Designer of Record

A designer of record is the authorised person who prepares and answers for a building's project documents. Slovak law calls this person the projektant.

What is a designer of record in Slovakia?

A designer of record is the authorised person who prepares and answers for the project documents of a building. The building act uses neither "designer of record" nor "architect of record". The act is zákon č. 25/2025 Z. z. (Stavebný zákon). It calls this person the projektant (§ 35).

Only an authorised person may be a projektant (§ 35 ods. 4). The projektant works within the scope of that authorisation. If the projektant has no authorisation for one part of the documents, the projektant must engage a person who has it (§ 35 ods. 2). Project work (projektová činnosť) is a reserved activity in construction (§ 34 ods. 2 písm. a).

One exception exists. Documents for notified alterations, notified minor structures and simple structures are not a reserved activity (§ 34 ods. 4 písm. a). This does not cover an apartment building with more than three apartments or a building for public use. A person with a degree in architecture, construction, mechanical or electrical engineering may prepare those documents. So may a person with secondary vocational education in construction, mechanical or electrical engineering and three years of practice (§ 34 ods. 5).

Is every projektant an architect?

No. A projektant may be an authorised architect, an authorised landscape architect or an authorised civil engineer, each within their own authorisation (Zákon č. 138/1992 Zb. § 3, § 4 písm. b, § 4a písm. b, § 5). An authorised person is entered in the list kept for that profession (§ 3 ods. 1 to 4). Two chambers exist: Slovenská komora architektov and Slovenská komora stavebných inžinierov.

People search for "projektant a architekt" and "hlavný projektant". The act does not use "hlavný projektant". It uses the generálny projektant, who is described below.

What is the difference between a designer of record and a design architect?

The act names no separate "design architect" role. The projektant who prepares the documents also answers for them (§ 35 ods. 6).

The act does split supervision of the works. The projektant and the author of the architectural work can be different people.

SupervisionWhoWhat it checks
Dohľad projektantaProjektant (§ 35 ods. 10)Conformity of the works with the project
Autorský dohľadAuthor of the architectural work (§ 35 ods. 10)Conformity of the works with the author's design
Stavebný dozorPerson appointed by the builder-developer (§ 36 ods. 1)Progress of the works against the verified project and technical rules

What does the projektant prepare?

The projektant prepares the project documentation (projektová dokumentácia). The act names four stages (§ 9 ods. 1).

StageWhat it isWhat it serves
Stavebný zámerText and drawings of the urban, architectural and basic building solution, including fire safety and the siting on the land (§ 9 ods. 2)The basis for the building intent proceedings
Projekt stavbyText and drawings of the architectural and building-technical solution, with the technical, technological and energy equipment (§ 9 ods. 3)The basis for building the structure and for project verification
Projekt stavby na ohlásenieArchitectural and building-technical solution of a structure that needs only a notification (§ 9 ods. 4)The basis for building a notified structure
Vykonávací projektDetailed elaboration of the verified project (§ 9 ods. 5)The works on site. Required for a reserved structure

The content and scope of each document sit in decree 60/2025 Z. z. of the Office for Spatial Planning and Construction. The annex "Projekt stavby" is annex 17 (§ 6 ods. 4 of the decree). Every document names the building, the builder-developer, the design stage, the designer and the date (§ 6 ods. 11 of the decree). This page does not list the drawing sheets. Read the annex for them. Read about the implementation project for the last stage.

What is the projektant responsible for?

Section 35 ods. 6 lists the projektant's responsibilities. Among them:

  • the building intent, prepared to the builder-developer's requirements (písm. a)
  • the project of the structure, prepared to the decision on the building intent (písm. b)
  • conformity with the intended purpose and with the binding part of the spatial planning documents (písm. d)
  • a design that meets the basic requirements for structures over its whole life, including barrier-free use for public buildings (písm. f)
  • envelope materials chosen to reach at least the minimum energy performance requirements, as far as technically, functionally and economically possible (písm. j)
  • the internal technical, energy and technology equipment of the building (písm. k)
  • suitable building products for the intended use (písm. l)

In a passive house the choices under písm. j and k set the U-value of the envelope, the thermal bridges, the airtightness and the heat recovery ventilation.

The designer of the structural part also answers for the load-bearing design, including the static assessment of strength and stability. That part must contain a verifiable static calculation (§ 35 ods. 8). The projektant may approve changes to the project only after preliminary approval by the fire protection specialist for the part concerned (§ 35 ods. 11).

What does the projektant do during construction?

The act gives the projektant a right of supervision and two duties on site. The right is dohľad projektanta over conformity of the works with the project (§ 35 ods. 10). The builder-developer must ensure that this supervision takes place (§ 30 ods. 4 písm. d). For a reserved structure the supervision must be continuous (§ 30 ods. 5 písm. c).

