A design brief is a written statement of what the client wants to build, how the building works in use, and the budget and schedule.
What is a design brief?
A design brief is a written statement of what the client wants to build and how the building will be used. In Slovak it is the zadanie, and the Building Act calls it technické zadanie.
The brief comes before the design. The architect reads it, asks questions and answers it with an architectural study. The brief states the problem and the study proposes a solution. A brief for a house usually covers the household, the rooms, the plot, the budget and the schedule. The sections below describe that content as practice. The law fixes only a small part of it.
Does the Building Act require a design brief?
The Building Act requires the client to give the designer a technical brief, but it sets no form for it.
Under § 30 ods. 1 of the Building Act (Act 25/2025 Z. z.), the client (stavebník) must give the designer a technical brief (technické zadanie) that states the purpose of the building, its operation and its scope. The designer then prepares the stavebný zámer as the client requires (§ 35 ods. 6 písm. a). The act does not list the headings of the brief. The decree on documentation, 60/2025 Z. z., sets the content of the stavebný zámer and the projekt stavby, not of the brief.
The Slovak Chamber of Architects names one phase of its service standard Zadanie (FS 1 (A)). Its page does not describe the content of the phase. See design phases.
What does a design brief for a house contain?
A brief for a house describes the people, the rooms, the plot, the budget and the schedule, in plain language that the architect can check.
| Topic. | What to write. | Question to answer. |
|---|---|---|
| Household. | Who lives in the house now and in the years ahead, and any need for access without stairs. | Who uses the house on a normal day? |
| Rooms. | The rooms you need, their purpose and approximate size. | Which rooms must exist and which are optional? |
| Connections. | Which rooms must be next to each other and which must be apart. | Should the kitchen open to the living room? |
| Plot. | What you know about the plot, its orientation and its constraints. | Which documents on the plot do you already hold? |
| Budget. | The sum you can pay for the building and for the design, stated separately. | What is the upper limit? |
| Schedule. | The date you want to move in and any fixed dates. | Is any date fixed by a loan or a sale? |
| Building standard. | Wishes for energy use, for example a passive house. | Which energy goal do you want? |
Write down priorities as well as wishes. When the budget is too small for all rooms, the architect needs to know which ones you keep. For the cost of the building, see construction budget.
What is a room programme?
A room programme is a list of the rooms the building needs, with the purpose, the approximate area and the neighbours of each room.
A short list is enough for a house, for example bedrooms, bathrooms, a kitchen with a dining area and a work room. For each room, write what happens in it and how many people use it. State whether an area figure is the usable floor area of the room or includes walls and corridors. Areas can be counted both ways, so a figure without this note can be misread.
Write the links between rooms as well. A question such as "should the work room be away from the living room" changes the plan more than a difference of two square metres. See day zone for the part of the house used in the daytime.
How should I prepare for the first meeting with an architect?
Bring a short list of rooms, a budget limit, a date and the documents you hold on the plot.
- a list of the people who will live in the house and how they use it.
- the rooms you need, in order of priority.
- pictures of houses and rooms you like, and some you do not like.
- the budget limit and the date you want to move in.
- every document you hold on the plot.
- your questions for the architect.
Tell the architect which surveys exist. Under § 30 ods. 2 of the Building Act, the client arranges three things unless client and designer agree otherwise. These are the survey by a surveyor, the geological and other investigations and the opinions of affected legal persons. The architect can then say which are missing. A site visit usually follows.
How is a design brief different from a feasibility study or an investment intent?
A design brief says what to build. A feasibility study checks whether the project can be done. An investment intent states why the investor wants it.
| Document. | Question it answers. |
|---|---|
| Investment intent. | What is the investor's goal and purpose? |
| Feasibility study. | Can the project be done on this plot, under these rules and with this money? |
| Design brief. | What does the client want built and how will it be used? |
| Architectural study. | What design answers the brief? |
The results of a feasibility study go back into the brief. For a family house, one short brief can cover both the intent and the brief.
Can the brief change during the design?
Yes, a brief can change, and the change should be written down and agreed with the architect.
A change after the architect starts can mean more work and a different price. Suppose the design contract is a contract for work and the parties agree the price by budget. Then the price does not rise without the client's consent (Civil Code § 635 ods. 1). If the price is an estimate, the architect must warn the client in writing when it will be exceeded by a lot (§ 636 ods. 1). Ask the architect how the contract prices a change. See the architect fee page.
Frequently asked questions
- What is the difference between a design brief and an architectural study?
- A design brief states what the client needs. An architectural study is the architect's design answer to it. The brief comes first.
- Does Slovak law require a design brief?
- The Building Act requires the client to give the designer a technical brief on the purpose, operation and scope of the building (§ 30 ods. 1). It sets no form and no headings.
- What should a design brief for a house include?
- It should describe the household, the rooms and their links, and what you know of the plot. It should also state the budget limit and the date you want to move in. Add priorities, so the architect knows what to keep if the budget is short.
- Can I hire an architect without a design brief?
- Yes. The architect can help you write one in the first meetings. You still need to state the purpose, operation and scope of the building, because the act puts that duty on the client (§ 30 ods. 1).
- Who arranges the surveys the design needs?
- Unless client and designer agree otherwise, the client does (Building Act § 30 ods. 2). It covers the surveyor, geological and other investigations and the opinions of affected legal persons.
- Can a design brief change during the design?
- Yes. Write the change down and agree it with the architect. Check how your contract prices it. A price agreed by budget does not rise without your consent (Civil Code § 635 ods. 1).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 30 ods. 1 a 2, § 35 ods. 6 písm. a)
- Štandardy služieb architektov · Slovenská komora architektov
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 635 ods. 1, § 636 ods. 1