Contract for Work: What It Must Contain

8 min read
Illustration: a family house construction site at the shell stage with ceramic block walls and scaffolding, a pallet of blocks and a small cement mixer

Which code applies when a private person orders a house?

A contract for building a house can be governed by the Civil Code or by the Commercial Code. The Commercial Code governs relations between businesses when they concern their business activity (§ 261(1)). Other parties may choose it, but only in writing (§ 262(1) and (2)). A family building a house to live in is usually a consumer. A consumer is a natural person who does not act within their business or profession when making the contract (Civil Code § 52(4)). Provisions that protect the consumer always apply when they are to the consumer's benefit (§ 52(2)). A template line saying "the contract is governed by the Commercial Code" therefore does not take your protection away.

QuestionCivil CodeCommercial Code
When the price is paidAfter the work is finished, unless agreed otherwise. For work in parts or with significant costs, reasonable advances may be requested (§ 634(2))At the time agreed in the contract, otherwise the right to the price arises when the work is done (§ 548(1))
Price based on a budgetMay not be increased without the client's consent (§ 635(1))An increase is possible if the contract does not guarantee the budget is complete and the work was not foreseeable, or if it calls the budget non-binding (§ 547(2) and (3))
Damage to the unfinished buildingThe contractor is liable for damage to or destruction of the building until the client takes it over, unless the damage would have happened anyway (§ 647)For a building on the client's land, the client bears the risk of damage unless the contract says otherwise (§ 542(1))
Warranty periodThree years from the day the client was to take over the building (§ 646(3))The period in the contract or the warranty statement, running from handover of the work (§ 563, § 429(2)). Without a warranty, defects of a building must be reported within five years of handover at the latest (§ 562(2)(c))

The biggest difference is in damage to the building. As a consumer you rely on Civil Code § 647: until takeover the contractor bears the damage. The Commercial Code puts the risk of the unfinished house on the client's land on the client. That rule would reach you only under a contract that code governs, for example when the client acts in a business. Write into the contract who bears the risk of damage until handover and who insures the building.

What must a contract for work contain, and what belongs there as a precaution?

The legal minimum is short. The contractor must issue a written confirmation of the order stating the subject of the work, its scope, quality, price and completion time (Civil Code § 632). The Commercial Code requires an agreed price or at least a stated method of setting it (§ 536(3)). Everything else is a matter of agreement. For a contract for work on a family house, these are the main clauses:

  • Scope. A reference to the approved building design, a priced bill of quantities and a list of work the price excludes.
  • Price. Under a fixed-price contract the contractor does the work for the agreed price at their own risk (§ 631). If the price cannot be agreed as a fixed sum, it must at least be set by estimate (§ 636(1)).
  • Dates. Start, main stages and completion. The contractor must do the work according to the contract, properly and at the agreed time (§ 633(1)).
  • Your duties. The developer hands the contractor the approved building design, the decision on the building plan and the land for setting up the site (Building Act § 30(3)(b)). The contract should state what else you provide and by when.

How do you set up payments so you do not pay for work in advance?

Under the Civil Code the price is paid after the work is finished, unless the parties agree otherwise. For work in parts or with significant costs, the contractor may ask for reasonable advances (§ 634(2)). The law therefore allows payment in stages. Every progress payment should follow a finished and checked stage, not a date in the calendar. It helps to tie each invoice to a stage acceptance record also signed by your site supervisor or designer.

If the contract says the client may inspect the work at a certain stage, the contractor must invite the client in good time. Otherwise it must allow a later inspection and bear its costs (Commercial Code § 553(1) and (2)).

Retention: how much and until when?

Retention money is not a legal term. The provisions on the contract for work in the Civil Code (§ 631 to 656) and in the Commercial Code (§ 536 to 565) do not regulate it. It exists only when the contract agrees it. The contract should state its amount, what it covers and the exact condition for release, for example the removal of defects recorded at handover. Without a release condition, retention is only settled in a dispute.

Contractual penalty: what should it cover?

A contractual penalty is payable even when the breach causes no damage. It can be agreed only in writing, with a set amount or a method of setting it (Civil Code § 544(1) and (2)). Paying the penalty does not end the obligation unless the agreement says otherwise (§ 545(1)).

