Site handover
A site handover is the step in which the builder gives the contractor the land and the documents to build on. The contract sets its form.
What is a site handover?
A site handover is the step in which the builder gives the contractor the land and the documents to build on. The Slovak name is odovzdanie a prevzatie staveniska. The act uses the words "prevzatie staveniska" (takeover of the site) for the day the construction diary starts (act 25/2025 Z. z., § 10 ods. 2).
The site (stavenisko) is the space that the building intent sets for the building, the site facilities and the building works. It includes the building plot and, to a set extent, other plots (§ 6 ods. 1). The decision on the building intent lists the plots that form the site, from cadastre data (§ 60 ods. 1 písm. c).
Does the law set a form for the handover?
No. The act sets no form, no content and no period for a record of the site handover. The Civil Code and the Commercial Code say nothing about a site handover. The parties choose the form in their contract for work (Civil Code 40/1964, § 631, and Commercial Code 513/1991, § 536).
The Commercial Code governs a contract for work between businesses (§ 261 ods. 1). Other parties may agree in writing to use it (§ 262 ods. 1 and 2). Without that, the Civil Code applies. See contract for work.
What must the builder hand over?
The act does name what the builder must give the contractor before the building works start. It names three things: the verified project, the final decision on the building intent and the land to set up the site (§ 30 ods. 3 písm. b). The builder must also tell the building office that the works start and name the contractor (§ 30 ods. 3 písm. a). See start of construction.
The surveyor's work adds a second handover. If one geodet prepares the building and another works during construction, the first hands over these items before the start of construction (decree 209/2025 Z. z., § 5 ods. 1):
- the geodetic base documents and the parameters of the reference system of the building
- the staking network
- the break points of the plot boundary and of the site facilities boundary, if the plot is not fenced
- the surface marks of the access roads
- the surface marks of the utilities and underground structures
- the break points of the boundaries of temporary and permanent land take
- the marks of the building position
- the protocol on the staking out of the spatial position
Both geodets sign a protocol of this handover (§ 5 ods. 2). See staking out a building.
Who does what after the handover?
| Party | Duty | Source |
|---|---|---|
| Builder | Hands over the project, the decision and the land. Protects the geodetic points and the staking network points on the site | Act 25/2025, § 30 ods. 3 písm. b, ods. 4 písm. f |
| Contractor | Ensures an authorised site manager, water and electricity if the works need them, the equipment for the works and for the workers, and a chief geodet | Act 25/2025, § 32 ods. 2 písm. a, c, d |
| Site manager | Manages the site and runs it, keeps the diary, and keeps the site fenced, signed and safe | Act 25/2025, § 37 ods. 1, § 38 ods. 1, § 39 ods. 1 |
The site must carry a sign with basic data on the structure and the parties (§ 6 ods. 3 písm. b). It must have a drive-in from a public road or a special-purpose road, and protection against entry by strangers (§ 6 ods. 3 písm. a, c).
What belongs in a handover record?
The law gives no list, so the parties decide. A record that follows the duties in the act can cover:
- the plots of the site, as in the decision on the building intent
- the documents handed over, with the verified project and the final decision
- the geodetic points, the staking marks and the protocols
- the position of utilities and underground structures
- access, water and electricity
- fencing and the site sign
- the names of the site manager and the chief geodet
- the date of the takeover, because the construction diary starts with it (§ 10 ods. 2)
Photographs and meter readings of the condition on that day are a practical addition. The act does not require them.
What if the site is not ready or hides an obstacle?
Between businesses, a client is in delay if it does not give the co-operation that the contractor needs to perform. The contractor may then claim damages (Commercial Code, § 370 and § 371 ods. 2). Under the Civil Code the contractor may set a reasonable time for the client's co-operation. After the time lapses, the contractor may withdraw if it warned the client (§ 638 ods. 1). The contractor gets reasonable compensation for a delay that comes from the client's side (§ 641 ods. 2).
