Minor Structure Notification

A minor structure notification is a notice to the building authority that a builder must file before building a small structure.

What is a minor structure notification?

A minor structure notification (ohlásenie drobnej stavby) is a notice that a builder gives to the building authority before the work starts (Act 25/2025 Z. z., § 63 ods. 1). It covers a minor structure or an alteration that the act says must be notified. The authority answers by verifying the project and issuing a verifying clause (overovacia doložka). People also search for "oznámenie o drobnej stavbe" and "ohlásenie stavby". The act uses only the word ohlásenie. The text follows the consolidated version valid from 1 November 2025 to 31 December 2026. The last section lists the changes from 1 January 2027.

The notification replaces the building intent proceedings and the decision on building intent for these small works. What counts as a minor structure is explained on the minor structure page.

When is notification enough, and when is it not needed?

Notification is enough for the minor structures in § 2 ods. 4 písm. a) to c) (§ 18 ods. 3). These are above-ground structures up to 50 m² and 5 m, underground structures up to 25 m² and 3 m, and forestry structures up to 50 m² and 5 m. It is also enough for other minor structures and alterations when one of the conditions in § 18 ods. 3 písm. a) to i) applies. The list of conditions is on the minor structure page.

Section 18 ods. 4 adds works that need notification. Examples are new electronic communication lines and solar equipment from 50 kW to 100 kW including. Maintenance that could affect stability or fire safety also needs it. Maintenance of a cultural monument also needs notification.

Section 18 ods. 5 lists works that need neither a decision nor a notification. Examples are repair of a facade, repair or replacement of roof covering and gutters, and replacement of windows and doors. Others are replacement of internal partitions, plaster, floors and fitted kitchens, and renewable energy equipment up to 50 kW including. Minor structures and alterations that meet none of the conditions in § 18 ods. 3 are also free of both.

Which documents must I file with the notification?

The notification contains the builder's identification data and data on the place and kind of work (§ 63 ods. 2). It also contains cadastre data that allow the authority to verify ownership of the plot or structure. Two attachments are required. The first is the project of the structure for notification (projekt stavby na ohlásenie). The second is the binding statements of the affected authorities and affected legal persons whose interests the work touches.

The project is a text and drawing description of the architectural and technical solution of a structure that needs notification (§ 9 ods. 4). If you file on paper, the authority converts the file to electronic form without delay. It stores the file in the information system (§ 63 ods. 3). The act speaks of the information system of the Office for Spatial Planning and Construction. It does not name any portal. Ask your building office how it accepts filings.

A binding statement is issued by each affected authority within its own remit (§ 21 ods. 3 písm. d).

Who may prepare the project?

Drawing the project for notification is not a reserved activity (§ 34 ods. 4 písm. a). Two kinds of person can do it (§ 34 ods. 5). The first holds a university degree in architecture and urban planning, construction, mechanical engineering or electrical engineering. The second has full secondary vocational education in construction, mechanical engineering or electrical engineering and at least three years of practice in the activity. Persons who hold an authorisation under § 34 ods. 1 also qualify.

How long does the authority have, and what if it does not answer?

The authority must decide within 30 days of delivery of the notification, by verifying the project and issuing the verifying clause (§ 63 ods. 6). If the notification is incomplete, the authority invites the builder to complete it. The 30 days do not run during that period (§ 63 ods. 4). If the builder does not complete it, the authority returns the filing (§ 63 ods. 4).

If the authority does not verify the project of a notified minor structure within 30 days, the act presumes that it issued the clause. The authority records this in the information system (§ 63 ods. 7). The 30 days apply to a complete notification only. The authority verifies the project only if the binding statements are positive. Otherwise it returns the notification with its attachments and states the reason (§ 63 ods. 6).

StepTime limitSource
Authority verifies the project or returns the notification30 days from delivery§ 63 ods. 6
Request for review of a returned notification10 working days from delivery of the return§ 63 ods. 8
Appeal body reviews the procedure30 days from delivery of the request§ 63 ods. 8
Start of the notified workWithin three years of verification§ 63 ods. 10

What can I do if the authority returns my notification?

You can ask the appeal body to review the authority's procedure. You must do so within 10 working days of delivery of the returned notification (§ 63 ods. 8). You attach the notification in the scope you gave to the authority. The appeal body reviews the procedure within 30 days. If it finds a mistake, it sends the notification back with instructions. If it finds none, it rejects the request.

