Building completion (dokončenie stavby)
Building completion is the stage when construction work ends and the contractor hands the building over, before kolaudácia starts.
What is building completion?
Building completion (dokončenie stavby) is the stage when construction work ends and the contractor hands the building over to the builder.
Act 25/2025 does not define completion as a legal status and names no completion certificate. It speaks of a completed building (dokončená stavba, § 66 ods. 1) and of a building that is stavebne dokončená, meaning finished in construction terms (§ 66 ods. 4 písm. a). The act decides when you may use the building. Permanent use starts only after kolaudácia (final inspection), which ends with the occupancy certificate (kolaudačné osvedčenie). The handover itself is a matter of contract. See building handover.
What must the contractor and the builder do at completion?
The act gives each side duties around the end of the work.
- The contractor prepares the finished building for a control inspection and invites the designer and the builder (§ 32 ods. 2 písm. k).
- The contractor hands the building and its documentation to the builder. The contractor records the handover in the information system (§ 32 ods. 2 písm. l).
- When the contractor calls for it, the builder inspects the completed building and takes it over (§ 30 ods. 4 písm. b).
- The site manager keeps the construction diary available from the first day of the site until the day of handover (§ 39 ods. 1).
- The contractor writes agreed changes against the verified project into the diary. The contractor also arranges the as-built documentation for kolaudácia (§ 32 ods. 3).
- Today the site manager also writes a final opinion. It confirms that the finished building follows the verified project, including agreed changes (§ 37 ods. 2, § 10 ods. 3).
Does the building office approve completion?
No. The office acts only in kolaudácia. At the inspection it finds out whether the building is stavebne dokončená, with induced works and access. It also finds out whether the building is fit for operation and safe use according to the verified project (§ 66 ods. 4 písm. a). If the building is fit for operation, the office issues the occupancy certificate (§ 66 ods. 7).
What happens between completion and kolaudácia?
The periods below are the same as on the page about the building permit timeline. The act sets no total period for the whole sequence.
| Step | Who | Period | Source |
|---|---|---|---|
| Handover and take-over of the building | Contractor and builder | The act sets no period | § 30 ods. 4 písm. b, § 32 ods. 2 písm. l |
| Proposal for kolaudácia with attachments | Builder | The act sets no period | § 66 ods. 2 |
| Notice of the date of the inspection | Office | Within 7 working days of the complete proposal | § 66 ods. 3 |
| Inspection of the building | Office | Within 30 days of the notice | § 66 ods. 3 |
| Occupancy certificate, if the building is fit for operation | Office | Within 15 days of the inspection | § 66 ods. 7 |
The final inspection is the visit in step four.
Which documents does kolaudácia need?
The proposal for kolaudácia carries attachments, depending on the type of building (§ 66 ods. 2). The table shows the list for 2026.
| Attachment | § 66 ods. 2 |
|---|---|
| Construction diary | písm. a |
| Final opinion of the site manager | písm. b |
| As-built documentation | písm. c |
| Survey documents from setting out the building, control protocol of the position measurement and the geometric plan that updates the cadastre | písm. d |
| Protocol of handover and take-over. The office may waive it in justified cases | písm. e |
| Evaluation protocol of trial operation, if the office permitted trial operation | písm. f |
| Test results of building product samples taken on site | písm. g |
| Results of measurements and inspections of reserved technical equipment, with proof that it can run safely | písm. h |
| Survey of the finished building as built | písm. i |
| Energy certificate, if the building must have one | písm. j |
| The binding opinions of affected authorities and the binding statements of affected legal persons that you obtained before the proposal | písm. k |
| Proof of payment of the local development fee, if the municipality charged it | písm. l |
Does every building need kolaudácia?
No. The act requires kolaudácia for three things. These are a new building, a change of a completed building and a terrain adjustment that needed a decision on the building intent. Buildings and alterations that need only a notification do not need it. The exception is an alteration that changes the use of the building (§ 66 ods. 1).
