Site plan / situation drawing

A site plan (situačný výkres) is a drawing that shows where a building stands on its plot, with the distances to boundaries and neighbouring buildings.

What is a site plan?

A site plan (situačný výkres, in practice situácia stavby) is a drawing in the project documentation. It shows a structure on its plot and in its surroundings. Decree 60/2025 Z. z. puts the site drawings in part C of the building intent, of the project of the building and of the execution project. The drawings carry the codes SIT.001 to SIT.005. A floor plan, a section and an elevation belong to part D, the documentation of the building objects.

Which site drawings does the decree list?

The decree describes each drawing by its content. The table shows the drawings of the project of the building (annex 17). The building intent (annex 15) and the execution project (annex 18) use the same first three.

CodeSlovak nameWhat the decree says it shows
SIT.001Situačný výkres širších vzťahovA larger area with the building, the plot boundary, the surrounding development and links to roads and utilities. It also shows protected interests and limits in the wider area. It is needed only if SIT.002 and SIT.003 cannot show these.
SIT.002Koordinačný situačný výkresThe current state of the area with the building, neighbouring buildings, plot and site boundaries, existing roads and utility networks. It shows the planned connections, green infrastructure, protection zones, any building to be removed and trees to be felled.
SIT.003Situačný výkres stavby na podklade katastrálnej mapyThe current state of the area with the building drawn in and the distances from the plot boundary and from surrounding buildings. The proposed buildings and objects are marked.
SIT.004Vytyčovací výkres alebo projekt vytyčovacej sieteThe set-out parameters of the building. For a reserved structure it is a project of the set-out network.
SIT.005Špeciálny situačný výkresAny other site drawing that the project needs.

In the building intent (annex 15) the staking drawing does not appear. SIT.004 there is the special drawing.

What distances does the site plan show?

SIT.003 shows the distances from the plot boundary and from the surrounding buildings (decree 60/2025, annexes 15, 17 and 18). The decree does not set the values. The minimum distances come from other rules, see building setback distances. SIT.002 adds the neighbouring buildings and the boundary of the construction site.

Which scale does a site plan use?

The decree sets no fixed scale for a site drawing. It requires SIT.002 and SIT.003 in a common scale. They use the cadastral map and the geodetic survey as the base (annexes 15, 17 and 18). The designer chooses the scale. The drawing frame shows the scale (decree § 6 ods. 11).

The scales in the decree belong to other drawings. The drawings of the building objects use 1:200 or 1:100 in the building intent (annex 15, part D). They use 1:100 or 1:50 in the project of the building and in the execution project (annexes 17 and 18, part D).

Which base map and survey does the site plan need?

SIT.002 and SIT.003 use the cadastral map and the geodetic survey of the original terrain, with height and position. An authorised geodesist and cartographer verifies the survey. The project of the building lists this survey as annex part E (decree 60/2025, annex 17). The geodetic survey and topographic survey pages explain the survey. The cadastre page explains the map.

How does the site plan change from the building intent to the execution project?

The building intent holds SIT.001 to SIT.003 and a special drawing (annex 15). The building intent shows the connection points to the networks as expected points. For the design stage before the building intent, see architectural study. For the pre-2025 name of these documents, see building permit documentation. The project of the building adds the staking drawing (annex 17).

In the execution project the site drawings give a more detailed coordination of parts of the building and of objects (annex 18, part C). They also cover paved areas, the shaping of the terrain and the grading of surfaces. They show how rainwater drains, soaks in or stays on the plot, and where green elements stand. Special site drawings can cover single objects, engineering structures or professions such as roads, utilities, technology and green areas. Sections and longitudinal profiles go with them.

What does the site drawing show for a structure that needs only a notification?

The project for notification has one site drawing, SIT.001 Situačný výkres stavby (decree 60/2025, annex 14). It shows the position of the structure on the plot. It also shows the distances from the boundaries with neighbouring plots and from neighbouring buildings. It uses the cadastral map as the base.

Who prepares the site plan?

The designer prepares the site plan as part of the project documentation (§ 35 ods. 1 of Act 25/2025 Z. z.). Only an authorised person can be a designer (§ 35 ods. 4). A geodesist provides the survey that the drawing uses. See designer of record. The builder submits the drawing in the information system with the rest of the documentation (§ 8 ods. 3).

What happens to the site plan after construction?

The documentation of actual execution (dokumentácia skutočného zhotovenia stavby) may be a copy of the verified project. The deviations are drawn in (decree annex 21). The site drawings take part in this record, see as-built documentation. The documentation is a basis for the occupancy approval (§ 10 ods. 4 of the Act).

Frequently asked questions

What is a situační výkres or situácia in a building project?
It is the site drawing that shows a structure on its plot. Decree 60/2025 Z. z. lists the site drawings SIT.001 to SIT.005 in part C of the building intent, the project of the building and the execution project.
What is a koordinačná situácia (koordinačný situačný výkres)?
It is drawing SIT.002 of the decree 60/2025 Z. z. It shows the current state of the area with the building and the neighbouring buildings. It adds the boundaries, the existing roads and utility networks and the planned connections. It uses the cadastral map and a verified geodetic survey.
What is the difference between a site plan and a floor plan?
A site plan shows the structure on its plot, with distances to boundaries and neighbouring buildings. A floor plan shows the layout of rooms inside the structure. The decree puts site drawings in part C and floor plans in part D.
What scale is a site plan drawn at?
The decree sets no fixed scale for site drawings. It requires a common scale for SIT.002 and SIT.003, on the cadastral map and the geodetic survey. The drawing frame shows the scale.
What is a katastrálny situačný výkres?
It is drawing SIT.003 in the decree, the site drawing of the structure on the base of the cadastral map. It shows the distances from the plot boundary and from surrounding buildings and marks the proposed buildings.
Does a small structure need a site plan?
Yes, if it needs a notification. The project for notification has one site drawing, SIT.001. It shows the position on the plot and the distances from the boundaries and neighbouring buildings (decree 60/2025, annex 14).

Sources

  1. Vyhláška Úradu pre územné plánovanie a výstavbu Slovenskej republiky č. 60/2025 Z. z. o štruktúre a prevádzke informačného systému územného plánovania a výstavby, o obsahu podaní a obsahu a rozsahu dokumentácie stavby · Úrad pre územné plánovanie a výstavbu SR, Slov-Lex · § 6 ods. 11, annex 14, 15, 17, 18, 21 (part C)
  2. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 8 ods. 3, § 10 ods. 4, § 35 ods. 1, 4