The authority can also tell you that the project may be carried out only on the basis of a decision on building intent (§ 63 ods. 5). It does so when the structure could affect the rights of third parties or conditions must be set. Then you follow the longer route.

How long is the verified project valid?

The notified work can start within three years of the day the project was verified (§ 63 ods. 10). The verification does not replace other decisions, statements or consents that special laws require from affected authorities (§ 63 ods. 9).

Do I need a surveyor, a final inspection or a builder?

  • A surveyor is not required to stake out a minor structure that needs notification (§ 42 ods. 1).
  • A final inspection (kolaudácia) is not required for structures that are notified (§ 66 ods. 1). See occupancy approval for the structures that do need it.
  • An owner may build the notified structure with their own labour if they arrange expert supervision (§ 26 ods. 3). The supervisor needs one of two qualifications. The first is full secondary vocational education in construction, mechanical engineering or electrical engineering and at least three years of practice. The second is a university degree in architecture and urban planning, construction, mechanical engineering or electrical engineering. Supervision of such works is not a reserved activity (§ 34 ods. 4 písm. b).

What happens if I build without a verified project?

Building a minor structure or alteration that needs notification without a verified project, or against it, is an offence. The fine is from €30 to €3,000 (§ 79 ods. 2 písm. a and ods. 6 písm. b). The building inspectorate fines a sole trader or a legal person from €1,000 to €5,000 (§ 80 ods. 2 písm. a).

The act sets no late-notification route in § 18 or § 63. From 1 January 2027, § 18 ods. 2 requires a decision on building intent to approve some works afterwards. These are works done without a verified project between 1 April 2025 and 31 December 2026, such as a structure that serves the main building. The decision is possible only under the conditions of § 60 ods. 3 and 4 (Art. I point 58 of Act 243/2026). Notifications delivered to the authority before 1 April 2025 are handled under the old rules (§ 84 ods. 4 písm. a).

What changes on 1 January 2027?

Art. I of Act 243/2026 Z. z. amends the rules from 1 January 2027. The table follows the amending text and is not law before that date.

TopicChangePoint of Art. I
AttachmentsBinding opinions of affected legal persons are named next to the binding statements137
Third-party rightsThe authority states its reasons and may require both a decision on building intent and a verified project138
Verifying clauseIt carries the official stamp. The authority records a presumed clause without delay and adds the clause to the project in the information system139
Binding statementsTheir requirements bind the builder once the project is verified141
Which minor structures need notificationThe rule that always requires notification for the first three groups is deleted (see the minor structure page)59
Project qualificationThe qualification rule of § 34 ods. 5 does not apply to the project of a minor structure that is not a building94

Frequently asked questions

What is the ohlásenie of a drobná stavba?
It is the notice that a builder gives to the building authority before the work starts (Act 25/2025 Z. z., § 63 ods. 1). It applies to a minor structure that needs notification. The authority verifies the project and issues a verifying clause.
When is notification enough for a minor structure?
Notification is enough for three groups (§ 18 ods. 3). They are above-ground structures up to 50 m² and 5 m, underground ones up to 25 m² and 3 m, and forestry ones up to 50 m² and 5 m. Other minor structures need it only under the conditions of § 18 ods. 3.
Which documents do I attach to the notification?
Attach the project of the structure for notification and the binding statements of the affected authorities and legal persons (§ 63 ods. 2). The notification itself gives your identification data, cadastre data and the place and kind of work.
How long does the authority have to answer a notification?
The authority has 30 days from delivery (§ 63 ods. 6). If it does not verify the project in that time, the act presumes that it issued the verifying clause (§ 63 ods. 7).
Can I notify a minor structure after I built it?
The act sets no late-notification route in § 18 or § 63, and building without a verified project is an offence (§ 79 ods. 2). From 1 January 2027, a decision on building intent can approve some unauthorised works afterwards (§ 18 ods. 2). These are works done between 1 April 2025 and 31 December 2026.
Is a final inspection needed after a notified minor structure?
No. Section 66 ods. 1 says that kolaudácia is not required for structures that are notified.

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 2 ods. 1, 4 to 6, § 9 ods. 4, § 18 ods. 2 to 5, § 21 ods. 3, § 26 ods. 3, § 34 ods. 4 to 5, § 42 ods. 1, § 63, § 66 ods. 1, § 79 ods. 2 and 6, § 80 ods. 2, § 84 ods. 4
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · Čl. I bod 1 to 17, 59 to 62, 94, 137 to 141, Čl. XV