Change before completion (zmena stavby pred dokončením)
A change before completion is a change to a building during construction that departs from the verified project and must be handled under § 43.
What was a change of a building before completion?
A change before completion is a change to a building during construction that departs from the verified project and must be handled under § 43.
Under the old act, the building office could permit a change of a building before its completion. It did so in justified cases, on the builder's application (§ 68 ods. 1 of Act 50/1976, text of 15 March 2025). The office discussed the change with the parties and decided. The rules of the building proceedings applied (§ 68 ods. 2).
That permit no longer exists as a separate procedure for new cases. This page keeps the old name, because people still search for it.
Does Act 25/2025 still have a permit for it?
No. The act mentions "povolenie na zmenu stavby pred dokončením" only in its transition rules (§ 84 ods. 5, 6, 12, 13). The term mapping in § 84 ods. 11 gives it no successor. The act handles deviations in § 43 and by verification of a change of the project.
In the new act, "zmena dokončenej stavby" means an extension, an add-on or a built-in structure (§ 5 ods. 1). That is another topic.
The old rules still apply in one case. Your building may have a zoning decision or a building permit under the old act. Then an application for a change before completion, filed after 31 March 2025, still follows the old rules (§ 84 ods. 5, 6).
| Situation | Route | Source |
|---|---|---|
| Deviation within the decision on the building intent and the conditions of the binding opinions and statements | Extraordinary control inspection. The designer marks the change and the site manager records it | § 43 ods. 2 |
| Deviation that cannot be permitted that way | The office decides on verification of the change of the project or on a new building-intent procedure | § 43 ods. 3 |
| Verification of a change of the project | Rules of project verification apply, with 30 days for the office | § 65 ods. 2, 7 |
| Building with an old zoning decision or an old building permit | Old rules for the application for a change before completion | § 84 ods. 5, 6 |
What can you change without a new decision?
Before the work starts, the builder may call an extraordinary control inspection when work would deviate from the verified project. The site manager, the designer or the supervising person may propose it (§ 43 ods. 2).
The office can handle the deviation on site if it does not conflict with the decision on the building intent. It must also respect the conditions of the binding opinions and binding statements. Then three things happen.
- The designer marks the deviation in the project of the building.
- The site manager lists it in the minutes of the inspection.
- The site manager records it in the construction diary (§ 43 ods. 2).
The site manager, the designer, the supervising person and the office employee sign the minutes. The minutes name the agreed change (§ 43 ods. 4). If the office did not attend, the builder sends it the minutes. The office approves them within three days and records this in the information system (§ 43 ods. 3).
When does a change need verification?
Sometimes the deviation cannot be permitted on site. Then the office decides that the change needs either verification of the changed project or a new building-intent procedure (§ 43 ods. 3). Verification of a change follows the rules of project verification (§ 65 ods. 7).
- The office has 30 days to verify (§ 65 ods. 2).
- It compares the changed project with the decision on the building intent and with the conditions of the binding opinions and statements (§ 65 ods. 3).
- It issues a verification clause for the change. The clause names the period of its validity (decree 60/2025, § 17).
- Annex 6 of the decree holds the form of the application (§ 4 ods. 6).
The state fee for verification of a change of a project during construction is 50 % of the verification fee (položka 59 písm. b bod 7 of Act 145/1995). The act gives no further test for choosing between the two routes. The office decides in each case.
When does a change need a new building-intent procedure?
A new procedure follows when the office decides that the change cannot be permitted on site (§ 43 ods. 3). You cannot fix such a change by changing the decision. The act lets the office change the decision on the building intent for four reasons only (§ 62 ods. 1).
- a change of the builder
- an extension of its validity
- a change of the construction period or of the duration of a temporary building
- the addition of a public communication line to a linear structure
A new design is not on the list. Read the decision on the building intent and the building intent proceedings for the procedure itself.
From 1 January 2027 the list gets a fifth reason: deviations from the verified project that cannot be permitted under § 43 ods. 2 (Act 243/2026, Čl. I bod 133). The state fee for a decision on a change of the building intent is 150 euro (položka 59 písm. g of Act 145/1995).
