Occupancy Certificate

An occupancy certificate is the document that the building office issues after kolaudácia to certify that a finished building suits its designed use.

What is an occupancy certificate?

An occupancy certificate (kolaudačné osvedčenie) is the document that certifies a finished building is technically fit for its designed purpose. The building office issues it after kolaudácia. The act calls it the proof that kolaudácia took place. The as-built documentation (dokumentácia skutočného zhotovenia stavby) is attached to it (§ 67 ods. 1 and 2 of act 25/2025 Z. z.).

The certificate does not replace an operating permit that special regulations require (§ 67 ods. 3). The act does not use the name "certificate of fulfilment of building purpose". The Slovak term is kolaudačné osvedčenie.

How is it different from the old kolaudačné rozhodnutie?

The old procedure ended in a decision, the kolaudačné rozhodnutie. The new procedure ends in the certificate. Since 1 April 2025 the old name kolaudačné konanie means kolaudácia under the building act 25/2025 (§ 84 ods. 11 písm. c). See also occupancy approval and the occupancy decision.

The old rules still apply to a request for a kolaudačné rozhodnutie that is filed after 31 March 2025. This holds if the building has a zoning decision under the old rules. It also holds if the building has an old building permit and needed no zoning decision (§ 84 ods. 5 and 6).

An owner of an older building can also use the old review of fitness for use (preskúmanie spôsobilosti stavby na užívanie). The owner must apply by 31 March 2029 and the building must meet the old conditions (§ 84 ods. 7 písm. a). See review of fitness for occupancy.

Which buildings need an occupancy certificate?

A new building, a change of a completed building and a terrain modification that needed a decision on the building intent need kolaudácia. A finished building may go into permanent use only after kolaudácia. Kolaudácia is not required for buildings that need only a notification. It is also not required for alterations (stavebné úpravy), unless they come with a change of use (§ 66 ods. 1, version 1 November 2025 to 31 December 2026).

From 1 January 2027 act 243/2026 rewrites § 66 ods. 1. Kolaudácia then also covers alterations and maintenance for which a decision on the building intent was issued. The building office may waive kolaudácia for a notified building, alteration or maintenance. This applies if the office ruled after the notification that the work needs a decision on the building intent.

Which documents does the proposal for kolaudácia need?

Kolaudácia starts on the proposal of the builder (stavebník). The attachments depend on the type of building (§ 66 ods. 2). The list in the version in force from 1 November 2025 to 31 December 2026 is:

  • the construction diary
  • the final opinion of the site manager (záverečné stanovisko stavbyvedúceho)
  • the as-built documentation
  • the surveying documents: the geodetic documentation of the staking out, the control protocol on the spatial position and the geometric plan for the cadastre update (see as-built survey)
  • the handover protocol (the building office may waive it in justified cases)
  • the evaluation protocol of the trial operation, if it was permitted
  • records of tests on samples of building products taken on site
  • results of measurements and inspections (revízie) of reserved technical equipment, and documents on its fitness for safe operation
  • the geodetic survey of the finished building as built
  • the energy performance certificate, if the building must have one
  • binding opinions and statements of the affected bodies that were obtained before the proposal
  • proof of payment of the local development fee (miestny poplatok za rozvoj), if the municipality assessed it

Act 243/2026 changes this list from 1 January 2027. The table shows the changes.

TopicTo 31 December 2026From 1 January 2027
Site manager's final opinionAttachment to the proposalNot an attachment. § 66 ods. 2 písm. b) and § 10 ods. 3 are deleted
Handover recordProtocol, may be waived in justified casesRecord (zápis) that includes the contractor's declaration that the building conforms to the verified project. The text has no waiver
Checks of technical equipmentMeasurements and revízieMeasurements, official tests, expert inspections and expert tests
Right to the landNot listedProof of the builder's right to the land or building. It is needed if the as-built building differs from the building intent and the builder is not the owner
Unfinished related worksThe office checks that related works and access are finishedThe office does not assess them if they were not a condition of the permit and the builder shows safe use and access
StagesNot providedA separate stage of a building approved in one building intent can pass kolaudácia if it is safe to use alone
Several purposesNot providedThe certificate names every purpose. For buildings it gives the share of floor area for each
AppealNot statedNo appeal against the certificate (new § 67 ods. 7)

What does the building office check, and how long does kolaudácia take?

The building office announces the date of the inspection (kolaudačná obhliadka) within seven working days of receiving a complete proposal. The inspection takes place within 30 days of the notice. The office issues the certificate within 15 days of the inspection if the building is fit for operation (§ 66 ods. 3 and 7). Act 243/2026 does not change these periods.

The office invites the general designer and the general contractor to the inspection. For a reserved building it also invites the person who carried out the building supervision and the future operator (§ 66 ods. 3).