Templates often overlook two rules. Unless agreed otherwise, you cannot claim damages for the same breach on top of the penalty, and damage above the penalty only when this is agreed (§ 545(2)). Under the Civil Code the debtor does not pay the penalty if the breach was not their fault, unless the agreement says otherwise (§ 545(3)). The Commercial Code is stricter. Circumstances excluding liability do not affect the duty to pay the penalty (§ 300), and the claim survives withdrawal from the contract (§ 302).

Agree a penalty for late completion, late removal of a defect and late clearing of the site, at a rate you can explain by reference to your actual loss.

Which clauses in the contractor's template need a closer look?

If you are a consumer, the Civil Code prohibits unfair terms. These are provisions that cause a significant imbalance in the parties' rights and obligations to the detriment of the consumer (§ 53(1)). Such terms are void (§ 53(5)). This does not apply to individually negotiated terms. But unless the trader proves otherwise, terms are not considered individually negotiated (§ 53(1) and (3)).

Clause in the templateWhat the law treats as unfairCivil Code
The contractor may move dates or change terms by noticeA one-sided change of contract terms without a reason agreed in the contract§ 53(4)(i)
The price is adjusted to material prices at the time of deliveryA price set only at the time of performance, or an increase without the consumer's right to withdraw if the agreed price is substantially exceeded§ 53(4)(j)
The client pays invoices even during a dispute about defectsA duty of the consumer to meet all obligations even when the trader has not met theirs§ 53(4)(h)
The contractor's site manager decides when a stage is completeA right of the trader to decide that their performance complies with the contract§ 53(4)(o)
Only defects recorded at handover can be claimedExcluding or limiting the consumer's rights from liability for defects§ 53(4)(d)
A high penalty only for the client, for example for late paymentAn unreasonably high sanction on the consumer for failing to meet an obligation§ 53(4)(k)

A void clause does not mean a won dispute. It is cheaper to have it rewritten before signing.

When should you ask the contractor for a bank guarantee?

A bank guarantee arises from the bank's written statement in a letter of guarantee. In it the bank promises to pay the creditor up to a certain sum if the debtor fails to meet an obligation (Commercial Code § 313). These relations are governed by the Commercial Code regardless of who the parties are (§ 261(6)(e)). Unless the letter says otherwise, the bank cannot raise the debtor's objections and pays on the creditor's written request (§ 317).

For a house a guarantee makes sense for a large advance and as a substitute for retention. Watch the period of validity. If it is limited and the creditor does not notify the bank of its claims in writing within it, the guarantee lapses (§ 321(1)). A guarantee that ends before the warranty period covers less than it seems.

How does the contract deal with extra works and material you buy yourself?

With a price based on a budget, extra works can be charged only when the client approved them in writing or ordered them later in writing (Civil Code § 635(1)). Under the Commercial Code, if the parties agree to change the work but not its effect on the price, the price rises or falls by the difference in the scope of activity and in reasonable costs (§ 549(2)). The contract should therefore set a change procedure. It should require a description, a price from the unit rates in the bill, the effect on the schedule and signatures of both parties before the work starts.

If you buy tiles or windows yourself, the contractor must warn you of defects in the material and of unsuitable instructions (§ 637(1)). Under the Commercial Code you bear the risk of damage to such material until processing makes it part of the work (§ 540(1)). The contract should set its delivery date.

Why do the construction diary and the handover record matter?

The construction diary records the progress of work from taking over the site to handover of the building and is usually kept in electronic form (Building Act § 10(2)). The site manager keeps it and must allow entries by the developer, the designer and construction supervision (§ 39(1) and (2)). The contractor records agreed changes from the approved design in it (§ 32(3)). Agree that a diary entry without a signed amendment does not change the price.

At the end the contractor hands over the building with its documentation and records the handover and takeover of the building electronically in the information system (§ 32(2)(l)). The contract should state that the record lists defects, deadlines for removing them and the link to the retention. The date in the record is not a formality, because the warranty period runs from handover and takeover of the building (Civil Code § 646(3), Commercial Code § 563(1)).

