Execution project (implementation project)

An execution project (vykonávací projekt) is the detailed design that refines the verified project so a contractor can build from it.

What is an execution project?

An execution project (vykonávací projekt) is the detailed design that refines the verified project of the building. It serves the carrying out of building work (§ 9 ods. 5 of the Building Act 25/2025 Z. z.). It is also called an implementation project. Slovak designers also say realizačný projekt. The act, the decree 60/2025 Z. z. and the amending act 243/2026 Z. z. do not use that name. This page uses the term of the act, execution project.

The act also has realizačná dokumentácia, which is a different thing. It means four documents (§ 10 ods. 1). They are the contractor's production preparation, the construction diary, the documentation of actual execution and the final statement of the site manager.

Does the law require an execution project?

For a reserved structure (vyhradená stavba) it does. The act says the execution project is mandatory for it (§ 9 ods. 5). The builder of a reserved structure must also arrange the execution project and a check of the load-bearing structures (§ 30 ods. 5 písm. b). A reserved structure is a technically demanding or unusual building or engineering structure (§ 2 ods. 8). The list holds, for example, a multi-storey building with the last ceiling more than 32 m above the terrain. It also holds a single-storey building with a roof span of more than 30 m. Ask the designer whether your structure is on the list.

For other structures the act texts read name no duty to prepare the execution project. The builder and the designer agree on it, and the builder and the contractor agree by contract which documents the work follows.

What does an execution project contain?

The decree 60/2025 Z. z. gives the purpose and the content in annex 18. The execution project refines and completes the building intent and the verified project. It defines structures, products, materials, machines, equipment and construction details. The detail is enough for building production and for the contractor's production preparation. The project keeps the general parts and the set parameters of the verified project.

  • Parts A to E: list of documentation, summary report, site drawings, documentation of building objects, annexes.
  • The summary report has the same parts as the summary report of the project of the building.
  • The site drawings give a more detailed coordination of parts of the building, paved areas, terrain, grading, rainwater and green elements. See site plan drawing.
  • Each building object has a technical report, calculations and drawings. The designer adds calculations only where the project changes or completes the calculations of the verified project. Otherwise the project refers to the verified project.
  • The project includes a control structural assessment of the load-bearing structures.
  • Drawings use scale 1:100 or 1:50, or another scale suited to the structure. Detail drawings use scales that show the construction clearly.
  • The drawings include a description of materials and lists of products. The detail allows a quantity list for materials, see bill of quantities.

Parts of the verified project that the execution project does not change are not redrawn. They appear in the list of annexes (annex 18).

How does the execution project differ from the project of the building?

The project of the building is the document that the building office verifies. The execution project works from the verified project and adds detail. The table compares them.

PointProject of the buildingExecution project
What the act saysArchitectural and building-technical design in line with the building intent. It is the basis for building the structure (§ 9 ods. 3).Detailed elaboration of the verified project for carrying out building work (§ 9 ods. 5).
Check by the authorityYes, verification within 30 days (§ 65).The act text read names no verification step.
MandatoryNeeded for the verification procedure.For a reserved structure (§ 9 ods. 5).
Plans, sections, elevationsScale 1:100 or 1:50, or another scale (annex 17).The same scales, plus detail drawings (annex 18).
CalculationA structural calculation that a reviewer can test (annex 17).A control structural assessment, and other calculations only where they change (annex 18).

The building permit documentation page explains the older name. For the design stage before the building intent, see architectural study.

How does it relate to the contractor's production preparation?

The production preparation (výrobná príprava zhotoviteľa stavby) is the contractor's own document. It completes the project of the building and the execution project for details that they do not cover (decree 60/2025, annex 19). Examples are drawings of auxiliary structures and reinforcement drawings. The execution project is the direct basis for it (annex 18, part D). The execution project does not prescribe the construction methods and does not hold the details of the production preparation.

Who prepares it and who agrees it by contract?

A designer may prepare every level of project documentation, including the execution project (§ 35 ods. 1). Only an authorised person can be a designer (§ 35 ods. 4). If several designers work on a project, the general designer coordinates them (§ 35 ods. 3). See coordination of professions.

A contract for work (zmluva o dielo) binds the contractor to carry out the work for the agreed price (Civil Code § 631). The contractor carries out the work according to the contract (§ 633 ods. 1). The contract therefore needs to name the documents that the work follows. Name the execution project, with its revision, if the work follows it. See contractor tender.

What happens during construction?

Before work starts, the builder gives the contractor three things (§ 30 ods. 3 písm. b). They are the verified project, the final decision on the building intent and the plots for the construction site. The person appointed to supervise construction checks the work against the verified project (§ 36 ods. 1 písm. a).

The designer may supervise the work for conformity with the project. The author of the architectural work may supervise it for conformity with the design (§ 35 ods. 10). The act calls this autorský dohľad. See author supervision. If work leads to a deviation from the verified project, an extraordinary inspection of the structure can be called (§ 43 ods. 2). Afterwards the documentation of actual execution records the built state, see as-built documentation.

What changes from 1 January 2027?

Act 243/2026 Z. z. does not amend the definition of the execution project in § 9 ods. 5. It removes the final statement of the site manager from the list in § 10 ods. 1 and removes § 10 ods. 3. The amendment applies from 1 January 2027.

Frequently asked questions

What is a realizačný projekt?
A realizačný projekt is the common name for the detailed design that the Building Act 25/2025 Z. z. calls vykonávací projekt. It refines the verified project for carrying out building work (§ 9 ods. 5). The act does not use the name realizačný projekt.
Is an implementation project required by law in Slovakia?
It is mandatory for a reserved structure (vyhradená stavba), under § 9 ods. 5 of Act 25/2025 Z. z. The act texts read name no duty for other structures. The builder and the contractor agree by contract which documents the work follows.
What is the difference between the project for the building office and the execution project?
The building office verifies the project of the building (§ 65). The execution project refines the verified project into details for building production, such as products, materials and construction details (decree 60/2025, annex 18).
What does the decree say an execution project contains?
It has five parts: list of documentation, summary report, site drawings, documentation of building objects and annexes. It includes a control structural assessment of the load-bearing structures and drawings at 1:100 or 1:50 with detail drawings (decree 60/2025, annex 18).
Is the execution project the same as the contractor's production preparation?
No. The production preparation is the contractor's own document. It completes details that the project of the building and the execution project do not cover (decree annex 19). The execution project is the direct basis for it.
Which structures are reserved structures?
A reserved structure is a technically demanding or unusual building or engineering structure (§ 2 ods. 8). The list holds, for example, a multi-storey building with the last ceiling more than 32 m above the terrain.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 2 ods. 8, § 8, § 9 ods. 5, § 10, § 30 ods. 3, 5, § 35, § 36, § 43 ods. 2, § 65
  2. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, Slov-Lex · annex 17, 18, 19, 21
  3. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated text) · Národná rada Slovenskej republiky, Slov-Lex · Art. I points 41, 42
  4. Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 631, § 633 ods. 1