Staking out a building
A building stake-out is a geodetic job that marks the position and height of a new building on the ground before building works start.
What is a building stake-out?
A building stake-out is a geodetic job that marks the position and height of a new building on the ground before building works start. The act and the decree call it vytýčenie stavby (act 25/2025 Z. z., § 42, and decree 209/2025 Z. z., § 4).
The decree splits the job in two. Staking out the spatial position (vytýčenie priestorovej polohy stavby) marks the main lines or axes, the main points and the main height points. Detailed staking (podrobné vytýčenie stavby) follows detailed drawings. The surveyor may stake out the building part by part (decree 209/2025, § 4 ods. 1, 4, 5, 9).
Is a stake-out required?
Yes, for a new building, an extension and terrain works. Act 25/2025 allows them only after a surveyor (geodet) stakes them out on the ground (§ 42 ods. 1). The 2026 text has one exception. It is a minor structure that needs only a notification (ohlásenie).
The staked position must match the final decision on the building intent and the staking drawing (§ 42 ods. 2). A builder who carries out the works by self-help (svojpomocou) has no contractor. That builder must ensure the stake-out and the match with the verified project (§ 30 ods. 6 písm. c).
Not ensuring the stake-out and the match of a new building with the project is an offence (§ 79 ods. 1 písm. c). The fine is 30 to 300 euro (§ 79 ods. 6 písm. a). These rules apply to 31 December 2026.
What changes from 1 January 2027?
Act 243/2026 amends § 42 ods. 1 from 1 January 2027. It deletes the sentence that exempts minor structures needing notification. It also limits the rule on terrain works to works that need a decision on the building intent (Art. I bod 104). Read the new text before you rely on the old exception.
Who may stake out a building, and who orders it?
A surveyor (geodet) who meets the requirements of the geodesy law stakes out the building (act 25/2025, § 40 ods. 1). Act 215/1995 requires a complete university or secondary education in geodesy and cartography, or a decision that recognises a foreign qualification (§ 5 ods. 1). Building a staking network and staking out structures are "selected" geodetic activities (§ 6 písm. g, h).
An authorised geodet must authorise the staking drawings, the staking protocol and the record of the quality check (decree 209/2025, § 12 ods. 1 písm. c, h, i). On paper the geodet adds an authorisation clause. In electronic form the geodet adds a qualified electronic signature (§ 12 ods. 2).
| Who | Duty | Source |
|---|---|---|
| Builder | Ensures geodetic work for the whole time of the works and protects the geodetic points and staking network points on the site | Act 25/2025, § 30 ods. 4 písm. e, f |
| Contractor | Ensures geodetic work on the building, names a chief geodet and has new underground infrastructure measured before it is covered | Act 25/2025, § 32 ods. 2 písm. a, o |
| Geodet | Builds the staking network, stakes out the position and the details, and checks the position during the works | Act 25/2025, § 40 ods. 3 písm. d, e, f |
| Site manager | Answers for the match of the spatial position with the verified project | Act 25/2025, § 37 ods. 2 |
The act does not say who orders and pays for the geodet. The contract between builder and contractor must settle it. On a reserved structure or a large structure, a chief geodet coordinates the other geodets (§ 40 ods. 2).
What does the geodet need before staking out?
The geodet needs two staking drawings (decree 209/2025, § 3 ods. 1). The drawing for the spatial position is a site plan and part of the building documentation. It shows the building and its characteristic points, the boundaries of the plot and of the neighbouring plots, and the neighbouring buildings. It also shows the utilities and underground structures on the plot and the staking network points. A list of coordinates of the foundation points and accuracy criteria complete it (§ 3 ods. 3).
The staking network is a set of stable geodetic points on or near the site. Their coordinates are in the reference system of the building (§ 2 ods. 1). On a reserved structure the network points define that system. On other structures the geodet may define it by numbers and geometry against nearby objects. Examples are the street line, the road axis or the edge of a pavement (§ 4 ods. 3).
How accurate must the stake-out be?
The decree sets no fixed figure. The project sets a staking deviation (vytyčovacia odchýlka) for each point. Or the geodet calculates it from the construction deviation in the project or in a technical specification. A staked point is right when its position differs from the design by less than that deviation (decree 209/2025, § 4 ods. 7, 13).
Two checks apply. The geodet who staked the building stakes it again, independently of the first staking, and records the differences. If that is not possible, the geodet checks the distances between neighbouring points or the geometric conditions (§ 4 ods. 6 and 8). A quality check follows. It uses an independent procedure, and the geodet who staked the building may not do it (§ 4 ods. 12 and 14).
