Construction budget
A construction budget (rozpočet stavby) is a priced list of the work items of a building, with a quantity and unit price for each item.
What is a construction budget?
A construction budget (Slovak: rozpočet stavby) is a priced list of the work needed to build a building. Each item of the list has a quantity, a unit price and a price for the item. The items add up to a total.
The quantities come from a bill of quantities (výkaz výmer). The budget is the same list with prices. Decree 60/2025 lists the two as separate documents with the file-name codes ROZ and VYV.
How is a budget different from an indicative cost estimate?
An indicative cost estimate is made early, before the drawings are detailed. It is based on comparable buildings and has no item list measured from drawings.
A budget is made when the drawings are detailed enough to measure. Each item is measured and priced. A contractor's offer is a budget that the contractor signs as a price.
| Document | Stage | Basis |
|---|---|---|
| Indicative cost estimate (orientačný rozpočet) | Building intent (stavebný zámer) | Comparable buildings and the scope of the intent |
| Bill of quantities (výkaz výmer) | Building project and execution project | Quantities measured from drawings |
| Budget (rozpočet stavby) | Same drawings, before the tender and the contract | Quantities with unit prices |
Does Slovak law require a construction budget for a house?
No. Decree 60/2025 does not list a budget in the content of the building intent, the building project or the execution project.
The decree requires one cost figure. Annexes 15 and 17 require the estimated total cost of the building in the summary report. The stated purpose is to set the administrative fee and the conditions for placing a work of art. For a building financed from public funds, the report also states how it is financed.
That figure is an estimate. It is not a budget and does not bind a contractor.
Does public procurement require a budget?
Only for contracting authorities. Under § 6 ods. 1 of Act 343/2015, a contracting authority sets the estimated value of a contract from data on comparable contracts. If it has no such data, it uses a market survey, a preliminary market consultation, a price monitoring system or another suitable way.
The act lists the contracting authorities in § 7 ods. 1. A private person who builds a house is not one of them.
Is the contract price binding if it is based on a budget?
It depends on the contract and on the code that governs it. A household client who orders a house from a firm is usually under the Civil Code. Two businesses are under the Commercial Code if the contract relates to their business (§ 261 ods. 1).
Under the Civil Code, if the price was agreed by budget, it may not rise without the client's consent (§ 635 ods. 1). Work and costs outside the budget may be charged only if the client approved them in writing or ordered the work later in writing.
If the price cannot be fixed as one sum, it must at least be set by estimate (§ 636 ods. 1). If the contractor finds later that the estimated price will be exceeded substantially, the contractor must tell the client without delay and in writing. Otherwise the contractor has no right to the difference.
Under the Commercial Code, a budget used for the price does not by itself change the price (§ 547 ods. 1). The contractor may claim an increase for unforeseeable work if the contract says the budget is not guaranteed to be complete (§ 547 ods. 2).
Under § 547 ods. 5 the client may withdraw if the claimed increase is more than 10 % above the price set by the budget. Read your contract for work to see whether the price is fixed or only estimated.
Why does the final cost differ from the budget?
A budget prices the work that is drawn and described. Cost grows when someone adds work after the budget, when a drawn item is missing from the list, or when the client changes the scope.
The acts cited here set no contingency percentage and no accuracy band for any stage. A contingency is a choice of the client and the preparer. Any such figure comes from the practice of the person who prepares the budget, so ask for the basis.
Who prepares the budget and when?
Keep the budget, the bill of quantities and the drawings they rest on together, with the date of each.
The acts cited here do not assign it to a profession. The design contract should say who prepares it and from which level of drawings. See architect fee.
A budget is most useful before the contractor tender, when the client can still change the scope. It is also the basis for comparing the offers.
During the works, the client may use the budget to check what the contractor invoices. A construction supervisor (stavebný dozor) can check the work on site against the items.
Frequently asked questions
- What is a construction budget?
- A construction budget (rozpočet stavby) is a priced list of the work needed to build a building. Each item has a quantity, a unit price and a price, and the items add up to a total.
- What is the difference between a bill of quantities and a construction budget?
- A bill of quantities (výkaz výmer) lists items and quantities. A budget adds a unit price to each item. Decree 60/2025 lists them as separate documents with the codes VYV and ROZ.
- Do I need a budget to get a permit?
- No. Decree 60/2025 does not list a budget in the content of the building intent, the building project or the execution project. It requires only the estimated total cost of the building in the summary report.
- Can the contractor raise the price above the budget?
- Under the Civil Code a price agreed by budget may not rise without the client's consent. Extra work needs written approval or a written order (§ 635 ods. 1). The Commercial Code has other rules in § 547.
- Which code applies to my contract with a contractor?
- A household client who orders a house from a firm is usually under the Civil Code. The Commercial Code applies between businesses if the contract relates to their business (§ 261 ods. 1).
- Is a public procurement budget the same as a private client's budget?
- No. Act 343/2015 binds contracting authorities such as the state and municipalities (§ 7 ods. 1). A private person who builds a house is not bound by it.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 9 ods. 1, 3 a 5
- Vyhláška č. 60/2025 Z. z. o informačnom systéme a o obsahu dokumentácie · Slov-Lex · § 6, prílohy č. 15, 17, 18, 24
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 634 ods. 1, § 635, § 636 ods. 1
- Zákon č. 513/1991 Zb. Obchodný zákonník · Slov-Lex · § 261 ods. 1, § 536 ods. 1, § 546, § 547
- Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Slov-Lex · § 6 ods. 1, § 7 ods. 1, § 53 ods. 1