Taking a Plot Out of Agricultural Land

8 min read
The edge of a freshly surveyed building plot cut out of an arable field, with survey stakes and string lines, a strip of stripped topsoil heaped at one side and the field continuing beyond

Why is a “building plot” from an advert often still agricultural land?

The land-use plan and the cadastre answer two different questions. The municipal land-use plan sets the functional use of an area, that is, what it may serve. The cadastre records the land type, that is, what the plot is today. Part A of the property register sheet shows the area and the land type. It also shows whether the plot belongs to the built-up area (Act 162/1995, § 8). A plot can be designated for housing in the plan and still be listed as arable land or garden in the cadastre. Anyone may inspect the cadastre. The map and property register data online are free and informative (Act 162/1995, § 68 ods. 1 and 4).

Act 220/2004 on the protection and use of agricultural land defines agricultural land. It is land that the cadastre records as arable land, hop field, vineyard, orchard, garden or permanent grassland (§ 2 písm. b). It can be used for non-agricultural purposes only on the basis of a withdrawal decision (§ 17 ods. 1). People say “taking land out of the agricultural fund”. The act uses the word withdrawal. The whole plot choice is in the article How to choose a plot. Reading the plan is in the article How to read a municipal land-use plan.

Which land types in the cadastre are agricultural land?

The cadastre divides land into eleven types (Act 162/1995, § 9). Six of them are agricultural land.

Land type in the cadastreAgricultural land?What it means for building
Arable land, hop field, orchard, garden, permanent grasslandYesA withdrawal decision is needed before building, unless an exception applies (§ 17 ods. 1 and 2)
VineyardYesThe act protects it specially (§ 12 ods. 1 písm. b, § 17 ods. 5 písm. f, h). The application needs a municipal opinion and an expert opinion of the Central Control and Testing Institute in Agriculture
Built-up area and courtyard, other areaNoWithdrawal is not an issue. After withdrawal the cadastre changes the land type to other area (§ 17 ods. 7)

Dividing a field into smaller parcels does not change the land type. The cadastre changes a land type on the basis of a final decision, a binding opinion or an opinion. The agricultural land protection authority issues it (§ 12 ods. 1). A new parcel sold as a building plot can therefore still be recorded as arable land. Subdivision of land has its own page.

Is it enough that the land-use plan allows building on the plot?

No. A change of the land-use plan is only the first step. While a plan is in preparation, the agricultural land protection authority must agree to the draft before approval. At this stage that authority is the district office in the regional seat (§ 13 ods. 2, § 22 písm. c). The consent to a possible future use of the land for building does not withdraw the land. It is a basis for the later withdrawal decision. If the municipality has no plan, the same office can give consent to an individual proposal (§ 15 ods. 1). Such a consent is valid for three years, unless the office sets a longer period. It does not lapse if an application for withdrawal is filed in that period (§ 15 ods. 3).

The act gives the office grounds to refuse. Land can be used for building only in unavoidable cases and to a justified extent. The protection authority must protect land of quality groups one to four and vineyards (§ 12 ods. 1). The applicant must also consider an alternative site beyond the built-up boundary, with regard to the best soils (§ 12 ods. 2 písm. b). If the proposal does not meet these principles, the office gives no consent (§ 16 ods. 1, § 17 ods. 12). When you buy, ask whether the area of your plot already has consent from the land protection side, and on what conditions. Ask the municipality and the district office.

When is withdrawal not needed?

No withdrawal decision is needed for a plot of up to 1,000 m² inside the built-up boundary (§ 17 ods. 2 písm. b). Nor is it needed for a property of up to 25 m² built area in an allotment garden area of the plan (písm. c). Even then it is not a free pass. The agricultural land protection authority issues an opinion on the planned project (§ 17 ods. 3). For a house on a plot outside the built-up area, the exception in písm. b does not apply.

Use of land for a non-agricultural purpose for less than one year, including return to the original state, needs no withdrawal. You must still ask the office for an opinion before you start. It sets the conditions and the deadline to restore the land (§ 18 ods. 1 and 2). Temporary withdrawal lasts at most ten years, and the land is then recultivated to its original state (§ 17 ods. 4 písm. b).

Who decides on withdrawal and what goes with the application?