What does an architect check in a draft contract?

This text is not legal advice, and in a disputed contract the last word belongs to a lawyer. An architect, though, sees whether the scope in the annex matches the design. During construction the developer must provide design supervision by the designer (Building Act § 30(4)(d)), and it only makes sense when the contract allows for inspections. When you read a draft, check:

  • whether the scope annex refers to the current version of the design and the bill of quantities,
  • whether the payment stages match states of the building that can be checked,
  • whether an inspection of structures before they are covered is agreed,
  • whether extra works are priced with unit rates from the bill.

How this service fits into the project stages and what it costs is covered in the article how much an architect costs.

Frequently asked questions

Does a contract for work on a house have to be in writing?
The provisions on the contract for work in the Civil Code (§ 631 to 647) and the Commercial Code (§ 536 to 565) do not prescribe a written form for the contract. The Civil Code does require the contractor to issue a written confirmation of the order stating the subject, scope, quality, price and completion time of the work (§ 632). A contractual penalty must also be agreed in writing (§ 544(2)), and so must approval of work outside the budget (§ 635(1)). For a house it is therefore sensible to have the whole contract and its annexes in writing.
What warranty period applies to a new house?
Under the Civil Code the warranty period for building work is three years from the day the client was to take over the building (§ 646(3)). The new Civil Code, Act No. 260/2026, taking effect on 1 July 2027 (§ 1920), sets five years (§ 1256(3)). Relations from contracts made earlier are governed by the previous rules unless the act provides otherwise (§ 1893(3)).
Can a court reduce a contractual penalty?
Yes. A court may reduce an unreasonably high contractual penalty, taking into account the value and importance of the secured obligation (Civil Code § 545a, Commercial Code § 301). Under the Commercial Code it may not go below the loss that arose up to the court decision (§ 301). A penalty therefore makes sense when its amount matches the loss the breach may cause you.
Can I inspect the firm's work during construction?
Yes. Under the Commercial Code the client may inspect how the work is being done and ask for removal of defects caused by poor workmanship (§ 550). The Civil Code provisions on the contract for work (§ 631 to 647) do not expressly regulate inspection during construction, so agree it in the contract. The Building Act also requires the developer to take part in inspections of the building (§ 30(4)(a)). It helps to bring your construction supervisor to them.
What if the firm cannot continue because it is waiting for me?
If the work needs your cooperation, the contractor may set you a reasonable period and, once it has passed without result, withdraw from the contract. It must have warned you of this consequence (Civil Code § 638(1)). If circumstances on your side delayed the contractor, it is entitled to reasonable compensation (§ 641(2)). Make product decisions by the dates the contract sets.
Can the contractor pass part of the build to another firm?
Under the Civil Code, whether the contractor must do the work in person depends on the contract and the nature of the work (§ 633(2)). Under the Commercial Code the contractor may entrust the work to another person unless the contract or the nature of the work says otherwise. It remains liable as if doing the work itself (§ 538). If a specific firm for the roof or windows matters to you, write it into the contract.
What if the firm hits a hidden obstacle during earthworks?
Under the Commercial Code the contractor must report without undue delay a hidden obstacle at the site that prevents the agreed way of working and propose a change to the work. Until agreement it may suspend the work. If the parties do not agree within a reasonable period, either of them may withdraw from the contract (§ 552(1)).

Sources

  1. Zákon č. 40/1964 Zb. Občiansky zákonník (consolidated version from 31.07.2026) · Slov-Lex · § 52, § 53, § 544, § 545, § 545a, § 631 to § 647
  2. Zákon č. 513/1991 Zb. Obchodný zákonník (consolidated version from 17.08.2026) · Slov-Lex · § 261, § 262, § 300 to § 302, § 313 to § 321, § 429, § 536 to § 565
  3. Zákon č. 25/2025 Z. z. Stavebný zákon (consolidated version from 01.11.2025) · Národná rada Slovenskej republiky, via Slov-Lex · § 10, § 30, § 32, § 39
  4. Zákon č. 260/2026 Z. z. Občiansky zákonník (version effective from 01.07.2027) · Slov-Lex · § 1256, § 1893, § 1920