Feasibility study

A feasibility study is a preliminary assessment that tests whether a planned building fits a plot, its legal conditions and a budget before design starts.

What is a feasibility study?

A feasibility study (štúdia uskutočniteľnosti) is a preliminary assessment of whether a planned project can be built on a given site. It tests the legal and financial conditions that apply. For a private house, it is a service that the client agrees by contract. No Slovak act defines it for this case. The text of Act 25/2025 (version from 1 November 2025) and its Decree 60/2025 do not use the term.

The term has a legal meaning only for public investments. A Government regulation sets conditions for a feasibility study of an investment or a concession (nariadenie vlády 174/2019). Its thresholds are 40 million euro and 10 million euro. A family house is far below these thresholds.

What does a feasibility study for a house check?

A useful study tests the plot against the conditions that the building office applies later. The act does not prescribe the list. The table maps each question to the legal test that it anticipates.

QuestionLegal test laterSource
Do you hold a right to the land that allows the works?The office checks the right to the plot or buildingZákon 25/2025, § 57 ods. 2 písm. a, § 29 ods. 1
Does the plan allow the use and the placement?The office rejects an application whose placement conflicts with the binding opinion of the planning authorityZákon 25/2025, § 59 ods. 1 písm. a. Zákon 200/2022, § 24 ods. 1
Is there access from a public road?The office rejects an application without access of sufficient capacityZákon 25/2025, § 59 ods. 1 písm. e
Can the plot connect to water, sewer and electricity?The office rejects an application when an affected legal person states that the connection is not possibleZákon 25/2025, § 59 ods. 1 písm. f, § 22 ods. 3
What do the ground and the plot measurements show?The builder arranges geodetic work and engineering geological surveys unless agreed otherwiseZákon 25/2025, § 30 ods. 2 písm. a and b

For the legal checks on a plot before purchase, see site due diligence and buildability of land. The first design service after a positive study is the architectural study.

The study can add a cost estimate. Treat any figure as an assumption until a contractor prices a full construction budget.

When should you order a feasibility study?

Order it before you sign a purchase contract for a plot and before you commission the building intent. If the plot is in a protection zone or has no clear plan conditions, ask for the study first. If the plan and the utilities are already clear from the zoning information and the utility statements, the study can be short.

The study does not replace the legal documents. A zoning information is not a binding opinion (zákon 200/2022, § 40 ods. 13). The planning authority issues the binding opinion on application (§ 24 ods. 3).

Who can prepare a feasibility study?

The act reserves some activities for authorised persons (zákon 25/2025, § 34 ods. 1). Design is one of them (§ 34 ods. 2 písm. a). Selected geodetic and cartographic activities are the other (§ 34 ods. 2 písm. d). A feasibility study is not on that list. A client can order it from an architect, an engineer or another consultant.

Reserved geodetic activities need an authorised person. If the study leads to a building intent, only a designer may prepare that document (§ 35 ods. 4 and § 59 ods. 1 písm. b).

How is a feasibility study different from a building intent?

A feasibility study answers whether to proceed. The building intent (stavebný zámer) is a legal level of project documentation (zákon 25/2025, § 9 ods. 1). It is the basis for the proceedings on the building intent (§ 9 ods. 2). The table compares the two documents.

AspectFeasibility studyStavebný zámer
Legal status for a private houseNo definition in the building act. A contract service.Level of project documentation (§ 9 ods. 1 and 2)
Prepared byAny consultant the client choosesThe designer (§ 35 ods. 6 písm. a)
ResultA recommendation to proceed or notThe basis for the decision on the building intent (§ 60 ods. 1)

The old terms DÚR and DSP belong to the regime that ended on 31 March 2025. A feasibility study does not replace them or the current stavebný zámer. For the investor document that comes before it, see investment intent.

Is a feasibility study required for a public investment?

Yes, above the thresholds. The regulation applies to an investment of 40 million euro or more (nariadenie vlády 174/2019, § 1 ods. 1). For informatisation the threshold is 10 million euro (§ 1 ods. 2). For a concession it is 40 million euro (§ 1 ods. 3). The thresholds include VAT (§ 1 ods. 4).

The study must contain six parts (§ 2):

  • a description of the current situation and the goals
  • an analysis of demand and supply
  • a selection and description of alternative solutions
  • a financial and economic analysis
  • a risk assessment
  • other information needed for a proper assessment

The Ministry of Finance methodology for public investments repeats the same list. Its working version adds a step for projects above 1 million euro. The investor sends them to the ministry for an economic evaluation. This page does not cover EU fund calls.

How much does a feasibility study cost and how long does it take?

No act sets a price or a duration for a feasibility study of a private house. The scope, the price and the delivery date come from your contract. Ask for a written scope that names each check from the table, a fixed price and a delivery date.

Frequently asked questions

What is a feasibility study in architecture?
A feasibility study (štúdia uskutočniteľnosti) is a preliminary assessment of whether a planned building can be built on a site. It tests the legal and financial conditions. For a private house, no Slovak act defines it.
Is a feasibility study required to build a family house in Slovakia?
No act in the building law reviewed here requires one. Act 25/2025 does not use the term. The proceedings start with an application on the building intent (zákon 25/2025, § 50).
When is a feasibility study required by law?
The law requires one for a public investment of 40 million euro or more (nariadenie vlády 174/2019, § 1 ods. 1). The threshold is 10 million euro for informatisation and 40 million euro for a concession. A private house is far below these values.
What does a feasibility study of a plot include?
A useful study checks the right to the land, the plan conditions, access from a public road, utility connection and ground and plot measurements. These are the tests the building office applies later (zákon 25/2025, § 57 and § 59).
Who can prepare a feasibility study?
Any consultant the client chooses can prepare it, because the building act does not reserve it. The act reserves design and selected geodetic work to authorised persons (zákon 25/2025, § 34 ods. 2).
How does a feasibility study differ from a building intent?
A feasibility study is a contract service that advises whether to proceed. A building intent (stavebný zámer) is a level of project documentation (zákon 25/2025, § 9 ods. 1). It is the basis for the proceedings on the building intent.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9, 22, 29, 30, 34, 35, 50, 57, 59, 60
  2. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 24 ods. 1, 3, § 40 ods. 13
  3. Nariadenie vlády Slovenskej republiky č. 174/2019 Z. z. o podmienkach vypracovania štúdie uskutočniteľnosti investície a štúdie uskutočniteľnosti koncesie · Vláda Slovenskej republiky, via Slov-Lex · § 1 ods. 1 to 4, § 2
  4. Metodika prípravy a hodnotenia investičných projektov (pracovná verzia) · Ministerstvo financií Slovenskej republiky