taken over the building. The law then presumes it was there at takeover (§ 646 ods. 2). The Commercial Code sets no warranty period for a building. The period agreed in the contract or in a warranty statement applies (§ 429 ods. 2, § 563 ods. 2). Defects must be notified without undue delay, and for a building no later than five years after handover (§ 562 ods. 2 písm. c).

A new Civil Code, Act 260/2026 Z. z., takes effect on 1 July 2027 and repeals Act 40/1964 Zb. (§ 1919, § 1920). For building a structure it sets a warranty period of five years (§ 1256 ods. 3). Legal relations that arose before that day stay under the earlier rules unless the act says otherwise (§ 1893 ods. 3). Check the date you sign the contract. Details are in the entry on the construction warranty period.

What do you do when a defect shows up after handover?

Under a Commercial Code contract, a work has a defect if it does not match the result set in the contract (§ 560 ods. 1). Under such a contract, inspect the building, or arrange for it to be inspected, as soon as possible after handover (§ 562 ods. 1). Report a defect in writing so you can prove it. Do it without undue delay after you find it, or a court will not grant the right arising from it (§ 562 ods. 2). Under the Civil Code, a contractor who refuses liability must give its reasons in writing (§ 646 ods. 5). The contractor is not liable for defects caused by your material or unsuitable instructions if it warned you about them (§ 646 ods. 4). Under a Commercial Code contract you must also insist on using them (§ 561).

Is the cheapest quote always the cheapest?

No. The sum on the cover sheet is not yet the price you will pay. It depends on whether the budget guarantees completeness. If it does not, the contractor may claim a reasonable price increase for activities outside the budget (Commercial Code § 547 ods. 2). The client may withdraw if the claimed increase exceeds the budget price by more than 10 %. The client then pays for the work partly done (§ 547 ods. 5).

Read the cheapest quote most carefully. The reasons a build price changes are covered in the article on why a build costs more than planned.

Where does the architect help with choosing a firm?

If the architect's contract includes it, the architect can prepare the documents and answer the firms' questions. During construction the act gives the architect specific tasks. The designer attends a site inspection when invited because of a project change or a product substitution (§ 35 ods. 7 písm. a). The designer may approve a change only after the fire protection specialist agrees in advance (§ 35 ods. 11).

The author of the architectural work has the right to author's supervision (§ 35 ods. 10). How these services fit into phases and payments is covered in the article on design phases and the payment schedule.

Frequently asked questions

Can I approach a firm that an acquaintance recommended?
Yes. A recommendation is a good reason to invite a firm, not a reason to skip the comparison. Give it the same documents and the same deadline as the others. If it is good, it will stand up next to the competition.
How much time should I give firms to prepare a quote?
The law sets no period for a private client. The public procurement act binds only contracting authorities (§ 7 ods. 1). Set a period long enough for the firm to collect subcontractor prices and ask questions about the project.
Must a building firm hold insurance?
Neither the Building Act nor the Commercial Code in § 536 to 565 requires the contractor to be insured. Ask for a copy of the policy and agree in the contract for work who insures the structure and until when.
Can I withdraw from the contract if the firm raises the price?
Under the Commercial Code you may withdraw without undue delay (§ 547 ods. 5). This applies if the claimed increase exceeds the budget price by more than 10 %. For a price set by estimate, you may withdraw after the new price is announced (Civil Code § 636 ods. 2).
What is the warranty period for a new house?
Under the Civil Code it is three years from the day you should have taken over the building (§ 646 ods. 3). A new Civil Code sets five years from 1 July 2027 (§ 1256 ods. 3). Relations under earlier contracts stay under the earlier rules unless the act says otherwise.
What if all quotes exceed my budget?
It does not mean all firms are expensive. Go through the biggest items with the architect and change the scope or the standard. Then let the firms price the revised bill of quantities again.
Is the firm liable for defects caused by material I supply?
Not if it warned you about the defective material or the unsuitable instructions (Civil Code § 646 ods. 4). Under the Commercial Code the firm is not liable if it warned you and you insisted on using them. It is also not liable if it could not have found the unsuitability even with professional care (§ 561). Hand over material in writing and keep the firm's warnings in writing.
Can I withdraw from the contract if the firm is late?
Under the Civil Code you may withdraw if the work clearly will not be finished on time or done properly. The firm must also fail to correct it within a reasonable period you give it (§ 642 ods. 2). If you withdraw before the work is done, you pay for work already done that the firm cannot use otherwise. You also pay costs reasonably incurred (§ 642 ods. 1). A contract under the Commercial Code follows other rules, which this text does not cover. Set the period for correction in writing.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9 ods. 3 a 5, § 30 ods. 3 a 4, § 31 ods. 1, 3, 5 a 7, § 32 ods. 2 a 3, § 35 ods. 7, 10 a 11, § 37 ods. 1, § 38 ods. 1, § 66 ods. 2
  2. Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 634 ods. 2, § 635 ods. 1, § 636, § 642, § 646 ods. 2 až 5, § 647
  3. Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261 ods. 1, § 429 ods. 2, § 536 ods. 3, § 547, § 548 ods. 1, § 549, § 554 ods. 6, § 560 ods. 1, § 561, § 562 ods. 1 a 2, § 563 ods. 2
  4. Zákon č. 260/2026 Z. z. Občiansky zákonník · Slov-Lex · § 1256 ods. 3, § 1893 ods. 3, § 1919, § 1920
  5. Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Národná rada Slovenskej republiky, via Slov-Lex · § 7 ods. 1
  6. Obchodný register Slovenskej republiky na internete · Ministerstvo spravodlivosti Slovenskej republiky · Vyhľadávanie podľa obchodného mena a identifikačného čísla
  7. Živnostenský register Slovenskej republiky · Ministerstvo vnútra Slovenskej republiky · Vyhľadávanie v živnostenskom registri
  8. Register predinsolvenčných, likvidačných a insolvenčných konaní · Ministerstvo spravodlivosti Slovenskej republiky · Konania, verejná časť
  9. Zoznam daňových dlžníkov · Finančná správa Slovenskej republiky · Zoznam daňových dlžníkov podľa § 52 ods. 1 písm. a) zákona č. 563/2009 Z. z.
  10. Register účtovných závierok · Ministerstvo financií Slovenskej republiky · Register účtovných závierok

Topic

  • Costs and fees