The district office in whose area the land lies decides on withdrawal (§ 17 ods. 1, § 23 písm. c). The district office in the regional seat decides on appeals (§ 22 písm. d). The administrative procedure code applies, unless the act says otherwise (§ 28 ods. 1). Section 17 sets no deadline for the decision, so ask the office about it. An application for permanent or temporary withdrawal must have these attachments (§ 17 ods. 5):

  • the consent under § 13 to 15,
  • the project documentation,
  • the topsoil stripping balance from a person with a completed second-cycle university degree in agriculture or natural science, specialising in soil science,
  • ownership data or, for a non-owner, a cadastre extract, and a copy of the cadastral map,
  • two copies of the land survey plan and the certificate of the soil-ecological unit (BPEJ),
  • the statements of the parties and of the affected authorities,
  • the binding opinion of the planning authority, except for strategic investments and strategic parks,
  • for a vineyard, the opinion of the municipality and the expert opinion of the Central Control and Testing Institute in Agriculture.

The decision states the purpose and the parcels. It approves the stripping balance and sets conditions to protect the land (§ 17 ods. 6). The withdrawn area can be the whole plot or just a part of it (§ 2 písm. j). The decision is valid only for the approved project (§ 17 ods. 8). It lapses if the land is not used for the project within three years of the decision becoming final. The levy paid is not refunded (§ 17 ods. 10). The office sends the final decision to the cadastre. The cadastre changes the land type to other area within 60 days of receipt at the latest (§ 17 ods. 7). The final decision on permanent withdrawal is a basis for the decision on the building intent (§ 17 ods. 14). Plan for it early in the preparation schedule.

How much does withdrawal cost: the administrative fee and the levy?

These are the administrative fees in the Schedule of Administrative Fees (Act 145/1995, version from 1 November 2026).

ActFeeItem
Consent to a possible future use of agricultural land for building and other projectsEUR 15046
Decision on withdrawal of agricultural landEUR 5045 písm. b
Opinion on non-agricultural use of agricultural landEUR 544 písm. b

The withdrawal levy is a different payment. It is income of the state budget (§ 12 ods. 4 of Act 220/2004). It is paid once, within 30 days of the decision becoming final (Government Regulation 58/2013, § 3 ods. 2). The base rate depends on the quality group of the soil by its BPEJ code, and it is in the annex of the regulation. The rates are not listed here, so ask the district office to calculate the levy for each withdrawn part of the parcel. Functional irrigation equipment on the land raises the rate by 50%. Land that directly adjoins the built-up area of a municipality lowers it by 30% (§ 2 ods. 1 and 2). A late payment brings a penalty of 0.05% of the unpaid amount for each day started (Act 220/2004, § 12 ods. 4).

The levy does not apply, among other cases, to land under a residential building of up to 200 m² (Regulation 58/2013, § 4 písm. f). A residential building has at least half of its floor area for permanent living (Building Act, § 3 ods. 2). By its wording, the exemption covers the land under the building. Check with the district office whether it also covers other withdrawn areas, such as a driveway. For a vineyard the base rate is fixed per region. It is EUR 100 per m² in the Little Carpathian and Tokaj regions. It is EUR 60 per m² in the Nitra and South Slovak regions. It is EUR 40 per m² in the Central Slovak and East Slovak regions (§ 2 ods. 3).

What is topsoil stripping and who arranges it?

A person who withdraws land permanently must strip the humus horizon. The person must also ensure its economical and purposeful use, as the stripping balance says (Act 220/2004, § 12 ods. 2 písm. e). The balance holds a proposal for that use (§ 17 ods. 5 písm. c). The office approves it in the withdrawal decision itself (§ 17 ods. 6 písm. d). Until building starts, the person who withdrew the land must give it basic care. This means mainly control of weeds and self-seeded trees (§ 12 ods. 2 písm. j).

What is the risk if someone took the land without a decision?

If the office finds that land was taken without a withdrawal decision after 25 June 1992, it orders recultivation. If the land cannot be returned to its original state, the office decides how to settle the unlawful state. It then calls on the person who took the land to submit documents to settle the land type in the cadastre (§ 19 ods. 1). The levy applies to land taken without a decision too (§ 12 ods. 3). A misdemeanour can bring a fine of up to EUR 2,000 (§ 25 ods. 1 písm. e and ods. 4). If a plot has a paved area or a building without withdrawal, the seller should settle the problem before the transfer.

What should I check before I sign the contract?

Whom to askWhat to ask
Cadastre (property register sheet, cadastral map)Land type, register C or E, whether the plot belongs to the built-up area
MunicipalityFunctional use under the plan and the built-up boundary
District officeWhether a withdrawal decision exists, for what project, whether it is valid, whether consent exists for the area and what the BPEJ code is
SellerWho files the application and pays the levy, and whether land was taken without a decision
Surveyor and architectThe land survey plan of the withdrawn area and the project for the application

If the seller says “the withdrawal is done”, ask for the final decision. Ask what project it covers and whether it still applies (§ 17 ods. 8 and 10). If withdrawal is not done, agree in the contract who files the application, who pays the levy and what happens if the office refuses. Buildability of land also depends on these points. The office also refuses an application if access from a public road is not secured. It also refuses it if an affected legal person states that the building cannot connect to the utility networks (Building Act 25/2025, § 59 ods. 1 písm. e and f). See the articles A Plot With No Utility Connections and Protection Zones and Easements on a Plot.

