Design service phases
Design phases are the steps of an architect's service, named in the Chamber of Architects standard, from initiation to use of the building.
What are architect service phases?
Architect service phases (výkonové fázy) are the steps in which an architect delivers services, from initiation of a project to use of the finished building.
The Slovak Chamber of Architects (SKA) published the Štandardy služieb architektov in 2025. The standards split architect services into basic, further and additional services. They organise the services in phases, which SKA describes as value packages across preparation, construction, modification and use of a building. The standards are a method for contracts between clients and architects. SKA states that their use is voluntary.
The phases are not in the Building Act. The act has its own documents and procedures, covered below.
What phases does the SKA standard define?
The SKA standard defines nine architect phases, numbered FS 0 to FS 8 with the mark (A).
| Phase. | SKA name. |
|---|---|
| FS 0 (A). | Iniciovanie. |
| FS 1 (A). | Zadanie. |
| FS 2 (A). | Koncept. |
| FS 3 (A). | Návrh. |
| FS 4 (A). | Povoľovanie. |
| FS 5 (A). | Príprava výstavby. |
| FS 6 (A). | Výstavba. |
| FS 7 (A). | Odovzdanie a kolaudácia. |
| FS 8 (A). | Užívanie. |
The SKA web page lists the names only. It does not describe the content of each phase. SKA publishes that detail in a downloadable document, dated May 2025 on the page, and in a web application at archdata.sk. The page states no percentages and no fee share for a phase.
The first outputs of the design work, such as the architectural study, belong to the early phases. The SKA page does not state which one.
SKA names the phase FS 1 (A) Zadanie. Under § 30 ods. 1 of the Building Act, the client must give the designer a technical brief (technické zadanie). The brief states the purpose, operation and scope of the building. See design brief.
What phases does a general designer have?
A general designer (generálny projektant) has five phases in the SKA standard, marked (GP), and some of them combine architect phases.
| Phase. | SKA name. |
|---|---|
| FS 0+1 (GP). | Organizačné zabezpečenie. |
| FS 2+3+4 (GP). | Projektová príprava. |
| FS 5 (GP). | Príprava výstavby. |
| FS 6 (GP). | Výstavba. |
| FS 7+8 (GP). | Dokončenie projektu. |
Under § 35 ods. 3 of the Building Act, the general designer coordinates the designers of the parts of the documentation and other specialists. The general designer also performs the usual tasks in the pre-design preparation, during the works and at the final inspection (kolaudácia). Under § 35 ods. 5, the general designer answers to the client for the completeness of the project documentation.
Which documents does the Building Act use?
The Building Act (Act 25/2025 Z. z.) names the documents of a building in § 8 to § 10. It does not use the old names DÚR and DSP.
Section 8 ods. 2 sets three levels of building documentation: project documentation (projektová dokumentácia), implementation documentation (realizačná dokumentácia) and operation documentation (prevádzková dokumentácia). Decree 60/2025 Z. z. § 6 names the annex that sets the content and scope of each document.
| Document. | What the act says. | Content in decree 60/2025. |
|---|---|---|
| Stavebný zámer (building intent). | Text and drawings of the urban, architectural and basic building solution. It is the basis for the building intent procedure (§ 9 ods. 2). | Annex 15. |
| Projekt stavby. | Text and drawings of the architectural and building-technical solution, in line with the stavebný zámer. It is the basis for building the structure (§ 9 ods. 3). | Annex 17. |
| Projekt stavby na ohlásenie. | The same kind of solution for a structure that needs only a notification (§ 9 ods. 4). | Annex 14. |
| Vykonávací projekt. | Detailed elaboration of the verified projekt stavby for the works (§ 9 ods. 5). | Annex 18. |
| Dokumentácia skutočného zhotovenia stavby. | Part of the realizačná dokumentácia (§ 10 ods. 1). | Annex 21. |
The vykonávací projekt is compulsory for a vyhradená stavba (§ 9 ods. 5). Ask the architect whether your building falls in that class. The realizačná dokumentácia also contains the production preparation of the contractor and the site diary (stavebný denník, § 10 ods. 1). For the as-built set, see as-built documentation.
The amendment Act 243/2026 changes the wording of § 9 and § 10. Its articles I to XIII apply from 1 January 2027. They remove the final statement of the site manager from the realizačná dokumentácia. The document names above stay.
Are DÚR, DSP and realizačný projekt still used?
People still search and use these names, but the Building Act in force since 1 April 2025 does not use them.
DÚR (documentation for the territorial decision) and DSP (documentation for the building permit) come from the old regime. The current act uses the stavebný zámer for the building intent procedure and the projekt stavby for verification and for building. The decree names the procedure forms by section of the Building Act. These are the building intent decision (§ 50), the verification of the projekt stavby (§ 65), the notification (§ 63) and the kolaudácia (§ 66).
The term realizačný projekt is also not an act term. The act has the vykonávací projekt in the project documentation and the realizačná dokumentácia as a separate level. When a contract uses an older name, ask the architect which document of the current act it means. See building permit documentation and execution project.
Which duties does the designer have during construction?
The designer has a right and some duties during the works. The author of the architectural work has a separate right of author supervision.
- The designer must take part in an inspection when the client calls the designer. This applies when the design changes or a product replaces another (§ 35 ods. 7 písm. a).
- The designer must ask the client and the site manager to remove deviations from the projekt stavby (§ 35 ods. 7 písm. b). The designer must record the ones that remain in the site diary (§ 35 ods. 7 písm. b).
- The designer may supervise on site that the works follow the projekt stavby, called dohľad projektanta (§ 35 ods. 10).
- The author of the architectural work may supervise that the works follow the design, called autorský dohľad (§ 35 ods. 10).
- The designer does not answer for changes that the designer did not approve (§ 35 ods. 10).
See author supervision. Whether these services are in the fee depends on the contract. The act sets no tariff, as § 11 of Act 138/1992 shows. See architect fee.
Frequently asked questions
- What phases does the Slovak Chamber of Architects define?
- The SKA standard has nine architect phases, FS 0 (A) to FS 8 (A). They are Iniciovanie, Zadanie, Koncept, Návrh, Povoľovanie, Príprava výstavby, Výstavba, Odovzdanie a kolaudácia and Užívanie. SKA published it in 2025.
- Are the SKA phases required by law?
- No. SKA says the use of its standards is voluntary. The Building Act has its own documents and procedures, and it does not use the FS numbers.
- Which documents does the Building Act use instead of DÚR and DSP?
- The act uses the stavebný zámer and the projekt stavby (§ 9). DÚR and DSP are names from the old regime. They are not terms of Act 25/2025 Z. z.
- What is a vykonávací projekt and is it compulsory?
- It is the detailed elaboration of the verified projekt stavby for the works (§ 9 ods. 5). It is compulsory for a vyhradená stavba. For other buildings the act does not require it in that paragraph.
- What does each SKA phase contain?
- The SKA web page does not say. The detail is in the SKA standards document and the archdata.sk application. Ask the architect to list the deliverables of each phase in the contract.
- Does each phase have a fixed share of the fee?
- No source gives one. The SKA page states no percentages, and Act 138/1992 sets no tariff. The contract sets the payment for each phase.
Sources
- Štandardy služieb architektov · Slovenská komora architektov
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Slov-Lex · § 8, § 9, § 10, § 30, § 35
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Slov-Lex · § 6
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) v znení neskorších predpisov a ktorým sa menia a dopĺňajú niektoré zákony · Slov-Lex
- Zákon č. 138/1992 Zb. o autorizovaných architektoch a autorizovaných stavebných inžinieroch · Slov-Lex · § 11