Pre-design Preparation Phase

Pre-design preparation is the stage before design in which the builder collects the site, ownership, planning and utility facts the designer needs.

What is pre-design preparation?

Pre-design preparation (predprojektová príprava) is the work done before a designer starts the building intent (stavebný zámer). Act 25/2025 names it once (§ 35 ods. 3). There the general designer coordinates the usual activities in the pre-design preparation of a building. The act gives no list of steps and no procedure for this stage. The steps below follow the duties the act gives to the builder and the designer.

The act calls the whole set of project documents "projektová dokumentácia". Its first level is the building intent, which is the basis for the proceedings on the building intent (§ 9 ods. 1 and 2). Pre-design preparation comes before it.

Who does the work in pre-design preparation?

The builder (stavebník) and the designer (projektant) share the work. A builder intends to carry out building works and owns the plot or holds another right to it. The role starts on the day the builder starts to secure the documents for the proceedings (§ 29 ods. 1).

  • The builder gives the designer a technical brief (technické zadanie) that states the purpose, the operation and the scope of the building (§ 30 ods. 1). See design brief.
  • The designer decides which surveys and measurements the project needs, if the type of building requires them (§ 35 ods. 6 písm. c).
  • If several designers work on the project, the builder arranges one general designer (§ 30 ods. 2 písm. d).

Only a person with the legal authorisation may act as general designer or as designer of a part (§ 35 ods. 4). The office rejects an application when a designer did not prepare the building intent (§ 59 ods. 1 písm. b).

Which documents and surveys does the builder arrange before design?

Unless the builder and the designer agree otherwise, the builder arranges the surveys and statements below (§ 30 ods. 2). The table names each document by its legal name.

Document or surveyWho provides itWhat it tells you
Výpis z listu vlastníctva (land registry extract)The district office, or Slovenská pošta when the data are held electronically (zákon 162/1995, § 69 ods. 2 and 6)Who owns the plot and which burdens lie on it. An extract is a public document (§ 69 ods. 3).
Územnoplánovacia informácia (zoning information)The municipality, on request, for a plan approved before 1 April 2024 (zákon 200/2022, § 40 ods. 13)The conditions for use of the land and for placing a building, as set in the binding part of the plan.
Polohopis a výškopis (topographic survey)A surveyor (geodet), arranged by the builder (zákon 25/2025, § 30 ods. 2 písm. a)The measured position and height of the plot, existing buildings and visible features. See geodetic survey.
Inžinierskogeologický prieskum (geotechnical survey)A specialist firm, arranged by the builder (§ 30 ods. 2 písm. b)Ground conditions for the foundations.
Záväzné vyjadrenie dotknutej právnickej osoby (binding statement of an affected legal person)The owner or operator of the road or utility network (§ 22 ods. 1 písm. a)Whether and how the plot can connect to water, sewer, electricity and roads.

The same paragraph lists assessments of the effect of the building on its surroundings, such as noise, air, surface water and groundwater (§ 30 ods. 2 písm. b). From 1 January 2027 the word "hydrogeologických" leaves that paragraph (zákon 243/2026).

Does the municipality give a binding opinion before design?

A zoning information is not a binding opinion. The act on spatial planning states that it is not issued for the placement or permit of a building (zákon 200/2022, § 40 ods. 13).

The binding opinion (záväzné stanovisko) of the planning authority judges whether a project agrees with the binding part of the plan (§ 24 ods. 1). The planning authority issues it on application (§ 24 ods. 3). The municipality is competent (§ 24 ods. 4). When the municipality has no territorial plan, the regional self-governing authority is competent (§ 24 ods. 5). The building office checks that the application agrees with this opinion (zákon 25/2025, § 57 ods. 2 písm. c).

Which findings can stop a project at this stage?

Four findings can end the application later, so check them first. The office rejects an application in these cases (zákon 25/2025, § 59 ods. 1):

  • The placement of the building conflicts with the binding opinion of the planning authority (písm. a).
  • The building does not have access from a public road with enough capacity for the operator, the users and visitors (písm. e).
  • An affected legal person states that the building cannot connect to water, sewer or the electricity grid at the site (písm. f). This does not apply when the building needs no connection or the networks are not within reach.
  • The builder has no right to the land that allows the building works. The office checks this right (§ 57 ods. 2 písm. a).

Walk the plot before you commission surveys: see site visit. If you still doubt that the project fits the plot, a feasibility study can test it before design starts.

How long does an affected legal person take to answer?

An affected legal person must issue the binding statement within 30 days of the request (zákon 25/2025, § 22 ods. 5). For a complex building the limit is 60 days. If the person asks you to make the request more exact, the period stops running. If the person does not answer in time, the act presumes no comments and no justified requirements (§ 22 ods. 5).

The same paragraph covers the request of the builder or of the designer (§ 22 ods. 3). The affected legal person must also give the designer, on request, the data from its documentation that the design needs. The designer pays reasonable costs (§ 22 ods. 2).

How long does pre-design preparation take and what does it cost?

No act sets a duration or a price for pre-design preparation. The time depends on the surveyor, the geotechnical firm, the municipality and the affected legal persons. Each party sets its fee by contract. Ask each one for a written quote and a delivery date before you commission the work.

What replaced the old steps before design?

Since 1 April 2025 the first project level is the building intent (stavebný zámer) under Act 25/2025 (§ 9 ods. 2). In the old regime, which ended on 31 March 2025, the first level was the documentation for the territorial decision (DÚR). For the old terms, the act now reads "konanie o stavebnom zámere" and "overenie projektu stavby" (§ 84 ods. 11 písm. a and b). The table shows the pairs. A pre-design checklist that mentions DÚR belongs to the old regime.

Old term (until 31 March 2025)Term in Act 25/2025
Územné konanieKonanie o stavebnom zámere
Stavebné konanieOverenie projektu stavby
Záväzné stanovisko k územnému konaniuZáväzné stanovisko k stavebnému zámeru

Frequently asked questions

What is pre-design preparation?
Pre-design preparation (predprojektová príprava) is the work before the designer starts the building intent. The builder gathers ownership, planning, survey and utility information. Act 25/2025 names the stage once, in § 35 ods. 3, and gives no list of steps.
Who pays for the surveys before design?
The builder arranges and pays for them unless the builder and the designer agree otherwise. The act gives the builder the duty to arrange the geodetic work, the engineering geological survey and other surveys the project needs (§ 30 ods. 2).
Is zoning information enough to know if I can build?
No. A zoning information (územnoplánovacia informácia) states the conditions of the plan but is not a binding opinion (zákon 200/2022, § 40 ods. 13). The planning authority issues the binding opinion on application (§ 24 ods. 3).
Do I need a land registry extract before design?
Yes, in practice, because the building office checks that you have a right to the land that allows the works (zákon 25/2025, § 57 ods. 2 písm. a). A výpis z listu vlastníctva is a public document and shows the owners and the burdens (zákon 162/1995, § 69 ods. 3).
How long does a utility company have to answer?
An affected legal person must issue the binding statement within 30 days, and within 60 days for a complex building (§ 22 ods. 5). If it does not answer in time, the act presumes it has no comments.
Is pre-design preparation a legal procedure?
No. The act defines no procedure or decision for it. The proceedings start with an application on the building intent. The builder attaches the project documentation and the report on the discussion of the intent (§ 50 ods. 1 and 2).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 9, 22, 29, 30, 34, 35, 50, 57, 59, 84
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon · Národná rada Slovenskej republiky, via Slov-Lex
  3. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 24 ods. 1, 3 to 5, § 40 ods. 13
  4. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (Katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 69 ods. 2, 3, 6