Construction Act (2022)
The Construction Act (zákon o výstavbe, 201/2022 Z. z.) is a repealed Slovak act of 2022 on building procedures. The current act is 25/2025 Z. z.
What is the Construction Act 201/2022?
The Construction Act (zákon o výstavbe, 201/2022 Z. z.) is a Slovak act of 2022 on building procedures that the Building Act repealed before consolidation. Parliament passed it on 27 April 2022 and it was promulgated on 7 June 2022. The current act is the Building Act, Act 25/2025 Z. z. Slov-Lex shows only the promulgated text of 201/2022 and no consolidated version. Do not use it for any current rule.
Its first section lists three subjects (§ 1):
- the procedure for preparing, building, changing, using and removing buildings
- the rights and duties of the people who carry out activities in construction
- the powers of the building authorities
Was the Construction Act ever in force?
Slov-Lex shows no consolidated version of the act. The sources show only these dates. The act's own start date was 1 April 2024 (§ 66). Act 46/2024 moved it to 1 April 2025. The Building Act repealed it, and Article I of the Building Act applies from 1 April 2025.
| Date | Event | Source |
|---|---|---|
| 27 April 2022 | Parliament passes 201/2022, which sets its start on 1 April 2024. Promulgation follows on 7 June 2022 | 201/2022, header and § 66 |
| 31 March 2024 | Act 46/2024 takes effect and moves the start of 201/2022 to 1 April 2025 | 46/2024, Art. VIII point 12 and Art. XI |
| 1 April 2025 | Article I of the Building Act applies, and its § 86 repeals 201/2022 | 25/2025, Art. IV and § 86 |
Section 86 names three amending acts of 201/2022: 205/2023, 272/2023 and 46/2024. No other amendment appears in that list.
Did the Construction Act repeal the 1976 building act?
No. The Spatial Planning Act 200/2022 Z. z. repeals act 50/1976 Zb. in its § 41 point 1. That point takes effect on 1 April 2025 (§ 43). Slov-Lex shows the last version of 50/1976 running from 15 March 2025 to 31 March 2025. The Spatial Planning Act is not repealed. Parliament passed it on the same day as the Construction Act and it applies today.
How does the 2022 act compare with the current Building Act?
The two acts share several procedure names. The table shows the headings of the 2022 text and the matching sections of the current act.
| Topic | Construction Act 201/2022 (repealed) | Building Act 25/2025 (current) |
|---|---|---|
| Main proceedings | Konanie o stavebnom zámere, § 37, ending in a "rozhodnutie o povolení stavby", § 38 | Konanie o stavebnom zámere, § 48 to 62, ending in a "rozhodnutie o stavebnom zámere", § 60 |
| Time limit for the decision | 15 days from a complete application, or from the settlement of a dispute (§ 38 ods. 3) | 30, 60 or 90 days from a complete application (§ 58) |
| Project check | Overenie projektu stavby, § 41, in 30 days | Overenie projektu stavby, § 65, in 30 days |
| Levels of project documentation | Building intent, building project and detailed design (§ 3 ods. 2) | Adds a project for notification (§ 9 ods. 1) |
| Final inspection | Kolaudácia stavby, § 44 to 46, ending in a kolaudačné osvedčenie | Kolaudácia, § 66, ending in a kolaudačné osvedčenie, § 67 |
| Small buildings | Ohlásenie drobných stavieb, § 48 | Ohlásenie, § 63 |
| Unpermitted buildings | Preskúmanie spôsobilosti nepovolenej stavby na prevádzku, § 63 | Preskúmanie spôsobilosti under the old rules, if the owner applies by 31 March 2029, § 84 ods. 7 |
| Start date | 1 April 2025 after act 46/2024 | 1 April 2025 for Article I |
The table compares headings, sections and the periods named. It does not compare the full content of each rule. The wording of individual rules can differ.
What is the difference between the old and the new building law?
Three acts matter. Act 50/1976 Zb. held the procedures until 31 March 2025. Act 50/1976 stayed valid until that date, so the Construction Act did not replace it. The Building Act 25/2025 replaced the 1976 procedures from 1 April 2025. Section 84 ods. 11 of the Building Act maps the old names to the new ones. Territorial proceedings became konanie o stavebnom zámere, building proceedings became overenie projektu stavby and final inspection proceedings became kolaudácia. See building intent proceedings.
Why does the 2022 act still appear in documents?
Articles and project files from 2022 to 2025 may cite it. Several terms in the current act, such as building intent proceedings, already appear in the 2022 text. A reference to 201/2022 in an old document is a reference to a repealed act. Do not confuse the title "zákon o výstavbe" with the current act. The current act is titled "Stavebný zákon".
A case started by 31 March 2025 continues under the rules valid until that date (§ 84 ods. 4 of the Building Act). Slov-Lex shows act 50/1976 valid until that date.
Which act applies to a project now?
The Building Act applies. A new building needs a building intent decision unless the Building Act says otherwise (§ 18 ods. 2). Notified small buildings and routine maintenance follow separate rules in the same section. Act 243/2026 Z. z. amends the Building Act from 1 January 2027. It does not revive the Construction Act. See building intent decision, building permit and builder-developer.
Frequently asked questions
- What was the Construction Act 201/2022?
- It was a Slovak act of 2022 on building procedures, titled "zákon o výstavbe". Parliament passed it on 27 April 2022. The Building Act 25/2025 Z. z. repealed it in § 86. Slov-Lex lists no consolidated version.
- Is the Construction Act 201/2022 in force?
- No. Section 86 of the Building Act 25/2025 Z. z. repeals it, and Article I of that act applies from 1 April 2025. That is the day 201/2022 was due to start.
- What replaced the Construction Act 201/2022?
- The Building Act, Act 25/2025 Z. z., replaced it. Its title is "Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon)" and it applies from 1 April 2025.
- Is "zákon o výstavbe" the current building act?
- No. The title "zákon o výstavbe" belongs to the repealed act 201/2022 Z. z. The current act is the Stavebný zákon, Act 25/2025 Z. z.
- Did the Construction Act repeal the 1976 building act?
- No. The Spatial Planning Act 200/2022 Z. z. repeals act 50/1976 Zb. in its § 41 point 1, effective 1 April 2025. Its last version ran from 15 March 2025 to 31 March 2025.
- Which act do I cite for a current project?
- Cite the Building Act, Act 25/2025 Z. z., in the version in force. Cases started by 31 March 2025 may still follow the old rules (§ 84 ods. 4).
Sources
- Zákon č. 201/2022 Z. z. o výstavbe (zrušený) · Národná rada Slovenskej republiky, Slov-Lex · § 1, § 3, § 37 to 48, § 63, § 66
- Zákon č. 201/2022 Z. z. History of the act · Slov-Lex, Ministerstvo spravodlivosti SR
- Zákon č. 46/2024 Z. z., ktorým sa mení a dopĺňa zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon) v znení neskorších predpisov a ktorým sa menia a dopĺňajú niektoré zákony · Národná rada Slovenskej republiky, Slov-Lex · Čl. VIII bod 12, Čl. XI
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 9, § 18, § 48 to 67, § 84, § 86, Čl. IV
- Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon) · Federálne zhromaždenie ČSSR, Slov-Lex
- Zákon č. 200/2022 Z. z. o územnom plánovaní · Národná rada Slovenskej republiky, Slov-Lex · § 41 bod 1, § 43