Indicative cost estimate

An indicative cost estimate (orientačný rozpočet) is an early estimate of a building's cost, made before the drawings are detailed.

What is an indicative cost estimate?

An indicative cost estimate (Slovak: orientačný rozpočet) is an early estimate of the cost of a building, made before the drawings are detailed. It has no item list measured from drawings.

Its use is to check, at an early stage, whether the scope the client wants fits the money the client has. It is not a price that a contractor must keep.

When is it prepared?

It is prepared at the start of the design, when the scope is still open. Under Act 25/2025 § 9 ods. 2, the building intent (stavebný zámer) is the first level of documentation. It states the urbanistic, architectural and basic building solution of the building.

At that level the quantities are not measured. A detailed construction budget comes later, from the building project and the execution project.

Before the building intent, the practice may prepare an architectural study. The old regime called the stages DÚR and DSP. See design phases for how they map to the current levels.

What does Slovak law require about the estimated cost?

Annexes 15 and 17 of Decree 60/2025 require the estimated total cost of the building. It goes in the summary report of the building intent and of the building project. The stated purpose is to set the administrative fee and the conditions for placing a work of art.

For a building financed fully or partly from public funds, the same item also states the way of financing.

The decree does not set a method, a rounding rule or an accuracy for this figure. It is an estimate for the office, not a price for a contractor.

Does the estimated cost set the administrative fee?

For a house, no. Under the Act on administrative fees 145/1995, item 59 písm. a) points 1 to 5, the fee for a decision on a building intent depends on the type and size of the building.

In the version from 1 November 2026, the fee for a building with one or two dwellings is 300 eur. The estimated cost enters the fee only for a civil engineering structure (item 59 písm. a) point 13).

The fee table has later versions from 1 December 2026 and 2027. Check the current table on Slov-Lex yourself before you budget a fee.

How is an indicative cost estimate made?

The method is a choice of the person who prepares it. The usual approach is to price the building from comparable buildings and adjust it for the scope of the intent.

The acts cited here do not set a method. Public procurement law gives a comparable rule for contracting authorities. Under Act 343/2015 § 6 ods. 1 the authority sets the estimated value from data on comparable contracts, a market survey, a preliminary market consultation or a price monitoring system.

A private client is not bound by that rule. It shows the same logic, which is to start from comparable data and a market check.

How accurate is it?

No act sets an accuracy band for any stage. A figure such as "±20 %" comes from the practice of the preparer, so ask for the basis and the date of the prices used.

The estimate changes when the scope, the specification or the site conditions change. Prices also change with time, so an old estimate is a reference and not a price.

How is it different from a budget, a bill of quantities and a contractor's offer?

  • Indicative cost estimate (orientačný rozpočet): A total cost from comparable buildings. Binds a contractor: no.
  • Bill of quantities (výkaz výmer): Items and quantities measured from drawings. Binds a contractor: no, it has no prices.
  • Budget (rozpočet stavby): Items, quantities and unit prices. Binds a contractor: only if the contract makes it binding.

The contract decides whether a price based on a budget can rise. Under the Civil Code a price agreed by budget may not rise without the client's consent (§ 635 ods. 1). See contract for work.

What should an indicative cost estimate state?

A useful estimate states its basis, so you can judge it. Ask the preparer to state these points:

  • which buildings and which date the prices come from.
  • which scope it covers and which parts it leaves out.
  • whether the prices include VAT.
  • which level of drawings it rests on.

The preparer may be the architect or a separate cost estimator. Agree this in the design contract. See architect fee.

Ask for a new estimate each time the scope changes, and keep the old one for comparison. The difference shows you what the change costs.

Can I use it for a bank or a subsidy?

This depends on the bank or the programme. Ask them which document they accept. The acts cited here do not set a rule for banks or subsidies.

Frequently asked questions

What is an indicative cost estimate?
An indicative cost estimate (orientačný rozpočet) is an early estimate of the cost of a building, made before the drawings are detailed. It has no item list measured from drawings.
When should an indicative cost estimate be prepared?
At the start of the design, when the scope is still open, for example with the building intent (stavebný zámer) or an architectural study. A detailed budget follows from the later drawings.
Does a permit application need a cost figure?
Yes, an estimate. Annexes 15 and 17 of Decree 60/2025 require the estimated total cost of the building in the summary report. It sets the administrative fee and the conditions for a work of art.
How accurate is an indicative cost estimate?
No act sets an accuracy band. Any percentage comes from the person who prepared the estimate, so ask for the basis and the date of the prices used.
What is the difference between an indicative estimate and a budget?
An indicative estimate prices the building from comparable buildings. A budget prices items that are measured from detailed drawings, so it is made later.
Does a contractor have to keep to an indicative estimate?
No. It is not a price offer. A price binds a contractor only through the contract. Under the Civil Code a price agreed by budget may not rise without the client's consent (§ 635 ods. 1).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 9 ods. 1, 3 a 5
  2. Vyhláška č. 60/2025 Z. z. o informačnom systéme a o obsahu dokumentácie · Slov-Lex · § 6, prílohy č. 15, 17, 18, 24
  3. Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 634 ods. 1, § 635, § 636 ods. 1
  4. Zákon č. 343/2015 Z. z. o verejnom obstarávaní a o zmene a doplnení niektorých zákonov · Slov-Lex · § 6 ods. 1, § 7 ods. 1, § 53 ods. 1
  5. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · Sadzobník, položka 59 písm. a) body 1 a 13