If the contractor finds a hidden obstacle at the place of work, the Commercial Code applies. The obstacle must make the agreed work impossible. The contractor must tell the client without undue delay and propose a change of the work. Until the parties agree, the contractor may interrupt the work. If they do not agree in a reasonable time, either may withdraw (§ 552 ods. 1).
The contractor must look for such obstacles before the work starts. If it did so with professional care, neither party has a claim for damages. The contractor then gets the price for the part of the work done until it could find the obstacle (§ 552 ods. 2).
Who bears the risk after the handover?
Take a contractor who builds on the client's land. The client then bears the risk of damage to the work in progress and owns it (Commercial Code, § 542 ods. 1). The contract may say otherwise. Under the Civil Code, the contractor answers for damage to a building made to order. This lasts until the client takes the finished building (§ 647). The texts do not tie the risk to the site handover. The contract should say who runs the site from which date.
Liability for accidents on the site follows other laws that this page does not cover.
How is a site handover different from other handovers?
| Handover | What it is | Source |
|---|---|---|
| Site handover | Builder to contractor, before the works: project, decision and land for the site | Act 25/2025, § 30 ods. 3 písm. b |
| Handover of geodetic documents | Geodet to geodet, before the start of construction, with a signed protocol | Decree 209/2025, § 5 ods. 1, 2 |
| Handover of the finished building | Contractor to builder. The contractor records it in the information system, and a protocol goes with the proposal for the final inspection | Act 25/2025, § 32 ods. 2 písm. l, § 66 ods. 2 písm. e |
| Handover of the finished work under the contract | The parties write and sign a record if either side asks | Commercial Code, § 554 ods. 6 |
See building handover for the finished building. From 1 January 2027 its handover record includes a declaration of the contractor. The contractor declares that the building matches the verified project (act 243/2026, Art. I bod 151).
Frequently asked questions
- What does site handover mean in construction?
- A site handover is the step in which the builder gives the contractor the land and the documents to build on. The act names three things (§ 30 ods. 3 písm. b). They are the verified project, the final decision on the building intent and the land for the site.
- Does the law require a site handover record?
- No law sets a form for it. The building act sets no form, content or period for a site handover record. The Civil Code and the Commercial Code say nothing about it. The contract between builder and contractor decides.
- What should a site handover protocol contain?
- The law gives no list. A record can name the plots of the site and the documents handed over. It can also name the geodetic points, access, water and electricity, fencing, the site sign, the site manager and the date of takeover.
- Is there a template for the site handover protocol?
- The building act and the two codes include no template. Use a template only as a base and write the items of your project into it. The date matters because the construction diary starts from the takeover of the site (act 25/2025, § 10 ods. 2).
- Is a site handover the same as the handover of the finished building?
- No. The site handover comes before the works and goes from the builder to the contractor. The handover of the finished building goes from the contractor to the builder and comes with the final inspection (act 25/2025, § 32 ods. 2 písm. l, § 66 ods. 2 písm. e).
- What if the contractor finds an obstacle on the site after the handover?
- Between businesses the contractor must tell the client without undue delay and propose a change of the work. It may interrupt the work until the parties agree. If they do not agree in a reasonable time, either may withdraw (Commercial Code, § 552 ods. 1).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 6, § 10, § 30, § 32, § 37, § 38, § 39, § 60, § 66
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 151
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky, ktorou sa ustanovujú podrobnosti o postavení a činnosti geodeta pri príprave, zhotovovaní stavby a užívaní stavby a o výkone geodetických a kartografických činností vo výstavbe (č. 209/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 5
- Zákon č. 513/1991 Zb. Obchodný zákonník · Federálne zhromaždenie Československej federatívnej republiky, via Slov-Lex · § 261, § 262, § 370, § 371, § 536, § 542, § 552, § 554
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slovenská národná rada, via Slov-Lex · § 631, § 638, § 641, § 647