Validity of a building intent decision
A validity period is the time a building intent decision stays in force, two years from final status for most structures (§ 61).
What is the validity period of a building intent decision?
A validity period is the time that a building intent decision (rozhodnutie o stavebnom zámere) stays in force after it becomes final.
Act 25/2025 Z. z. has no building permit. Since 1 April 2025 the decision on the building intent is the main decision of the procedure. The act renamed the old territorial proceedings to proceedings on the building intent (§ 84 ods. 11). The validity rule is in § 61 ods. 1.
How long does a building intent decision stay valid?
The decision stays valid for two years from the day it becomes final. Some structures get a different period. The authority may also set a longer period in the decision (§ 61 ods. 1).
| Type of structure | Validity from the day the decision is final | Source |
|---|---|---|
| Most structures | 2 years | § 61 ods. 1 |
| Linear structure (líniová stavba) | 3 years | § 61 ods. 1 |
| Reserved structure (vyhradená stavba) | 3 years | § 61 ods. 1 |
| Information construction (informačná konštrukcia) and assembled product (zmontovaný výrobok) | 1 year | § 61 ods. 1 |
When does the validity period start?
The period starts on the day the decision becomes final (právoplatnosť), not on the day the office issues it (§ 61 ods. 1). Under the administrative procedure act (71/1967 Zb., § 52 ods. 1) a decision is final when no appeal can be filed against it.
A party can file an appeal within 15 days of notification (71/1967 Zb., § 54 ods. 2). A decision that a party can still appeal is therefore not yet final. Read more in appeal against a decision.
The office announces the decision in the same way as the start of proceedings. If there are more than 20 parties, or an environmental impact assessment came first, it uses a public notice (§ 61 ods. 2 and 3).
Must I start building within the validity period?
No. The act tests something else. The decision does not lose validity if you filed a request for project verification within the period (§ 61 ods. 1).
You file the request with the authority that issued the decision. The authority has 30 days to verify the project (§ 65 ods. 1 and 2). If the proceedings covered the building intent together with the project, the office verifies the project when it issues the decision. This does not apply if the proceedings show that the project needs more work (§ 65 ods. 2).
Plan the verification request before the period ends. The act gives one other way to keep the decision in force, an extension.
How long is the verified project valid?
The verification clause (overovacia doložka) loses validity if work has not started within two years of its issue. The authority may set a longer period (§ 65 ods. 6).
When the clause loses validity, the building intent decision loses validity on the same day (§ 61 ods. 1). The two-year clock after verification therefore decides how long the whole approval lasts.
A structure that needs only a notification (ohlásenie) follows a different rule. Work may start within three years of the verification of the notified project (§ 63 ods. 10). See minor structure notification.
Can I extend the validity period?
Yes, if you apply before the period ends. The authority extends it by up to two years per request. The total with all extensions may not exceed seven years. The seven-year limit does not apply to linear structures and nuclear installations (§ 62 ods. 3). The page on extension of a building intent decision gives the detail.
What happens if the decision expires?
The act describes no remedy after expiry. An extension request must reach the authority before the period ends (§ 62 ods. 3). If the period has already passed, ask the building office what it needs from you.
Does the decision pass to a new owner?
The decision binds the legal successors of the parties (§ 61 ods. 4). A legal successor of the builder can ask the authority to change the builder. The request needs a copy of the document that proves the transfer of rights and duties (§ 62 ods. 1 písm. a and ods. 2).
How long is a building permit from before April 2025 valid?
Under the repealed Act 50/1976 Zb., a building permit (stavebné povolenie) lost validity without a start of work within two years of finality. The office could set a longer period (§ 67 ods. 2, text valid until 31 March 2025).
Act 25/2025 keeps the legal relations that old decisions created (§ 84 ods. 1). A period that began under the old rules keeps running until it ends (§ 84 ods. 3).
What changes in 2027?
Act 243/2026 Z. z. amends Act 25/2025 from 1 January 2027. No point of its Article I rewrites § 61 ods. 1 or the extension rules in § 62 ods. 3 and 4. Article I does restructure § 65 on project verification, so look up the new paragraph numbers after that date. For the other deadlines see building permit timeline.
Frequently asked questions
- How long is a building intent decision valid?
- A building intent decision is valid for two years from the day it becomes final. The period is three years for linear and reserved structures. It is one year for an information construction and for an assembled product (§ 61 ods. 1).
- Do I need to start building within two years?
- No. The decision stays valid if you filed a request for project verification within the period. After verification, the clause lapses if work has not started within two years, unless the authority set a longer period (§ 61 ods. 1, § 65 ods. 6).
- When does the validity of the decision start?
- It starts on the day the decision becomes final (právoplatnosť), not on the day the office issues it (§ 61 ods. 1). A decision that a party can still appeal is not yet final (71/1967 Zb., § 52 ods. 1).
- How long is the project verification valid?
- The verification clause lapses if work has not started within two years of its issue, unless the authority set a longer period (§ 65 ods. 6). When the clause lapses, the building intent decision lapses on the same day (§ 61 ods. 1).
- Can I extend the validity of the decision?
- Yes. File a request before the period ends. The authority extends the validity by up to two years per request. The total may not exceed seven years, except for linear structures and nuclear installations (§ 62 ods. 3).
- How long is a building permit from before April 2025 valid?
- Under the old Act 50/1976 Zb. a building permit lost validity after two years without a start of work, unless the office set a longer period (§ 67 ods. 2). A period that began before 1 April 2025 keeps running (§ 84 ods. 3 of Act 25/2025).
Sources
- Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, via Slov-Lex · § 61, 62, 63, 65, 84
- Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon (promulgated 7 October 2026) · Národná rada Slovenskej republiky, via Slov-Lex · Čl. I, body 130 to 136, 143 to 148
- Zákon č. 71/1967 Zb. o správnom konaní (správny poriadok) · Národné zhromaždenie, via Slov-Lex · § 52 ods. 1, § 54 ods. 2
- Zákon č. 50/1976 Zb. o územnom plánovaní a stavebnom poriadku (stavebný zákon), repealed · Slovenská národná rada, via Slov-Lex · § 67 ods. 2