Building Permit 2026: Process and Deadlines

8 min read
Freshly poured strip foundations with reinforcement starter bars on an otherwise empty building plot

Does the building permit still exist?

No. The building act, Act 25/2025 Z. z. (building act), has no building permit (stavebné povolenie). It has applied since 1 April 2025. You may build only to a project that the office verified. It must be verified in the proceedings on the building intent, or on the basis of a notification (§ 25). The old names now map to new terms (§ 84 ods. 11).

Old nameTerm in Act 25/2025Provision
Zoning proceedings (územné konanie)Proceedings on the building intent§ 84 ods. 11 písm. a)
Building proceedings (stavebné konanie)Project verificationpísm. b)
Final inspection proceedings (kolaudačné konanie)Kolaudáciapísm. c)

So the proceedings did not merge into one step. The office first decides on the building intent and then verifies the project. The act sets a deadline for each step. It sets no total time from first idea to kolaudácia, and this article does not invent one. For small works and alterations, read Notification or Building Permit? What Applies Now.

What are the steps and deadlines from building intent to kolaudácia?

StepPeriodProvision
Binding opinion of an affected authority30 days, or 60 days for a complex structure, from delivery of the request§ 21 ods. 9
Binding opinion of the planning authority30 days for simple and notified structures, 60 days for others, 90 days for reserved structures, from delivery of the complete request200/2022 § 24a ods. 5
Binding statement of an affected legal person30 days, or at most 60 days for a complex structure, from delivery of the request§ 22 ods. 5
Office calls the applicant to complete the application15 days from delivery of the application§ 50 ods. 3
Notice of the start of proceedings7 days from the day the application is complete§ 51 ods. 1
Decision on the building intent, no hearing or site visit30 days from the day the application is complete§ 58 ods. 1
Decision on the building intent, with a hearing or site visit60 days from the day the application is complete§ 58 ods. 1
Decision on a reserved or linear structure, a case with many parties or a case with an expert opinion90 days, the paragraph sets no start day§ 58 ods. 2
Compliance declaration30 days, or 60 days for a complex structure, from delivery of the request§ 24 ods. 2
Project verification30 days, the paragraph sets no start day§ 65 ods. 2
Notice of the date of the final inspection7 working days from delivery of the complete proposal§ 66 ods. 3
Final inspection and occupancy certificateinspection within 30 days of the notice, certificate within 15 days of the inspection§ 66 ods. 3 and 7

The periods in § 58 ods. 1 apply unless the act or a special regulation says otherwise. The total time also depends on preparing the project and the opinions, and that preparation is not part of these periods.

How long does the decision on the building intent take?

The building office decides on the building intent within 30, 60 or 90 days (§ 58):

  • 30 days if it can decide from the application alone, without a hearing or site visit (§ 58 ods. 1),
  • 60 days in all other cases (§ 58 ods. 1),
  • 90 days for a reserved structure, a linear structure, a case with many parties, or a case that needs an expert opinion (§ 58 ods. 2).

The period depends on the need for a hearing or site visit, not on the size of the house. The office orders a hearing if the builder and designer did not accept conditions from statements that conflict (§ 53 ods. 1). The period does not include the time to deliver the notice of start or the time until the hearing (§ 58 ods. 3). In the 90-day group it does not run on days when the office has no expert opinion or state expert review (§ 58 ods. 2).

What if the office or an authority misses its deadline?

For the decision on the building intent, the act has no deemed approval. Section 58 does not say that the decision counts as issued after the period ends. The act presumes consent only for some other steps:

  • if an affected authority does not issue a binding opinion in time, the act presumes that it has no comments or requirements. This concerns the building intent. The designer records this in the report on consultation (§ 21 ods. 9),
  • the same applies if an affected legal person does not issue a binding statement (§ 22 ods. 5),
  • a planning authority that does not issue its opinion in time is inactive (200/2022 § 24a ods. 13). The act then presumes that it has no comments and has issued a binding opinion of compliance with the spatial plan (200/2022 § 35 ods. 1 písm. a),
  • if an authority does not issue a compliance declaration in time, the act presumes that it issued a consenting one (§ 24 ods. 3).