Which documents does the stake-out produce?
The geodet writes a staking protocol (protokol o vytýčení) and records the stake-out in the construction diary (act 25/2025, § 42 ods. 3). There is one protocol for the spatial position and one for detailed staking. Each has five parts (decree 209/2025, § 4 ods. 11):
- a technical report
- the name of the person who takes over the points
- a list of coordinates
- a record of the correctness check
- a drawing of the staked points
The diary entry gives the subject, the geodet's name, the dates and the protocol reference. It also gives the number and marking of the points. The persons who hand over and take over the documentation and the staked points sign it (§ 4 ods. 10).
Three documents go with the proposal for the final inspection (kolaudácia), depending on the type of structure. They are the documentation of the stake-out, a control protocol of the position and a geometric plan (act 25/2025, § 66 ods. 2 písm. d).
How does a stake-out differ from other geodetic jobs?
| Job | What it does | Source |
|---|---|---|
| Pre-design survey | Prepares the base documents for the design. See geodetic survey | Decree 209/2025, § 1 ods. 2 |
| Staking out the site boundary | Marks the boundary of the site and the access roads, as part of the base documents | Decree 209/2025, § 1 ods. 2 písm. d |
| Staking out a building | Marks the position and the height of the new building | Act 25/2025, § 42. Decree 209/2025, § 4 |
| Staking out a plot boundary | Marks the break points of a plot boundary in the field. The marks are permanent if the owners and other entitled persons agree, and temporary if not. It is a cadastral job | Decree 461/2009, § 51 and § 53 |
| As-built survey | Measures each element of the building while it is accessible, before it is covered. See as-built survey | Decree 209/2025, § 7 ods. 1 |
What does the geodet do after the stake-out?
During construction the geodet does the detailed staking that is still open. The geodet measures the building, the utilities and the underground structures before the contractor covers them. The geodet also makes check measurements and, if the project requires it, measures displacements and deformations (decree 209/2025, § 5 ods. 3).
Another geodet may take over during construction. The first geodet then hands over four items before the start of construction:
- the base documents
- the staking network
- the marks of the site and of the building position
- the staking protocol
Both geodets sign a protocol (§ 5 ods. 1, 2). See site handover.
Frequently asked questions
- What is the difference between staking out a building and staking out a plot boundary?
- Staking out a building marks where the new building will stand (act 25/2025, § 42). Staking out a plot boundary marks the break points of a plot boundary in the field (decree 461/2009, § 51). The first is a construction job. The second is a cadastral job.
- Do I need a stake-out for a garden shed or another minor structure?
- Not in the 2026 text. A minor structure that needs only a notification is exempt from the stake-out (act 25/2025, § 42 ods. 1). From 1 January 2027 amendment 243/2026 deletes that exception, so check the new wording.
- Who may stake out a house in Slovakia?
- A geodet who meets the requirements of the geodesy law does it (act 25/2025, § 40 ods. 1). An authorised geodet must authorise the staking drawings and the staking protocol (decree 209/2025, § 12 ods. 1).
- How accurate must the stake-out be?
- The decree gives no set number. The project, or a calculation from the construction deviation in the project, sets the staking deviation for each point. A point is right when its error is smaller than that deviation (decree 209/2025, § 4 ods. 7).
- Which document do I get after the stake-out?
- You get a staking protocol with a list of coordinates and an entry in the construction diary (decree 209/2025, § 4 ods. 10, 11). Keep them for the final inspection (act 25/2025, § 66 ods. 2 písm. d).
- When does the stake-out happen?
- It happens before building works and terrain works start (act 25/2025, § 42 ods. 1). The detailed drawings come from the verified project (§ 42 ods. 3). Fencing and site set-up may come earlier, because they are not the start of construction (§ 41).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 30, § 32, § 37, § 40, § 41, § 42, § 66, § 79
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 104
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky, ktorou sa ustanovujú podrobnosti o postavení a činnosti geodeta pri príprave, zhotovovaní stavby a užívaní stavby a o výkone geodetických a kartografických činností vo výstavbe (č. 209/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu SR, via Slov-Lex · § 1 to § 5, § 7, § 12
- Zákon Národnej rady Slovenskej republiky č. 215/1995 Z. z. o geodézii a kartografii · Národná rada Slovenskej republiky, via Slov-Lex · § 5, § 6
- Vyhláška Úradu geodézie, kartografie a katastra Slovenskej republiky, ktorou sa vykonáva zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) (č. 461/2009 Z. z.) · Úrad geodézie, kartografie a katastra SR, via Slov-Lex · § 51, § 53