The duties in § 35 ods. 7 are these. First, the projektant attends the inspection when invited because the project must change or because products or building systems are replaced. Second, the projektant requires the builder-developer and the site manager to remove deviations from the project at once. The projektant records in the construction diary the deviations that stay.

The contractor carries out the works. The projektant is not responsible for changes and deviations that the projektant did not approve (§ 35 ods. 10). The builder-developer must cooperate with the projektant when the works are checked against the verified project and at the occupancy approval (§ 30 ods. 4 písm. c). The building office invites the general designer to the occupancy inspection (§ 66 ods. 3).

What is a general designer (generálny projektant)?

A general designer is a projektant who also coordinates the designers of the parts and the other specialists (§ 35 ods. 3). The general designer ensures that the documentation is consistent and complete, and does the usual work before design, during construction and at the occupancy inspection.

If the result depends on several designers working together, the builder-developer ensures a general designer, unless the parties agree otherwise (§ 30 ods. 2 písm. d). The general designer answers to the builder-developer for the completeness and usability of the documentation. A designer of one part answers to the general designer for the completeness and factual correctness of that part (§ 35 ods. 5).

What liability does a designer carry?

Architects and engineers answer for damage they cause in connection with their work (Zákon č. 138/1992 Zb. § 12 ods. 1). This includes damage caused by their employees and by representatives acting under a power of attorney. An architect or engineer must take out liability insurance within ten days of entry in the list and tell the chamber (§ 12 ods. 2).

Architects and engineers authenticate the documents they prepare with the impression of their stamp. The stamp carries the title "autorizovaný architekt" or "autorizovaný stavebný inžinier" and a registration number. The chamber keeps a record of stamps (§ 14 ods. 1 to 3).

What changes from 1 January 2027?

Zákon č. 243/2026 Z. z. amends the act. Its Art. I applies from 1 January 2027. Three changes concern the designer.

  • Section 35 ods. 1 will read: the projektant is a person authorised to prepare project documentation or a part of it (Art. I point 95). Today the text says the projektant may prepare all stages.
  • A new § 34 ods. 6 removes the education requirement of § 34 ods. 5 for three kinds of work. They are the project of a notified minor structure that is not a building, alterations that leave the load-bearing structure alone, and exterior works (Art. I point 94).
  • The construction supervision person changes from "authorised" to "obliged" to carry out the tasks in § 36 (Art. I points 98 and 99).

Frequently asked questions

What does designer of record mean in Slovakia?
Slovak law has no term "designer of record". The equivalent is the projektant, an authorised person who prepares the project documents and answers for them (§ 35 of zákon č. 25/2025 Z. z.). An architect of record is a projektant who is an authorised architect.
Who can be a projektant?
Only an authorised person may be a projektant (§ 35 ods. 4). Authorised architects and authorised civil engineers qualify within their authorisation. Documents for notified alterations, notified minor structures and simple structures may also come from a person with the education in § 34 ods. 5.
Is a general designer the same as a chief designer?
The act knows the general designer (generálny projektant), not a chief designer. The general designer coordinates the designers of the parts and the specialists. The general designer answers to the builder-developer for the completeness and usability of the documentation (§ 35 ods. 3 and 5).
Does the projektant stay involved during construction?
Yes, in part. The projektant may supervise the works for conformity with the project, and the builder-developer must ensure that this supervision takes place (§ 35 ods. 10, § 30 ods. 4 písm. d). The projektant must attend an inspection when invited because the project must change (§ 35 ods. 7).
Is the projektant responsible for deviations from the project?
The projektant is not responsible for changes and deviations that the projektant did not approve (§ 35 ods. 10). The projektant must require removal of deviations and record in the construction diary those that stay (§ 35 ods. 7 písm. b).
Must a designer carry liability insurance?
Yes, an authorised architect or engineer must. The insurance contract is due within ten days of entry in the list and the chamber must be told (Zákon č. 138/1992 Zb. § 12 ods. 2).

Sources

  1. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 9, § 30, § 34, § 35, § 66
  2. Zákon Slovenskej národnej rady č. 138/1992 Zb. o autorizovaných architektoch a autorizovaných stavebných inžinieroch · Slovenská národná rada, Slov-Lex · § 3, § 4, § 5, § 12, § 14
  3. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, Slov-Lex · § 6 ods. 4, ods. 11
  4. Zákon č. 243/2026 Z. z., ktorým sa mení a dopĺňa zákon č. 25/2025 Z. z. Stavebný zákon · Národná rada Slovenskej republiky, Slov-Lex · Čl. I body 94, 95, 98, 99