Three firms receive the same design and return three different offers. The natural question is whether they all priced the same thing. Without a shared basis, that is not certain. There need not be bad intent. If a construction budget does not rest on a common document, each firm reads the scope, materials and standard in its own way.
What is the difference between a bill of quantities and a construction budget?
A bill of quantities is a list of structures and works derived from the design. Each item has a quantity in units, for example m2, m3, linear metres or pieces, and a description with the technical specification. The budget exists once unit prices are added to the items. If two firms price the same bill of quantities, their numbers can be compared. If each firm measures its own quantities, you compare different houses.
Decree 60/2025 Coll. lists a bill of quantities (code VYV) and a budget (code ROZ) as separate document types. This is in its file naming rules (annex 24).
Must a bill of quantities be part of the design?
No. The Building Act (25/2025 Coll.) does not use the term "bill of quantities". Decree 60/2025 Coll. does not require it as part of any level of documentation. It knows only the code VYV for a file name. In the summary report of the building intent and of the project of the building, it asks for the expected total cost of the building. This serves to set administrative fees and the conditions for placing a work of art (annexes 15 and 17, part B point 9). That is an estimate, not a priced list of items. The entry on the indicative cost estimate covers it. If you want a bill of quantities, agree it in the design contract.
What kind of price can a contract for work set?
The Civil Code distinguishes a fixed sum, a price set by a budget (§ 635) and a price set by an estimate (§ 636). The Commercial Code requires the contract to agree the price or at least a method to determine it (§ 536 ods. 3). The exception: the parties show they intend to conclude the contract without it. It deals with a price set by a budget in § 547. The rules differ depending on which code applies. The Commercial Code governs obligations between entrepreneurs in the course of their business (§ 261 ods. 1). A household that builds for itself usually falls under the Civil Code. That is a conclusion from § 261 ods. 1, not a direct text. In a contract for work, the word "budget" alone is therefore not enough.
What applies to a budget price under the Civil Code?
- A price agreed by a budget may not be raised without the client's consent (§ 635 ods. 1).
- Work and costs not in the budget can be billed only after written approval or a later written order (§ 635 ods. 1).
- If the price is set by an estimate, the contractor must warn you in writing without delay when it will be substantially exceeded. The contractor must also state the new price. Otherwise the contractor has no right to the difference (§ 636 ods. 1).
- After the new price is announced you may withdraw from the contract. If you do not withdraw without undue delay, you pay the new price (§ 636 ods. 2 and 3).
What applies to a budget price under the Commercial Code?
- The fact that the price rests on a budget that is part of the contract does not change the price (§ 547 ods. 1).
- The contract may state that the budget is not guaranteed to be complete. Then the contractor may ask for a reasonable increase for activities not in it. The need must appear during the work and must not have been foreseeable at signing (§ 547 ods. 2).
- If the contract treats the budget as non-binding, the contractor may ask for an increase. The increase is the amount by which the reasonably incurred costs necessarily exceed the costs in the budget. If you disagree, the court sets the amount (§ 547 ods. 3 and 4).
- If the contractor asks for more than 10 % above the budget price, you may withdraw without undue delay (§ 547 ods. 5). The contractor must announce the need to exceed the budget without undue delay, or the claim lapses (§ 547 ods. 6).
What must the written confirmation of an order contain?
If the work is not done on the spot, the Civil Code requires a written confirmation of receipt of the order. The contractor issues it to the client. It names the subject of the work, its scope, quality, price and time of completion (§ 632). A bill of quantities or a budget can make the scope and price more precise. The contract or the confirmation must refer to it expressly. That is a practical conclusion, because the act does not prescribe such an annex.
What happens when the client's basis or instruction is unsuitable?
Both codes deal with unsuitable items and instructions from the client. Under the Civil Code the contractor must warn the client without undue delay in two cases. One is supplied material with defects that prevent proper work. The other is a client request for an unsuitable method. If the client insists on the order despite the warning, the contractor may withdraw from the contract (§ 637).
Under the Commercial Code the contractor must warn of the unsuitable nature of items or instructions if professional care would have revealed it. If unsuitable items or instructions block the work, the contractor interrupts it to the extent necessary. Work resumes after the instructions change or after the client states in writing that it insists on them (§ 551 ods. 1). A contractor who warned is not liable for defects caused by what the client insisted on in writing (§ 551 ods. 2). A contractor who did not warn is liable for them (§ 551 ods. 3). Whether a bill of quantities supplied by the client counts as an instruction depends on the contract. That is an interpretation, not the text of the act.
