Construction Diary

A construction diary is the record in which the site manager writes how building work proceeds, from site takeover to building handover.

What is a construction diary?

A construction diary (stavebný denník) is the record of how building work proceeds. It runs from the takeover of the site to the full completion of the work and the handover of the building. It is part of the execution documentation (realizačná dokumentácia) of the building (§ 10 ods. 1 and 2 of act 25/2025 Z. z.).

Decree 60/2025 Z. z. says what it records (§ 6 ods. 7, annex 20):

  • the course of the building work during the whole construction
  • important data on the timing and quality of the work
  • deviations from the documentation of the building, with the reason
  • control inspections of the building and state building supervision
  • entries of the other authorised participants in construction

Who keeps the construction diary?

The site manager (stavbyvedúci) keeps it (§ 37 ods. 1, § 39 ods. 1). The site manager must allow entries by the persons named in § 39 ods. 2:

  • the general designer, the designers of parts of the project and the fire protection specialist
  • the builder and the owner of the building
  • the geodet and the person who carries out the building supervision
  • the person who carries out state building supervision or a control inspection, and authorised persons of other supervising bodies
  • the coordinator of project documentation, the safety technician and the safety coordinator
  • the author of the architectural work, for authorial supervision
  • the geologist and the geotechnician
  • the manager of an apartment building, if the work is on such a building

The person who carries out the building supervision (stavebný dozor) checks how the diary is kept (§ 36 ods. 1 písm. h). If the builder does the work without a contractor, the builder keeps the diary and records the essential events of the work (§ 30 ods. 6 písm. g). See builder and contractor.

What must a construction diary contain?

Annex 20 of decree 60/2025 sets four parts.

PartWhat it holds
A. Identification dataThe building ID if the information system assigned one, the name and place of the building, and the number and date of the verification clause of the project. The data of the builder, the owner, the designer, the contractor, the subcontractors and the site manager, and changes of these persons. The persons authorised to write, the contracts for the work, and the dates of site takeover and handover
B. Records of working meetingsMinutes of control inspections. Records of state building supervision and of other supervising bodies. Records of facts that decide the performance of the contract
C. Technical records, regular entriesDate, working hours, weather, number and position of workers, progress and scope of work. Start, interruption or stop of work, with the reason
C. Technical records, other entriesDeliveries and installation of materials, certificates of products and machines used. Facts that affect the flow or quality of the work, finds on site, takeover of the foundation base, tests and measurements. Checks of reserved technical equipment, instruction of workers and accidents. Changes against the verified project, waste, other findings and consents. Records of the supervisor, the designer and other participants
D. AttachmentsDocuments kept outside the diary. Examples are the site handover record, the protocol on surveying data, the staking protocol, control measurement protocols and the health and safety plan

The annex lists the content. It does not say that entries must be daily. It asks for regular entries on the progress of the work.

Which events must be recorded by law?

The act names these entries:

  • staking out of the building, by the geodet (§ 42 ods. 3), and the geodet's record of handover of surveying data, as a protocol or a diary entry (§ 40 ods. 3 písm. c)
  • each control inspection (§ 43 ods. 5) and each agreed deviation from the verified project (§ 43 ods. 2, § 32 ods. 3)
  • deviations that the designer or the supervisor found and nobody corrected (§ 35 ods. 7 písm. b, § 36 ods. 1 písm. f)
  • a find of a monument, an archaeological find or a protected natural feature, with time, circumstances, report and measures (§ 44 ods. 1 písm. d)
  • an immediate stop of work that the supervisor orders, if the supervisor does not report it to the building inspectorate (§ 36 ods. 2)
  • the end of state building supervision when the inspector finds no defects. Until 31 December 2026 this may be a diary entry or an official record (§ 72 ods. 3). From 1 January 2027 only the official record stays (act 243/2026)

When does the diary start and end?

The diary is with the site manager for entries and checks. This runs from the first day the site is set up until the building is handed over (§ 39 ods. 1). The project verified by the building office and the diary must be on site during the whole construction. An authorised person keeps the diary (§ 6 ods. 5). For a set of buildings, the diary is kept separately for each building (§ 10 ods. 2).

Is the diary paper or electronic, and is there an official template?

The diary is kept as a rule in electronic form (§ 10 ods. 2). The act does not say paper is forbidden. It says "as a rule electronic". Neither the act nor decree 60/2025 gives a fill-in form. The decree sets the content and extent in annex 20. Another annex of the decree sets how electronic files are named.

Is the diary part of the proposal for kolaudácia?

Yes, it is the first attachment on the list, and the attachments depend on the type of building (§ 66 ods. 2). Act 243/2026 keeps the diary on the list from 1 January 2027. See the occupancy certificate entry and occupancy approval.

What happens if the site manager does not keep the diary?

The building inspectorate fines the site manager from €300 to €3,000 for these failures (§ 80 ods. 7 písm. e):

  • the site manager does not keep the diary
  • the site manager keeps it so that it is stolen, damaged or spoiled, or gets unauthorised entries
  • the site manager does not make needed entries
  • the site manager does not allow entries by authorised persons

From 1 January 2027 § 80 ods. 7 is deleted. A new § 80 ods. 6 sets the same range of €300 to €3,000 for a site manager who does not fulfil the duties of the act.

Frequently asked questions

Who keeps the construction diary?
The site manager keeps it (§ 37 ods. 1 and § 39 ods. 1 of act 25/2025). If the builder does the work without a contractor, the builder keeps it (§ 30 ods. 6 písm. g).
What must a construction diary contain?
Annex 20 of decree 60/2025 sets four parts: identification data, records of working meetings, technical records of the work and attachments. The technical records cover date, weather, workers, progress, deliveries, tests, finds and changes against the verified project.
Who may write in the construction diary?
The site manager must allow entries by the designers, the builder and the owner, the geodet and the building supervisor. Inspectors, other supervising bodies, safety coordinators, the author of the architectural work, the geologist and the geotechnician may also write. For apartment buildings the building manager may write too (§ 39 ods. 2).
Must the construction diary be electronic, and is there an official template?
The diary is kept as a rule in electronic form (§ 10 ods. 2). The act does not give a fill-in form and neither does decree 60/2025. Annex 20 of the decree lists the content and extent. A ready-made template from a private supplier is not an official form.
Can I keep the construction diary myself when I build my own house?
Yes. A builder who does the work without a contractor must keep the diary and record the essential events of the work (§ 30 ods. 6 písm. g). Building for yourself without a person who carries out building supervision is an offence (§ 79 ods. 2 písm. b).
Do I need the construction diary for kolaudácia?
Yes, the diary is an attachment to the proposal for kolaudácia, according to the type of building (§ 66 ods. 2). It stays on the list in the version from 1 January 2027.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 6, 10, 30, 32, 35, 36, 37, 39, 40, 42, 43, 44, 66, 72, 79, 80
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (Art. I from 1 January 2027, Art. XV) · Národná rada Slovenskej republiky, via Slov-Lex · Art. I bod 41, 42, 171, 220, 221
  3. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby (č. 60/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 6 ods. 7, annex 20