Can you move in before kolaudácia?
Not for permanent use. You may put a completed building into permanent use only after kolaudácia (§ 66 ods. 1). Using a building before the occupancy certificate is an offence (§ 79 ods. 2 písm. e and ods. 3 písm. c). The fine is 30 to 3 000 euro under ods. 2 and 30 to 15 000 euro under ods. 3 (§ 79 ods. 6 písm. b and c).
The act gives two temporary routes. Both need a decision of the office.
- Trial operation lets you run a finished building to test its function. It can last up to 24 months, and up to four years with extensions (§ 69 ods. 1, 4).
- Early use lets you use a building or a separate part of it before it is fully finished, if this does not endanger the completion. It can last up to 12 months, and up to five years with extensions (§ 70 ods. 1, 4). The office decides within 30 days of the application (§ 70 ods. 3).
Does completion start the warranty period?
The Civil Code links the warranty period to the takeover, not to the occupancy certificate. For a contract for work on a building, the warranty period is three years. It runs from the day the client should have taken over the building (§ 646 ods. 3 of Act 40/1964). Act 25/2025 sets no warranty period. Read your contract and see warranty period.
What changes from 1 January 2027?
Act 243/2026 amends § 66 and § 67 from 1 January 2027 (Čl. I bod 149 to 162). It is not current law today. The numbers of paragraphs inside § 66 shift. The main changes are these.
- Kolaudácia applies to a new building, a change of a completed building, and an alteration or maintenance that needed a decision on the building intent. The office may waive it for notified works that it sent into the intent procedure.
- The final opinion of the site manager leaves the list of attachments. The handover protocol becomes a record of handover and take-over. It contains the contractor's declaration that the building follows the verified project.
- At kolaudácia the office does not judge the completion of induced works or access works, unless the decision made them a condition. It may waive such a condition if safe use and safe access are secure.
- A building built in stages can have a kolaudácia for each stage, and the certificate lists all purposes of use. No appeal lies against the certificate.
These points do not change the periods of 7 working days, 30 days and 15 days.
Frequently asked questions
- Is completion the same as kolaudácia?
- No. Completion is when the work ends and the contractor hands the building over. Kolaudácia (final inspection) is the procedure of the office that ends with the occupancy certificate (§ 66, § 67).
- How long does kolaudácia take?
- The office announces the date within 7 working days of a complete proposal. The inspection follows within 30 days of that notice. The certificate follows within 15 days of the inspection (§ 66 ods. 3, 7). The act sets no total period.
- Which documents do I need for kolaudácia?
- The attachments depend on the type of building. They include the construction diary, the as-built documentation, the survey documents and the energy certificate if the building needs one. You also attach the binding opinions you already have (§ 66 ods. 2).
- Can I live in the house before kolaudácia?
- Not for permanent use. Permanent use starts only after kolaudácia (§ 66 ods. 1). The office can permit trial operation or early use for a limited time (§ 69, § 70). Use without the certificate is an offence (§ 79).
- What follows after the occupancy certificate?
- You may use the building for the purpose in the certificate. A change of purpose needs a new kolaudácia (§ 45 ods. 2 písm. h). The certificate does not replace a permit to operate under other laws (§ 67 ods. 3). The office informs the affected authorities (§ 67 ods. 4).
- Does completion start the warranty period?
- The warranty period for a building is three years from the day the client should have taken it over (Civil Code § 646 ods. 3). It does not start with the occupancy certificate. Read the contract for other terms.
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 10 ods. 3, § 30 ods. 4, § 32 ods. 2 a 3, § 37 ods. 2, § 39 ods. 1, § 45 ods. 2, § 66, § 67, § 69, § 70, § 79 ods. 2, 3, 6
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I bod 149 až 162
- Zákon č. 40/1964 Zb. Občiansky zákonník · Slov-Lex · § 646 ods. 3