This article does not describe what a builder can do against a late office.

What must I file and who prepares it?

You file the application with the building office electronically, on the prescribed form. The attachments are the project documentation made by an authorised person and the report on consultation of the building intent (§ 50 ods. 1 and 2). The builder or the designer writes the report and evaluates in it all opinions and statements received (§ 23 ods. 1). If the application lacks the prescribed items, the office calls you within 15 days to complete it. If you do not complete it in the set period, the office stops the proceedings (§ 50 ods. 3, § 56 ods. 1 písm. e).

A designer must prepare the building intent, or the office rejects the application (§ 57 ods. 2 písm. g, § 59 ods. 1 písm. b). You ask for the opinions and statements before you file. If you asked fewer bodies than you should have, you must ask later for the missing opinion (§ 21 ods. 10). A separate page describes the content of the building intent.

Can a neighbour or a dispute delay the proceedings?

Yes, in several ways. A party to the proceedings can appeal the decision. The appeal period is 15 days from notice of the decision, and a timely appeal has suspensive effect (Act 71/1967 Zb. § 54 ods. 2, § 55 ods. 1). Act 25/2025 does not exclude these rules for the decision on the building intent (§ 82 ods. 1). Other situations also delay the proceedings:

  • if the office orders no hearing, the period for comments and objections is at least 7 working days. It runs from delivery of the notice of start (§ 51 ods. 2),
  • if binding opinions of authorities conflict and the authorities do not agree at the hearing, the office interrupts the proceedings. The superior bodies have 30 days, and the Office for Spatial Planning and Construction has 30 more (§ 54 ods. 2),
  • in a dispute over ownership or other rights to the plot, the office interrupts the proceedings. It sets at most 60 days to file a court claim (§ 55 ods. 2).

How long is the decision valid and can I extend it?

The decision on the building intent is valid for two years from the day it becomes final. The period is three years for linear and reserved structures and one year for an information structure and an assembled product. The office may set a longer period. The decision does not lapse if you applied for project verification in that period (§ 61 ods. 1). The office extends validity by at most two years if you apply before it expires. With extensions, validity can last at most seven years in total (§ 62 ods. 3). The extension decision needs a new binding opinion of the planning authority and a new binding statement of the legal person. This does not apply if the data for the area in the information system has been updated (§ 62 ods. 4).

What comes after the decision?

The builder asks for compliance declarations from the authorities that reserved the review of the project in their opinions (§ 24 ods. 2). Then the builder applies for project verification with the project and the declarations. The office verifies the project within 30 days. If the declarations are not consenting or the project does not match the decision, the office returns the application with its reason (§ 65 ods. 2 and 3). Within 10 working days you can ask the appeal body to review the return, and it has 30 days (§ 65 ods. 4). The office may decide on the intent and verify the project in one step if the builder files consenting compliance declarations (§ 57 ods. 3). The verification clause lapses if work does not start within two years of its issue (§ 65 ods. 6).

After construction comes kolaudácia. The office gives notice of the inspection date within 7 working days. The inspection takes place within 30 days of the notice. The office issues the occupancy certificate within 15 days of the inspection (§ 66 ods. 3 and 7). The article Final Inspection Step by Step describes the steps. The whole course of a build is in How a House Is Built in Slovakia.

When may I start building, and what is not yet the start of construction?

A new building or an extension may be built only after a surveyor has set it out, except a minor structure needing only a notification. The surveyor issues a setting-out protocol (§ 42 ods. 1 and 3). Preparatory work does not count as the start of construction. Examples are fencing the site, setting up the site, securing access and the water and power supply, or clearing vegetation (§ 41).

What must I attach to the application for kolaudácia?

Kolaudácia starts on the application of the builder, and the attachments depend on the type of structure (§ 66 ods. 2). They include the construction diary, the final statement of the site manager and the as-built documentation. They also include the survey documentation, the geometric plan for updating the cadastre and the building energy certificate, if the building is subject to certification.

How much are the state fees for a family house?