At the inspection the office checks whether (§ 66 ods. 4):

  • the building is finished, fit for separate use and safe, in line with the verified project
  • defects found at control inspections were removed
  • the technical building system and other technical equipment work
  • the building is connected to working utility networks, where they exist in the municipality
  • rainwater is collected or drained without burdening the surroundings
  • reserved technical equipment runs smoothly and safely
  • the building meets the required energy performance

If the building is unfinished or has defects, the office records them and asks the applicant to remove them within a set period. The office interrupts kolaudácia (§ 66 ods. 5). If the applicant does not remove them in time, the office stops kolaudácia (§ 66 ods. 6). The office also stops it if the building was built against the verified project (§ 66 ods. 8). These paragraph numbers belong to the version to 31 December 2026.

Can I use the building before I get the certificate?

No. A finished building may go into permanent use only after kolaudácia (§ 66 ods. 1). To operate a building, or let another person operate it, before the certificate is issued is an offence (§ 79 ods. 2 písm. e). The building office can allow two forms of temporary use.

  • Trial operation (skúšobná prevádzka) is for tests and measurements that only operation can show. It may last up to 24 months. Extensions are possible up to four years in total (§ 69 ods. 1 and 4). The limits do not apply to line structures and nuclear structures.
  • Early use (predčasné užívanie) lets the builder use a building, or a part that can stand alone, before it is fully finished. It may last up to 12 months. Extensions are possible up to five years in total (§ 70 ods. 1 and 4).

Both permits end when the certificate is issued, if they do not end earlier (§ 69 ods. 6 and § 70 ods. 5).

What does the occupancy certificate cost?

The administrative fee is 30 % of the fee for the decision on the building intent for the same type of building (act 145/1995 Z. z., item 59 písm. e and a). For a building with one or two dwellings that base fee is €300.

FeeAmountBasis
Occupancy certificate, building with one or two dwellings€9030 % of €300 (item 59 písm. e and a)
Repeated inspection (opakovaná kolaudačná prehliadka), same building€6020 % of €300 (item 59 písm. f)

The amounts are the same in the versions of the act valid from 1 November 2026, 1 December 2026 and 1 January 2027. Other building types follow the rates in item 59 písm. a. The fee does not include the documents you attach, such as the geodetic survey.

What happens after the certificate is issued?

The building office tells the affected authorities that it issued the certificate (§ 67 ods. 4). The administrator of the information system of spatial planning and construction informs the district cadastre office. It sends the information on the certificate and on the verification of the as-built documentation (act 162/1995 Z. z., § 21 ods. 2). See cadastral registration.

The building may then be used only for the purpose named in the certificate (§ 68 ods. 1). A change of the prevailing way of use is a change of use. See change of use.

Frequently asked questions

What documents do I need for kolaudácia of a family house?
The attachments depend on the type of building (§ 66 ods. 2 of act 25/2025). They include the construction diary, the site manager's final opinion, the as-built documentation, surveying documents and the energy performance certificate if one is needed. The full list is above. From 1 January 2027 the final opinion is no longer an attachment.
Is the occupancy certificate the same as the old kolaudačné rozhodnutie?
No. The old procedure ended in a decision, the kolaudačné rozhodnutie. Since 1 April 2025 the procedure is called kolaudácia and ends in the kolaudačné osvedčenie (§ 66, § 67, § 84 ods. 11 písm. c). The old rules still apply to some cases that began under the old permits (§ 84 ods. 5 and 6).
Can I move into the house before I have the certificate?
No. A finished building may go into permanent use only after kolaudácia, and to operate it earlier is an offence. The building office may allow trial operation for up to 24 months or early use for up to 12 months (§ 66 ods. 1, § 69, § 70, § 79 ods. 2 písm. e).
How much does the occupancy certificate cost?
For a building with one or two dwellings the fee is €90. This is 30 % of the €300 fee for the decision on the building intent (act 145/1995, item 59 písm. e and a). A repeated inspection costs €60. Other building types follow the rates in item 59 písm. a.
How long does the building office take?
It announces the inspection date within seven working days of a complete proposal. The inspection takes place within 30 days of that notice. The office issues the certificate within 15 days of the inspection if the building is fit for operation (§ 66 ods. 3 and 7).
Is a geodetic survey part of the documents?
Yes. The list to 31 December 2026 names four surveying items: the geodetic documentation of the staking out, the control protocol on the spatial position, the geometric plan and the geodetic survey of the finished building. Which of them applies depends on the type of building (§ 66 ods. 2).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 10, 15, 66, 67, 68, 69, 70, 79, 84
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (Art. I from 1 January 2027, Art. XV) · Národná rada Slovenskej republiky, via Slov-Lex · Art. I bod 149 to 162, Art. XV
  3. Zákon Národnej rady Slovenskej republiky č. 145/1995 Z. z. o správnych poplatkoch · Národná rada Slovenskej republiky, via Slov-Lex · Položka 59 písm. a, e, f
  4. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 21 ods. 2