Frequently asked questions

How long does the withdrawal procedure take?
Section 17 of the agricultural land protection act sets no deadline for the decision. The administrative procedure code applies, unless the act says otherwise (§ 28 ods. 1). Ask the district office for the current deadline. The application needs all attachments under § 17 ods. 5, so collect them first.
Can I apply for withdrawal if I do not own the plot yet?
Yes. The act allows an applicant who is not the owner. Instead of the ownership data, the applicant attaches a cadastre extract (§ 17 ods. 5 písm. e). The application also needs the statements of the parties. When you buy, agree who files the application and who pays the levy.
Do I need withdrawal for a building site or a temporary road?
For use shorter than one year, including return to the original state, you need no withdrawal. You do need an opinion of the district office first, with conditions and a deadline to restore the land (§ 18 ods. 1 and 2). Longer use is temporary withdrawal for at most ten years. The levy for temporary withdrawal is paid for each year started (Regulation 58/2013, § 3 ods. 3).
Can the district office refuse withdrawal?
Yes. If the application does not meet the principles of agricultural land protection, the office gives no consent to withdrawal (§ 17 ods. 12). The principles say that land can be used only in unavoidable cases and to a justified extent. They also say that land of quality groups one to four and vineyards must be protected (§ 12 ods. 1). The office also considers an alternative site beyond the built-up boundary (§ 12 ods. 2 písm. b).
Why is a vineyard a special case?
The act protects vineyards specially, in the same way as land of quality groups one to four (§ 12 ods. 1). A vineyard application needs a municipal opinion and an expert opinion of the Central Control and Testing Institute in Agriculture (§ 17 ods. 5). The base rate of the levy is EUR 40, 60 or 100 per m², by wine-growing region (Regulation 58/2013, § 2 ods. 3).
Who pays the levy, the buyer or the seller?
The act puts the duty to pay the levy on two persons. The first is the person who proposes the non-agricultural use (§ 12 ods. 2 písm. l). The second is the person who took the land without a decision (§ 12 ods. 3). In a purchase it can be either party, depending on who files the application. Agree it in the contract and ask the district office to calculate the levy.
Where do I find out whether a plot is agricultural land?
On the property register sheet. Its part A shows the area, the land type and whether the plot belongs to the built-up area of the municipality (Act 162/1995, § 8). Anyone may inspect the cadastre. The map and property register data are free on the cadastre access point and are informative (§ 68 ods. 1 and 4). If the land type is arable land, hop field, vineyard, orchard, garden or permanent grassland, it is agricultural land (Act 220/2004, § 2 písm. b).

Sources

  1. Zákon č. 220/2004 Z. z. o ochrane a využívaní poľnohospodárskej pôdy a o zmene zákona č. 245/2003 Z. z. · Národná rada Slovenskej republiky, via Slov-Lex · § 2 písm. b, c, j, § 12 ods. 1 až 4, § 13 ods. 2, § 15 ods. 1, 3, § 16 ods. 1, § 17 ods. 1 až 8, 10, 12, 14, § 18 ods. 1, 2, § 19 ods. 1, § 22 písm. c, d, § 23 písm. c, § 25 ods. 1, 4, § 28 ods. 1
  2. Nariadenie vlády Slovenskej republiky č. 58/2013 Z. z. o odvodoch za odňatie a neoprávnený záber poľnohospodárskej pôdy · Vláda Slovenskej republiky, Slov-Lex · § 1 ods. 2, § 2 ods. 1 až 3, § 3 ods. 2, 3, § 4 písm. f
  3. Zákon Národnej rady Slovenskej republiky č. 145/1995 Z. z. o správnych poplatkoch · Slov-Lex · Sadzobník správnych poplatkov, položky 44 písm. b, 45 písm. b, 46
  4. Zákon č. 162/1995 Z. z. o katastri nehnuteľností a o zápise vlastníckych a iných práv k nehnuteľnostiam (katastrálny zákon) · Národná rada Slovenskej republiky · § 8, § 9, § 68 ods. 1, 4
  5. Zákon č. 25/2025 Z. z. Stavebný zákon a o zmene a doplnení niektorých zákonov (Stavebný zákon) · Národná rada Slovenskej republiky, Slov-Lex · § 3 ods. 2, § 59 ods. 1 písm. e, f

Topic

  • Building plot