Why do offers for the same house differ so much?
Without a shared bill of quantities, each firm decides what to include in the price and what to leave out. The differences arise mainly like this:
- Scope of delivery. One offer covers a house with floors and sanitary ware, another stops at a shell or holodom.
- Material specification. If the design does not name the window system, roof covering or insulation type, the firm prices its own standard.
- Uncertain items. A firm prices parts that are not known, for example groundworks on unknown subsoil, as a fixed sum, as an estimate, or leaves them out. The codes distinguish these ways, as shown above.
- Exclusions. Connections, paved areas, fencing or site setup can stay outside the price without being obvious at first glance.
So the lowest offer need not be the cheapest house. It may be the offer with the narrowest scope or the most optimistic assumptions.
| Budget line item | Where offers can diverge |
|---|---|
| Groundworks and foundations | Soil bearing capacity, groundwater level and excavation depth without a survey. Unless you agree otherwise with the designer, the builder arranges the geological survey for the design (§ 30 ods. 2 písm. b of the Building Act). |
| Shell (walls, floors, roof structure) | Structure build-up, insulation thickness, roof covering type. |
| Windows and doors | Standard or higher profile, glazing, hardware. |
| Building services (heating, electrics, ventilation) | Heat source type, routing of distribution, items missing from an incomplete design. |
| Finishes | Scope of delivery, level and price tier of the selected materials. |
| External works and connections | Connections, paved surfaces and fencing that may sit outside the base offer. |
| Site setup | Site facilities, transport and insurance, either in the price or billed separately. |
When is the bill of quantities prepared, and by whom?
Neither the act nor the decree says who prepares a bill of quantities or when. Agree it in the design contract. A bill of quantities needs a detailed basis. Under annex 18 of decree 60/2025 Coll. the execution project is worked out to a level of detail that defines structures, products and materials. The act requires it only for a reserved structure (§ 9 ods. 5). The verified project of the building is the basis for construction (§ 9 ods. 3). It is less detailed, so more decisions stay with the firm at pricing.

The more detailed the basis before you approach firms, the less guesswork is left on the price side. A bill of quantities alone does not guarantee the final sum, as the budget rules above show.
How do you compare offers from several firms fairly?
For a comparison to mean anything, every firm must price the same document:
- Send everyone the same basis. The same design and the same bill of quantities, not just a floor plan and an idea.
- Ask for an itemised budget, not just a bottom line. A single number at the end cannot be checked or compared. A breakdown into items shows where and why prices diverge.
- Check what is and is not in the price. Connections, paved areas, site setup, transport of materials and whether the sum includes VAT.
- Ask about the assumptions behind uncertain items. If a firm works from an estimate, ask what it rests on and how the final sum will be adjusted. For a price set by an estimate, the contractor must warn in writing about a substantial overrun (§ 636 ods. 1).
- Do not decide on price alone. References, experience with similar buildings and how clearly the offer is presented matter as much as the number at the bottom.
Choosing a firm this way is a small tender. The public procurement act governs contracting authorities (§ 7 ods. 1 of Act 343/2015 Coll.). A private person who builds with their own money is outside these rules. It can also bind other persons. An example is a person who gets over 50 % of the funds for a contract above the limit (§ 8 ods. 1).
What raises the price during construction?
Even a well-prepared budget can grow during construction. For each source there is a rule in the code or in the contract:
- An incomplete or inaccurate bill of quantities. Missing items surface once work is underway. Who pays for them depends on the contract and the code, as described above.
- Changes during construction. The client asks for different windows, tiling or a different bathroom layout. Agree the change in writing before it is carried out, with its price and effect on the deadline.
- Underpriced uncertain items. An estimate for unknown conditions, for example in the foundations, was set too low. With an estimate the contractor must announce a substantial overrun in writing without delay (§ 636 ods. 1 of the Civil Code).
- Time between the offer and the work. A budget is a price on a given day. Agree how long the offer is valid and what happens to the price afterwards if much time passes before work starts.
- Vague exclusions. Items you thought were in the price are billed separately. The contract sets the scope of the work. On the reserve in a budget, see the article on why a build costs more than planned.
Summary: the bill of quantities sets what is priced and how much, and the budget adds prices to it. The law does not require a bill of quantities, so agree it in the design contract. The two codes treat a budget price differently. The contract must say whether the price is fixed and who bears what is missing from the budget.
