Start of construction

The start of construction is the point where building works directly tied to the structure start, not fencing or site set-up.

What is the start of construction under Slovak law?

The start of construction (začatie stavby) is the point where building works directly tied to making the structure start (act 25/2025 Z. z., § 41). Many people call it groundbreaking. The act does not use that word and does not mention a ceremony.

Act 25/2025 applies from 1 April 2025 (Art. IV). This page covers act 25/2025 only.

Which works are not yet the start of construction?

The act lists preparatory works that do not count as the start (§ 41):

  • fencing the building place and setting up the site
  • equipping the site
  • access and a drive-in to the site
  • water and electricity supply to the site
  • removing vegetation
  • stripping the topsoil of agricultural land
  • hauling away waste
  • marking the building

Preparatory works are also not "unpermitted building works" (§ 28 ods. 2). The site must carry a sign with basic data on the structure and the parties (§ 6 ods. 3 písm. b). The decision on the building intent may set requirements for the marking of the site and the building (§ 60 ods. 1 písm. d).

What must be in place before construction starts?

A building may be built only to a verified project (§ 25). The project is verified in the proceedings on the building intent, or on a notification. Before the first building works, these items must be in place:

  • The decision on the building intent is final, and the building office has verified the project with a verification clause (overovacia doložka). The office has 30 days (§ 65 ods. 2, 5).
  • The builder has handed the verified project, the final decision and the land for the site to the contractor (§ 30 ods. 3 písm. b). See site handover.
  • A surveyor has staked out a new building, an extension or terrain works (§ 42 ods. 1). See staking out a building.
  • The builder has told the building office that the works start (§ 30 ods. 3 písm. a).

The act does not fix an order for these steps. The verification clause is not a start permit. The office issues it before the works, and it lapses if the works do not start in time.

Must I tell the building office before I start?

Yes. Before the works start, the builder must notify the building office of the start and name the contractor (§ 30 ods. 3 písm. a). The 2026 text names no period and no form for this notice.

If the builder picks the contractor after the project is verified, the decision may add a duty. The builder then gives the contractor's trade name and the site manager's name within 15 days of signing the contract (§ 60 ods. 1 písm. h).

How long can I wait before I start?

The decision on the building intent is valid for a set time from the day it becomes final. The office may set a longer time (§ 61 ods. 1).

TypeValidity of the decision
Standard structure2 years
Linear structure and reserved structure3 years
Information construction (informačná konštrukcia) and assembled product (zmontovaný výrobok)1 year

The decision does not lapse if the builder files a request for project verification in that time. It lapses on the day the verification clause lapses (§ 61 ods. 1). The clause lapses if the works have not started within two years of its issue, unless the office set a longer time (§ 65 ods. 6). The office extends the validity of the decision on request by up to two years each time. The total may not exceed seven years, except for linear structures and nuclear facilities (§ 62 ods. 3). See validity of the decision.

Notified works must start within three years of the verification of the project (§ 63 ods. 10).

Legal relations that rest on a building permit under the old rules remain (§ 84 ods. 1). Periods that already run continue (§ 84 ods. 3). The old act decides how long such a permit is valid.

Do I wait 30 days after a notification?

No. For works that need only a notification, the 30 days are the office's deadline. The office must verify the project within 30 days of delivery (§ 63 ods. 6). If it does not, the act presumes that it issued the clause (§ 63 ods. 7). Work may not start without a verified project (§ 25 and § 79 ods. 2 písm. a). See minor structure notification.

What happens if I start without a verified project?

Building works without a verified project, or against it, are unpermitted works (§ 28 ods. 1). A state building inspector calls on the builder and the contractor to stop them at once (§ 73 ods. 4). Building without a verified project is an offence. The fine is 30 to 15,000 euro (§ 79 ods. 3 písm. a and ods. 6 písm. c). For a notified structure the fine is 30 to 3,000 euro (§ 79 ods. 2 písm. a and ods. 6 písm. b). These are the amounts to 31 December 2026.

What runs from the first day?

The construction diary runs from the takeover of the site until the handover of the building (§ 10 ods. 2). The site manager keeps it from the first day the site is set up (§ 39 ods. 1). The site manager manages the site and runs it (§ 37 ods. 1).

If the decision sets a control inspection before a stage of the works, the site manager must announce the date in good time. The site manager tells the building office, the affected authority, the builder, the designer and the supervisor (§ 43 ods. 1).

How is the start different from other steps?

StepWhat it isSource
Start of constructionWorks directly tied to making the structure startAct 25/2025, § 41
Preparatory worksFencing, site set-up, access, utilities for the site, vegetation removal, topsoil stripping, waste removal, markingAct 25/2025, § 41
Stake-outA surveyor marks the building on the ground. It must come before a new building or an extensionAct 25/2025, § 42 ods. 1
Site handoverThe builder hands the project, the decision and the land to the contractorAct 25/2025, § 30 ods. 3 písm. b
Notice to the building officeThe builder announces the start and names the contractorAct 25/2025, § 30 ods. 3 písm. a

What changes from 1 January 2027?

Act 243/2026 changes three points from 1 January 2027. The notice of the start goes through a form designated for it (Art. I bod 89 on § 30 ods. 3 písm. a). Failing to notify the start of construction becomes an offence under § 79 ods. 1 písm. e (bod 185). In the 2026 text that offence covers only a change of builder. The minimum fine for building without a verified project rises to 300 euro (bod 199).

Frequently asked questions

What counts as the start of construction in Slovakia?
The start is the start of works directly tied to making the structure (act 25/2025, § 41). Fencing, site set-up, access, water and power supply, vegetation removal, topsoil stripping, waste removal and marking the building are preparatory works and do not count.
Do I have to notify the building office before I start?
Yes. Before the works start, the builder must notify the building office of the start and name the contractor (act 25/2025, § 30 ods. 3 písm. a). The 2026 text names no period and no form.
Is there a template for the notice of the start of construction?
The 2026 text of § 30 ods. 3 names no form. From 1 January 2027 the notice goes through a form designated for it (amendment 243/2026, Art. I bod 89). Use that form when it applies.
How long can I wait before I start building?
A decision on the building intent is valid for 2 years, or 3 years for linear and reserved structures (act 25/2025, § 61 ods. 1). The verification clause lapses if works have not started within 2 years of its issue, unless the office set a longer time (§ 65 ods. 6).
Do I wait 30 days after I notify a minor structure?
No. The 30 days are the office's time to verify the project (act 25/2025, § 63 ods. 6). If the office does not act in that time, the act presumes that it issued the clause (§ 63 ods. 7). You then have 3 years to start (§ 63 ods. 10).
Does fencing the plot count as the start of construction?
No. Fencing the building place and setting up the site are preparatory works, not the start of construction (act 25/2025, § 41). The site must carry a sign with basic data on the structure and the parties (§ 6 ods. 3 písm. b).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 6, § 10, § 25, § 28, § 30, § 37, § 39, § 41, § 43, § 60, § 61, § 62, § 63, § 65, § 73, § 79, § 84, Čl. IV
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 89, 185, 199