Building alteration notification

A building alteration notification is a filing that tells the building office about listed alteration work before it starts.

A building alteration notification is a filing that tells the building office about listed alteration work before it starts. The Slovak name is ohlásenie stavebných úprav. The legal basis is § 63 of the Building Act 25/2025 Z. z. The act uses the word notification (ohlásenie) for this filing, and it has no building permit for alterations. This page describes the act as consolidated from 1 November 2025 to 31 December 2026. A separate section lists what Act 243/2026 changes from 1 January 2027.

What counts as a building alteration?

A building alteration (stavebná úprava) is a building work that changes an existing structure without enlarging it. The act defines it in § 2 ods. 9. Its main groups are:

  • Work on the structure of an existing building that is not a change of a completed structure. Examples are renewal of the outer or roof envelope and interior alterations that keep the size of the building.
  • Changes to electrical, communication, gas, water supply and sewer lines, if the work serves the original purpose and the route does not change.
  • Terrain works and outside works, such as driveways and paved areas of up to 40 m².

Maintenance (údržba stavby) is a different thing. It keeps a structure in working order. It does not touch the load-bearing structure and does not change the use or outer appearance (§ 2 ods. 10). An extension, a raised storey and an insertion of new space inside the volume are a change of a completed structure under § 5 ods. 1. They are not alterations. They need the decision on the building intent (§ 18 ods. 2), explained on the page about building intent proceedings.

When does an alteration need a notification?

An alteration needs a notification only if § 18 ods. 3 or 4 lists it. The act reads as a list of triggers, and § 18 ods. 5 písm. k says that alterations outside the list need neither a decision nor a notification. For an alteration the triggers in ods. 3 are works that:

  • take place in a public space,
  • affect a cultural monument,
  • affect a building in a heritage area, in a protected area outside the built-up area, or in a protection zone of a protected area,
  • may endanger human health, harm the environment significantly, or endanger fire safety, mechanical resistance, stability or safety in use,
  • put a structure or terrain works on the builder's plot closer than 2 m to the plot boundary (§ 18 ods. 3 písm. b),
  • are done on a riverside plot, in a flood area with retention potential, or in a protection zone of a drinking-water, healing or mineral source.

Section 18 ods. 4 adds four more cases. They are new lines of electronic communication networks and solar installations from 50 kW to 100 kW. They also include maintenance that could affect stability, fire safety, the look of the building in public space or the environment. The fourth is maintenance of a cultural monument. Section 18 ods. 5 lists works that need neither a decision nor a notification. The table shows examples. Maintenance of a cultural monument is itself a trigger (§ 18 ods. 4 písm. d).

WorkRouteSource
Repair of a facade, repair or replacement of roofing, replacement of gutters and of windows and doorsNeither decision nor notification§ 18 ods. 5 písm. a bod 1
Repair or replacement of interior partitions, plaster, wall tiles, floors, doors and stair railingsNeither decision nor notification§ 18 ods. 5 písm. a bod 2
Painting, wallpapering and plasteringNeither decision nor notification§ 18 ods. 5 písm. a bod 7
Replacement of a fitted kitchen, sink, bath, shower or toiletNeither decision nor notification§ 18 ods. 5 písm. b
Solar installation up to 50 kWNeither decision nor notification§ 18 ods. 5 písm. i
Solar installation from 50 kW to 100 kWNotification§ 18 ods. 4 písm. b
Work on a cultural monumentNotification§ 18 ods. 3 písm. f
Work that may endanger stability or fire safetyNotification§ 18 ods. 3 písm. h

Does a load-bearing wall removal need a notification?

The act has no rule that names load-bearing walls. It lists work that may endanger mechanical resistance and stability (§ 18 ods. 3 písm. h) and maintenance that could affect stability (§ 18 ods. 4 písm. c). The designer and the building office judge whether a given load-bearing wall removal falls under these letters. The act gives no list of such walls. The office may also tell the builder that the work needs a decision on the building intent instead (§ 63 ods. 5).

The act does not use the term static assessment (statický posudok). It makes the designer of the static part of the documentation responsible for the load-bearing structure. This includes the static assessment of its resistance and stability (§ 35 ods. 8). A static assessment in practice is this part of the design. A non-load-bearing partition (nenosná priečka) carries only its own weight. Repair and replacement of interior partitions need neither a decision nor a notification, unless a trigger above applies.

What must a notification contain?

The notification contains the identification of the builder, cadastre data that prove ownership, and the place and kind of the work. The attachments are the project for notification (projekt stavby na ohlásenie) and the opinions of affected bodies. These are the binding opinions of affected authorities and the binding statements of affected legal persons that the work concerns (§ 63 ods. 2). A binding opinion comes from an authority such as a heritage office. A binding statement comes from a legal person such as a network operator.

The project for notification is a text and drawing description of the architectural and construction solution (§ 9 ods. 4). Drawing it is not a reserved activity. A person with a degree in architecture, construction, mechanical or electrical engineering may also draw it. So may a person with secondary vocational education in these fields and at least three years of practice (§ 34 ods. 4 and 5). A paper notification is allowed. The office scans it into the information system (§ 63 ods. 3).

How long does the office have to decide?

The office has 30 days from delivery of the notification. It verifies the project and issues a verification clause (overovacia doložka). It verifies only if the binding opinions are favourable. Otherwise it returns the notification with the reasons (§ 63 ods. 6). If the notification is incomplete, the office asks the builder to complete it by a set date. The 30 days do not run during that time. If the builder does not complete it, the office returns the filing (§ 63 ods. 4).

