Extension of a building intent decision
An extension is a change of a building intent decision that adds up to two years of validity, within seven years in total.
What is an extension of a building intent decision?
An extension is a change of a building intent decision that lengthens the time the decision stays valid.
The authority (správny orgán) may change a building intent decision in four listed cases (§ 62 ods. 1). One is the extension of its validity. The others are a change of builder and a change of the construction period or of the duration of a temporary structure. The last is the addition of an underground electronic communications line to a linear structure.
Act 25/2025 Z. z. has no building permit. The extension applies to the decision on the building intent. The validity rules that it extends are in the page on validity of a building intent decision.
How long can the validity be extended?
The authority extends the validity by up to two years per request. It may extend more than once. The total validity with all extensions may not exceed seven years (§ 62 ods. 3).
| Rule | Value | Source |
|---|---|---|
| Time added by one extension | Up to 2 years | § 62 ods. 3 |
| Number of extensions | Repeated extension is allowed | § 62 ods. 3 |
| Maximum total validity | 7 years | § 62 ods. 3 |
| Not covered by the 7-year limit | Linear structures, nuclear installations, structures related to a nuclear installation | § 62 ods. 3 |
The act does not say from which day the seven years count. A calculation from § 62 ods. 3 shows the effect, if the seven years include the original two. After two extensions of two years the decision has run six years. A third extension can then add one year at most.
When must I apply for the extension?
You must file the request before the validity period ends (§ 62 ods. 3). The act gives no extension after expiry.
From the day you file until the decision on the request becomes final, the validity period does not run (§ 62 ods. 3). Filing early therefore does not use up validity. Section 62 sets no separate deadline for the office to decide.
Without a request the decision lapses on the normal dates. The periods are two years for most structures and three for linear and reserved structures. They are one year for an information construction and an assembled product (§ 61 ods. 1).
Which opinions does the office need before it extends?
The office needs a new binding opinion (záväzné stanovisko) of the spatial planning authority for the area. It also needs a new binding statement (záväzné vyjadrenie) of the affected legal person, for example a utility. It does not need them if the information system already holds updated data on the affected area (§ 62 ods. 4).
Who takes part and who decides?
The parties to the proceedings are the builder, the owner of the structure and the owner of the plot (§ 62 ods. 9). The act gives the decision to the administrative authority (správny orgán, § 62 ods. 1 and 3). Ask the building office that issued your decision where to send the request.
Can I appeal if the office refuses?
The act bars an appeal against a decision on a change of a building intent decision (§ 62 ods. 8). Only the change that adds an underground electronic communications line is open to appeal. The act does not say separately whether a refusal of your request counts as such a decision. Ask the office before you rely on an appeal. See appeal against a decision.
Does the extension also cover the project verification?
No. Section 62 ods. 1 lists the building intent decision only. The verification clause (overovacia doložka) lapses if work has not started within two years of its issue. The authority may set a longer period (§ 65 ods. 6).
The building intent decision loses validity on the day the clause does (§ 61 ods. 1). If you hold a clause, plan the start of work for the clause deadline.
Can I extend a permit issued before April 2025?
Act 25/2025 keeps the legal relations that old decisions created (§ 84 ods. 1). A period that began under the old rules keeps running (§ 84 ods. 3).
Under the repealed Act 50/1976 Zb., a building permit (stavebné povolenie) lost validity after two years without a start of work. The office could set a longer period (§ 67 ods. 2). The old act also knew a decision on the extension of its validity (§ 69 ods. 1).
Section 84 ods. 5 and 6 send a request for a change of decision, filed after 31 March 2025, to the old rules. This applies where an old territorial decision exists, or where an old building permit exists and no territorial decision applied. The act does not say whether an extension request counts as a change of decision. Ask the building office.
What changes in 2027?
Act 243/2026 Z. z. amends § 62 from 1 January 2027. It removes the duration of a temporary structure from § 62 ods. 1 písm. c. It adds a new ground in písm. e, a change for deviations from the verified project (Article I, points 131 to 133). No point amends the extension rules in § 62 ods. 3 and 4.
Frequently asked questions
- What is an extension of a building intent decision?
- It is a change of the decision that lengthens its validity. The authority may grant it on the request of the builder, filed before the validity ends (§ 62 ods. 1 písm. b, ods. 3).
- How long can the validity be extended?
- By up to two years per request, repeated if needed. The total validity with all extensions may not exceed seven years. The limit does not apply to linear structures and nuclear installations (§ 62 ods. 3).
- Do I have to apply before the validity ends?
- Yes. The request must be filed before the validity ends. From the day of filing until the decision on the request becomes final, the validity period does not run (§ 62 ods. 3).
- Which opinions does the office need for an extension?
- A new binding opinion of the spatial planning authority and a new binding statement of the affected legal person. They are not needed if the information system already holds updated data on the area (§ 62 ods. 4).
- Does the extension also cover the project verification?
- No. Section 62 ods. 1 lists only the building intent decision. The verification clause lapses after two years without a start of work, unless the authority set a longer period. The decision lapses with it (§ 65 ods. 6, § 61 ods. 1).
- Can I extend a building permit from before April 2025?
- Old decisions stay in force and their running periods continue (§ 84 ods. 1 and 3). The act does not say if an extension request falls under the old or new rules (§ 84 ods. 5 and 6). Ask the building office.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 61, 62, 65, 84
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 131 to 136
- Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon), repealed · Slovenská národná rada, via Slov-Lex · § 67 ods. 2, § 69 ods. 1