The fee schedule of Act 145/1995 Z. z. (version valid on 1 November 2026, položka 59) sets these fees for a building with one or two flats:

  • 300 euro for the decision on the building intent (písm. a bod 1),
  • 30% of that rate, so 90 euro, for project verification assessed together with the intent, or 50%, so 150 euro, for separate verification (písm. b bod 1 and 2),
  • 30% of the rate, so 90 euro, for the occupancy certificate (písm. e).

This page does not cover designer fees or fees of third parties. Read the current fee schedule before you pay.

What if I started under the old act?

A filing that reached the building office by 31 March 2025 is handled under the previous rules. So are proceedings started by that day (§ 84 ods. 4 písm. a and b). The same applies to later applications for a structure that already has a zoning decision or a building permit (§ 84 ods. 5 and 6). A period in a decision that started to run keeps running (§ 84 ods. 3). Legal relations created under the previous rules stay in place (§ 84 ods. 1). This page does not describe the periods of the old Act 50/1976 Zb.

What changes on 1 January 2027?

Act 243/2026 Z. z. amends the building act from 1 January 2027 and is not current law before that day. It rewrites § 58 ods. 3. The time to deliver the notice of start and the time until the hearing, if there is one, will not count towards the decision period. If there is no hearing, the time until the end of the period for comments and objections will not count (Art. I point 124). The amendment does not change the periods of 30, 60 and 90 days in § 58 ods. 1 and 2. From 1 January 2027 the final statement of the site manager is no longer an attachment to the application for kolaudácia (Art. I point 150).

Timber profile boards at the corner of a plot, two taut string lines crossing above bare earth with a plumb bob hanging from the intersection
Profile boards and string lines mark the position of the house on the plot before work starts.

Frequently asked questions

How long does a building permit take in 2026?
The act has no building permit. The building office decides on the building intent within 30, 60 or 90 days (§ 58). It then verifies the project within 30 days (§ 65 ods. 2). Preparing the project and the opinions comes on top of that. The act sets no total time.
What documents do I need for the application for a decision on the building intent?
You file the application electronically on the prescribed form. The attachments are the project documentation by an authorised person and the report on consultation of the building intent. The report includes the opinions of affected authorities and the statements of affected legal persons (§ 50 ods. 1 and 2, § 23 ods. 1).
If the office does not decide in time, is my application approved?
No. For the decision on the building intent, the act has no deemed approval (§ 58). Presumed consent applies only to opinions and statements, compliance declarations and notification (§ 21 ods. 9, § 22 ods. 5, § 24 ods. 3, § 63 ods. 7).
Can a neighbour appeal, and does it stop me?
A party to the proceedings can appeal within 15 days of notice of the decision, and a timely appeal has suspensive effect (Act 71/1967 Zb. § 54 ods. 2, § 55 ods. 1). So the decision does not take effect until the appeal is decided.
Does the old 1976 building act still apply to my project?
Only if the filing or the proceedings started at the building office by 31 March 2025. It also applies if you already hold a zoning decision or a building permit under the previous rules (§ 84 ods. 4 to 6). New projects follow Act 25/2025.
How long is the decision on the building intent valid?
Two years from the day it becomes final. It is three years for linear and reserved structures and one year for an information structure and an assembled product. It does not lapse if you applied for project verification in that period (§ 61 ods. 1). Extensions add up to seven years in total (§ 62 ods. 3).
Can I start building right after the decision on the building intent?
No. A structure may be built only to a verified project (§ 25), and a new building only after a surveyor has set it out. A minor structure needing only a notification is the exception (§ 42 ods. 1). Preparatory work such as fencing and setting up the site is not the start of construction (§ 41).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 21 to 25, § 41, § 42, § 50 to 59, § 61, § 62, § 65, § 66, § 82 ods. 1, § 84
  2. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 124, 150
  3. Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, via Slov-Lex · § 24a ods. 5, 13, § 35 ods. 1
  4. Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59 písm. a bod 1, písm. b bod 1 a 2, písm. e
  5. Zákon č. 71/1967 Zb. o správnom konaní (správny poriadok) · Národná rada Slovenskej republiky, via Slov-Lex · § 54 ods. 2, § 55 ods. 1

Topic

  • Building process