If the office does not verify the project within 30 days, the act presumes that it issued the clause. The office records this in the information system (§ 63 ods. 7). The builder may start the notified work within three years from the day of verification (§ 63 ods. 10). Verification does not replace the decisions, opinions and consents that special laws require (§ 63 ods. 9).

The office may also tell the builder that the work can be done only on the basis of a decision on the building intent. It does this if the work could affect the rights of third parties or if conditions for the work must be set (§ 63 ods. 5). The builder can react to a returned notification with a petition (podnet) to the appeal body. The petition is due within 10 working days from delivery of the returned notification. The appeal body reviews the procedure within 30 days (§ 63 ods. 8).

StepPeriodSource
Office verifies the project and issues the clause30 days from delivery§ 63 ods. 6
Builder files a petition against a returned notification10 working days from delivery§ 63 ods. 8
Appeal body reviews the petition30 days from delivery§ 63 ods. 8
Builder starts the notified workWithin three years from verification§ 63 ods. 10

What does a notification cost?

The administrative fee depends on the building. The fee schedule of Act 145/1995, in the version from 1 November 2026, sets the price of verification after notification. It is 150 euro on a residential building and 300 euro on a non-residential building or an engineering structure. Terrain works and outside works cost 50 euro (položka 59 písm. b bod 6). If the office decides after notification that the work needs proceedings on the building intent, that decision costs 100 euro (položka 59 písm. a bod 15). Read the current schedule before you file, because the schedule changes.

Is a final inspection needed after notified alterations?

No, as a rule. Kolaudácia is not required for notified structures and alterations. The exception is an alteration that is connected with a change of use (§ 66 ods. 1). In that case the office deals with the change of use after the alteration is finished (§ 68 ods. 3).

What happens if I start the works without a verified project?

Making alterations or minor structures that need notification without a verified project, or against it, is an offence. The building inspectorate may impose a fine from 30 euro to 3,000 euro (§ 79 ods. 2 písm. a and ods. 6 písm. b). For an entrepreneur or a legal person the fine is from 1,000 euro to 5,000 euro (§ 80 ods. 2 písm. a). The page on minor structure notification describes the same filing for new minor structures.

What changes on 1 January 2027?

Act 243/2026 amends Act 25/2025 from 1 January 2027. These changes concern alterations:

  • The words that tie notification to minor structures under § 2 ods. 4 písm. a to c no longer appear in § 18 ods. 3 (Art. I point 59). Notification is then required only where a listed trigger applies.
  • The trigger for heritage work is reworded. For a building in a heritage area that is not a cultural monument, it applies only if the work changes the outer appearance (point 61).
  • Section 18 ods. 4 is rewritten. It lists, among others, heat and electricity generation from renewable sources of 50 kW to 300 kW if it is an alteration. It also lists maintenance of a monument, or of a building in a heritage area that changes its outer look (point 62).
  • The office must state its reasons when it requires a decision on the building intent and project verification (§ 63 ods. 5, point 138). Conditions from binding opinions and statements become binding on the builder when the project is verified (§ 63 ods. 9, point 141).
  • Some works done from 1 April 2025 to 31 December 2026 without a verified project, or against it, need a decision on the building intent. Alterations are among them. The office may legalise them late, only under § 60 ods. 3 and 4 (§ 18 ods. 2, point 58).
  • The definition of an alteration moves to § 2 ods. 12 and the limit for paved areas rises from 40 m² to 50 m² (points 21, 24).

Frequently asked questions

Do I need a permit to renovate a house in Slovakia?
Often you need neither a permit nor a notification. Repairs, replacement of windows, interior partitions, floors and fitted kitchens need neither a decision nor a notification (§ 18 ods. 5). A notification is needed only if a trigger in § 18 ods. 3 or 4 applies, such as work on a cultural monument.
What is the difference between an alteration and a change of a completed structure?
An alteration changes an existing structure without enlarging it (§ 2 ods. 9). A change of a completed structure is an extension, a raised storey or an insertion of new space (§ 5 ods. 1). The change of a completed structure needs the decision on the building intent.
How long does the office have to verify a notified alteration?
The office has 30 days from delivery of the notification (§ 63 ods. 6). The time stops while the builder completes a notification that lacks required parts (§ 63 ods. 4).
What if the office does not answer within 30 days?
The act presumes that the office issued the verification clause, and the office records this in the information system (§ 63 ods. 7). The builder may start the work within three years from the day of verification (§ 63 ods. 10).
Is a notification enough to remove a load-bearing wall?
The act does not name load-bearing walls. Work that may endanger stability is a notification trigger (§ 18 ods. 3 písm. h), but the designer and the office judge each case. The office may require a decision on the building intent instead (§ 63 ods. 5).
What happens if I start the works without a verified project?
It is an offence. The building inspectorate may impose a fine from 30 euro to 3,000 euro (§ 79 ods. 2 and 6). For an entrepreneur or a legal person the fine is from 1,000 euro to 5,000 euro (§ 80 ods. 2).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 2 ods. 9, 10, § 5 ods. 1, § 9 ods. 4, § 18 ods. 2 to 5, § 34 ods. 4 and 5, § 35 ods. 8, § 63, § 66 ods. 1, § 68 ods. 3, § 79 ods. 2 and 6, § 80 ods. 2
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I points 21, 24, 58, 59, 61, 62, 138, 141
  3. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · sadzobník položka 59 písm. a bod 15, písm. b bod 6