Is a change a notification?
No. A notification (ohlásenie, § 63) comes in advance, for alterations and minor structures. The office verifies the project for notification (§ 63 ods. 1, 6). The act has no notification for a change of a project that the office already verified. See minor structure notification.
Who does what when a change comes up?
| Person | Duty | Source |
|---|---|---|
| Designer | Attends the inspection that the builder called because of a change of the project or a swap of products or systems | § 35 ods. 7 písm. a |
| Designer | Asks the builder and the site manager to remove deviations at once, and writes unremoved deviations in the diary | § 35 ods. 7 písm. b |
| Designer | Is not liable for changes that nobody agreed with the designer | § 35 ods. 10 |
| Designer | Approves a change only after a fire protection specialist pre-approved the part it touches | § 35 ods. 11 |
| Contractor | Writes agreed changes into the diary and arranges the as-built documentation | § 32 ods. 3 |
| Site manager | Writes a final opinion that covers the agreed changes | § 37 ods. 2 |
| Builder | Takes part in control inspections | § 30 ods. 4 písm. a |
See author supervision for the architect's right to watch the work.
What if you build differently without approval?
Work against the verified project counts as unauthorised building work (§ 28 ods. 1). If a control inspection finds such work, the office calls on the builder to stop it and informs the building inspectorate (§ 43 ods. 6).
Kolaudácia stops when the building stands against the verified project (§ 66 ods. 8). Building against the verified project is an offence. The fine is 30 to 15 000 euro (§ 79 ods. 3 písm. a, ods. 6 písm. c).
The old act allowed the office to join the change to the kolaudačné konanie. This worked if the real building did not differ substantially from the verified documents (§ 81 ods. 4 of Act 50/1976). I found no such joining in Act 25/2025.
What changes from 1 January 2027?
Act 243/2026 amends § 43 from 1 January 2027 (Čl. I bod 105, 106). It is not current law today.
- An extraordinary inspection can handle a deviation on site only if the rights of the land owner and the building owner stay within the decision.
- The builder can instead show the verified consent of the land owner.
- The office approves the minutes within seven working days instead of three days.
Frequently asked questions
- Is a change of a building before completion still possible in 2026?
- Yes, in the form of § 43. The old permit for a change before completion survives only for buildings with an old zoning decision or an old building permit (§ 84 ods. 5, 6).
- Is a change before completion a new building intent procedure?
- Only when the office decides so. A deviation that you cannot handle on site needs either verification of a changed project or a new building-intent procedure (§ 43 ods. 3).
- Can I make a small change without asking the office?
- You can call an extraordinary control inspection. If the deviation does not conflict with the decision and the binding opinions, the designer marks it. The site manager records it (§ 43 ods. 2).
- How long does the verification of a change take?
- The office has 30 days (§ 65 ods. 2, applied by § 65 ods. 7). The fee is 50 % of the verification fee (položka 59 písm. b bod 7 of Act 145/1995).
- Does a change before completion affect kolaudácia?
- Yes. Agreed changes go into the diary and the as-built documentation. The office stops kolaudácia if the building stands against the verified project (§ 66 ods. 8).
- Is a change a notification?
- No. Notification (ohlásenie) is for alterations and minor structures before work starts (§ 63). The act has no notification for a change of an already verified project.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 5, § 28, § 30 ods. 4, § 32 ods. 3, § 35 ods. 7, 10, 11, § 37 ods. 2, § 43, § 62 ods. 1, § 63, § 65, § 66 ods. 8, § 79, § 84 ods. 5, 6, 11
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 105, 106, 133
- Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon) · Slov-Lex · § 68, § 81 ods. 4
- Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby (č. 60/2025 Z. z.) · Úrad pre územné plánovanie a výstavbu Slovenskej republiky, via Slov-Lex · § 4 ods. 6, § 17
- Zákon č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · položka 59 písm. b bod 7, písm. g